Accidental beam losses and protection in the LHC - PowerPoint PPT Presentation

1 / 49
About This Presentation
Title:

Accidental beam losses and protection in the LHC

Description:

for the Working Group on Machine Protection. HB 2004 Bensheim ... Fast emittance growth: beam size explodes. Both. Can happen very fast ... – PowerPoint PPT presentation

Number of Views:81
Avg rating:3.0/5.0
Slides: 50
Provided by: Rudi65
Category:

less

Transcript and Presenter's Notes

Title: Accidental beam losses and protection in the LHC


1
Accidental beam losses and protection in the LHC
  • R.Schmidt and J.Wenninger
  • for the Working Group on Machine Protection
  • HB 2004 Bensheim

LHC parameters and associated risks Overview
accidental beam losses Aperture and accidental
beam losses Protection and redundancy Conclusions
2
Beam dump tunnel
LHC tunnel
3
Some numbers for 7 TeV
  • Momentum at collision 7 TeV/c
  • Beam intensity 2808 ? 1.1 ? 1011 protons per
    beam
  • Luminosity 1034 cm-2s-1
  • Dipole field at 7 TeV 8.33 Tesla
  • Typical beam size 200-300 µm
  • Energy stored in the magnet system 10 GJoule
  • Energy stored in one (of 8) dipole circuit 1.1
    GJoule
  • Energy stored in one beam 350 MJoule
  • Average beam power to compare with
  • high power accelerators, both beams
    some 10 kWatt
  • Instantaneous beam power for one beam 3.9
    TWatt
  • .during 89 µs
  • .corresponds to the power of 1700 nuclear power
    plants
  • Energy to heat and melt one kg of copper 700 kJ


4
Bunch intensities, quench and damage level
  • Intensity one pilot bunch 5?109
  • Nominal bunch intensity 1.1?1011
  • Batch from SPS (216/288 bunches at 450
    GeV) 3?1013
  • Nominal beam intensity with 2808 bunches 3?1014
  • Damage level for fast losses at 450 GeV 1-2?1012
  • Damage level for fast losses at 7 TeV 1-2?1010
  • Quench level for fast losses at 450 GeV 2-3?109
  • Quench level for fast losses at 7 TeV 1-2?106
  • Damage and quench assessment approximative,
    supported by experience in SPS and calculations
  • Further calculations and material tests at SPS in
    two weeks planned


5
Livingston type plot Energy stored in the beam
6
Failure scenarios and accidental beam losses
  • A large number of different mechanisms can cause
    accidental particle losses Classification of
    accidental beam losses according to time constant
    for the loss
  • Ultra fast beam losses (single turn or less)
  • to be avoided, beam dump block is the only
    element that can safely absorb the 7 TeV LHC beam
  • passive protection with collimators and beam
    absorber
  • Very fast beam losses (some turns to some
    milliseconds)
  • Fast beam losses (5 ms several seconds)
  • Slow beam losses (several seconds 0.2 hours)
  • active protection, by detecting failure and
    extracting the beams into beam dump block

7
Single turn accidental beam losses
  • Failure mechanisms
  • Failure of beam dump kicker (prefiring,
    asynchronous beam dump)
  • Failure of kickers for tune measurements and
    aperture exploration
  • During transfer and injection
  • failure of injection kicker
  • wrong trajectory or mismatch of beam energy
  • obstruction of beam passage
  • Recent studies on protection during transfer and
    injection of the beams from SPS at 450 GeV to the
    LHC (see H.Burkhardt)
  • Strategy for protection
  • Avoid such failures (systems with high
    reliability)
  • Block beam transfer from SPS to LHC if parameters
    are not correct (i.e. magnet current)
  • Beam trajectory after such failure is reasonably
    well defined
  • Passive protection rely on collimators and beam
    absorbers

8
Consequence of a failure scenario Full 7 TeV LHC
beam deflected into copper target
2808 bunches 7 TeV 350 MJoule
Copper target
2 m
Energy density GeV/cm3 on target axis
vaporisation
melting
Target length cm
collaboration with N.Tahir (GSI) et al.
9
Density change in target after impact of 100
bunches
Copper target
copper solid state
radial
100 bunches target density reduced to 10
collaboration with N.Tahir (GSI) et al.
Target radial coordinate cm
  • Energy deposition calculations using FLUKA
  • Numerical simulations of the hydrodynamic and
    thermodynamic response of the
  • target with two-dimensional hydrodynamic
    computer code
  • From this calculations one can estimate the
    longitudinal range of full beam in copper between
    10m and 40m

10
LHC Layout eight arcs (sectors with a length of
about 2300 m) eight long straight sections (about
700 m long)
IR5CMS
IR6 Beam dumping system
IR4 RF Beam instrumentation
IR3 Momentum Cleaning (normal conducting magnets)
IR7 Betatron Cleaning (normal conducting magnets)
IR8 LHC-B
IR2ALICE
IR1 ATLAS
Injection
Injection
Transfer Line
Transfer Line
11
  • Collimators for cleaning the beam halo
  • close to the beam between 5-10 ?
  • must be accurately adjusted (within a fraction
    of one ?)
  • position depends on optics and possibly on energy

IR5CMS
IR6 Beam dumping system
IR4 RF Beam instrumentation
IR3 Momentum Cleaning (normal conducting magnets)
IR7 Betatron Cleaning (normal conducting magnets)
IR8 LHC-B
IR2ALICE
IR1 ATLAS
Injection
Injection
Transfer Line
Transfer Line
12
  • Collimators for protection of equipment against
    single turn beam losses
  • shadow equipment downstream
  • must be adjusted (better than one s)
  • position depends on LHC operational mode
    (injection, energy ramp, ) and on optics

IR5CMS
IR6 Beam dumping system
IR4 RF Beam instrumentation
IR3 Momentum Cleaning (normal conducting magnets)
IR7 Betatron Cleaning (normal conducting magnets)
IR8 LHC-B
IR2ALICE
IR1 ATLAS
Injection
Injection
Transfer Line
Transfer Line
13
  • For protection of equipment against multiturn
    beam losses
  • all collimators limiting the aperture contribute
    to this function

IR5CMS
IR6 Beam dumping system
IR4 RF Beam instrumentation
IR3 Momentum Cleaning (normal conducting magnets)
IR7 Betatron Cleaning (normal conducting magnets)
IR8 LHC-B
IR2ALICE
IR1 ATLAS
Injection
Injection
Transfer Line
Transfer Line
14
  • Collimators for protection and cleaning of the
    low-beta insertions, mainly in IR1 and IR5
  • close to the beam about 10 ?
  • must be accurately adjusted (within about one ?)
  • mainly required during squeeze and for squeezed
    beams

IR5CMS
IR6 Beam dumping system
IR4 RF Beam instrumentation
IR3 Momentum Cleaning (normal conducting magnets)
IR7 Betatron Cleaning (normal conducting magnets)
IR8 LHC-B
IR2ALICE
IR1 ATLAS
Injection
Injection
Transfer Line
Transfer Line
15
Lifetime of the beam - for nominal intensity at
7 TeV
Accidental beam losses
16
Accidental multiturn beam losses
  • Closed orbit grows around the ring
  • Fast emittance growth beam size explodes
  • Both
  • Can happen very fast
  • Can be detected around the entire accelerator
  • Local orbit bump
  • cannot happen very fast
  • might be detected only locally
  • Protection Detect failure and dump beam
  • Detection, transmission to beam dump, and beam
    dump takes at least 3 turns 270 ?s


17
Multiple turn failures Magnet powering failures
  • Quench of superconducting magnets
  • Discharge of superconducting magnets switching a
    resistance into the circuit (after quench, or by
    accident)
  • Failure of magnet powering
  • For some magnets very fast beam loss (several
    turns) D1 normal conducting magnet
  • Electric short in the coil of a normal conducting
    magnet

18
Multiple turn failures Other failures
  • Aperture limitation in beam pipe (circulating
    beam)
  • Vacuum valve moves into beam
  • Collimator moves into beam
  • Other element moves into beam
  • Loss of beam vacuum
  • Failure in the RF system
  • Debunching of beam and number of protons in the
    abort gap could lead to single turn failure when
    beam is dumped
  • Operational failures
  • Combined failures, for example after Mains
    Disturbances (thunderstorm, )

19
Beam losses and aperture
  • The aperture of the LHC at 450 GeV is limited
    (about 7.5s, assuming closed orbit excursions4
    mm, beta-beating, .)
  • Critical operation at 7 TeV with squeezed optics
  • ?-function up to 4850 m in insertions IR1 and IR5
  • very strong low-? quadrupole magnets with orbit
    offset
  • normal conducting dipole magnets
  • superconducting dipole magnets
  • In general, particle losses first at collimators
  • Fast orbit changes are the most critical failures
  • collimators at about 6-9 ? from the beam
  • 1 of the beam would damage the collimators for
    fast beam loss

20
Critical apertures around the LHC (illustration
drawing)in units of beam size ? at 450 TeV
collimators (betatron cleaning)
collimators (momentum cleaning)
arc aperture down to about ? 7.5 ?
? 6-9 ?
aperture in cleaning insertions about ? 6-9 ?
aperture in cleaning insertions about ? 6-9 ?
IR1
IR2
IR3
IR4
IR5
IR6
IR7
IR8
21
Critical apertures around the LHC (illustration
drawing)in units of beam size ?
7 TeV and ? 0.55 m in IR1 and IR5
Triplet
Triplet
arc aperture about ? 50 ?
triplet aperture about ?14 ?
IR1
IR2
IR3
IR4
IR5
IR6
IR7
IR8
22
Most likely failures for fast losses
quenchesFailures leading to the fastest
multiturn losses D1 magnet
orbit mm
MB quench fast loss
Quench of - MQX - D2 - MB Powering Failure of
D1 normal conducting
D1 normalconducting very fast loss
D2 quench fast loss
MQX 2 quads quench fast loss
time seconds
V.Kain Diploma thesis 2001 / O.Brüning
Squeezed optics with max beta of 4.8 km All 4
quadrupole magnets (inner triplet MQX) quench ,
approximately Gaussian current decay with time
constant 0.2 s Powering failure for D1,
exponential current decay, time constant 2.5
s Quench of one MB, approximately Gaussian
current decay with time constant 0.2 s
23
Particles that touch collimator after failure of
normal conducting D1 magnets After about 13
turns 3109 protons touch collimator, about 6
turns later 1011 protons touch collimator
1011 protons at collimator
Dump beam level
V.Kain
HERA experience confirmes worries very fast beam
losses
24
Protection and redundancy what triggers a beam
dump?
  • Hardware diagnostics
  • Quench signal from Quench Protection System
  • Beam loss monitors at the collimators and other
    aperture limitations
  • Beam loss monitors in the arcs
  • Magnet current change monitors
  • Beam position change monitors
  • Fast beam current decay (lifetime) monitors

25
Hardware failure diagnostics
  • Vacuum valve leaving the OUT position (away
    from end switch)
  • Other movable devices leaving the OUT position
  • Powering failures detected by the power
    converter, requesting a beam dump (typical times
    in the order of 10 ms)
  • Failures of cooling for normal conducting magnets
  • Failure in the RF system
  • Anticipated failure in the beam dumping system
    (before it is too late), e.g. when 1 out of 15
    kicker is lost
  • Failure in critical beam absorbers and
    collimators

26
Hardware failure diagnostics
  • PLUS
  • Does not require collimators to have correct
    settings
  • If early enough, can dump the beam before
    particle losses
  • MINUS
  • For many type of failures the beam dump comes too
    late
  • Complexity of hardware not all failures are
    detected
  • Too many channels too many False Beam Dumps
  • Risk of including failures that would not lead to
    particle losses

27
Quench detection
  • Magnet starts to quench
  • Resistive Voltage across magnet gt 0.1 V
  • 10 ms quench detection
  • fire quench heater
  • requests energy extraction
  • requests a beam dump

The quench heaters become effective
3 ms the interlock system transmits the
request to the beam dump
300 ?s the beam dump kicker extracts beam
Magnet current starts to debypass magnet by diode

5 ms current starts to decay exponentially
28
Quench detection
  • PLUS
  • Does not require collimators to have correct
    settings
  • If early enough, beam gone before losses
  • Dumps beam for failures of the quench protection
    system
  • Does not reduce the availability of LHC Quench
    protection is always required. After a quench the
    beam must be dumped
  • MINUS
  • Only covers beam losses due to magnet quenches
  • Might be too late (being further analysed,
    efficiency depends on quench process, magnet
    field, beam loss pattern, etc)
  • Large complexity (several 1000 channels) good
    post mortem analysis required

29
Beam loss monitoring at aperture limitations
  • In general, collimators are limiting the aperture
  • Always true for beam blow up
  • Mostly true for orbit changes
  • Beam loss monitors at aperture restrictions
    continuously measuring beam losses
  • Losses are detected within less than a turn
  • After detection it takes 2-3 turns to extract all
    particles into beam dump block

30
Beam loss monitoring at aperture limitations
  • PLUS
  • Should capture (nearly) all types of accidental
    beam losses
  • Dumps the beam if there are really particle
    losses
  • Very fast (lt 100 ?s)
  • Limited complexity (some 100 channels)
  • Expected to be very reliable
  • MINUS
  • Does require collimators to have correct settings
    and defining the aperture
  • Does not catch beam losses in the arcs (for
    example, closed orbit bumps)
  • Random spikes might trigger beam dump
  • Setting of thresholds not obvious - if too low,
    False Beam Dumps if too high - risk of damage

31
Beam loss monitoring around the accelerator
  • Beam loss monitors continuously measuring beam
    losses
  • Together with the BLMs at aperture limitations,
    covers most of the LHC (all arcs)
  • Losses can be detected within less than a turn
  • After detection it takes 2-3 turns to extract all
    particles into beam dump block

32
Beam loss monitoring around the accelerator
  • PLUS
  • Dumps the beam if there are really particle
    losses
  • For failures leading to orbit changes and
    emittance growth
  • Detection can be made very fast (lt 100 ?s)
  • Does not require collimators to have correct
    settings
  • Catches failures that appear only in the arcs
    (for example, closed bump)
  • MINUS
  • Large complexity (some 1000 channels)
  • Could increase number of False Beam Dumps
  • Setting thresholds delicate balance between
    avoiding magnet quenches and avoiding False Beam
    Dumps

33
Magnet current decay monitoring for critical
magnets
  • Very fast detection of power converter / magnet
    failures
  • Monitors change of magnet current (Hall probes,
    voltage, )
  • Prototype quick and dirty gave promising
    results (M.Zerlauth)
  • Similar technique recently successfully
    implemented at HERA (M.Werner)
  • Should be possible to detect powering failures in
    less than one millisecond

34
Magnet current decay monitoring for critical
magnets
  • PLUS
  • Independent method to monitor failures in the
    powering system power converter fault /
    thunderstorm / short circuit in magnet / other
    problems
  • Does not require collimators to have correct
    settings
  • Can be made fast (lt 1ms)
  • Mainly for normal conducting magnets
  • MINUS
  • Needs to be demonstrated if practical (EMC, )
    wait for HERA experience
  • Setting of thresholds required could be
    delicate
  • Should be limited to a few electrical circuits
    with normal conducting magnets otherwise too
    complex

35
Beam position change monitors
  • If the orbit start to moves very fast, dump the
    beam
  • Fast orbit changes can be observed anywhere
    around the LHC
  • Observation for each beam, each plane, two
    monitors with 90 degrees phase advance in total
    8 BPMs
  • system with limited complexity
  • BPMs at location of high beta function, using the
    same monitors that are already required for
    machine protection (to ensure x lt 4 mm in
    the insertion IR6 for the beam dumping system)

36
Beam position change monitors thresholds
450 GeV fastest orbit movement during normal
operation by an orbit corrector
magnet Superconducting orbit correctors 2
mm/s 15 mm/s Normal conducting orbit
correctors 0.6 mm/s 1.7 mm/s 450 GeV if
the change of the orbit exceeds, say, some 10
mm/s corresponding to 0.01 mm/msec, there is
something wrong Detection of very fast orbit
drifts (IF dx/dt gt 0.1 mm/ms) OR (IF dx/dt
gt 1 mm/100ms) THEN beam dump 7 TeV if the
change of the orbit exceeds, say, some 1 mm/s
corresponding to 0.001 mm/msec, there is
something wrong (IF dx/dt gt 0.05 mm/ms) OR
(IF dx/dt gt 0.3 mm/100ms) THEN beam dump
numbers preliminary
37
Beam position change monitors
  • PLUS
  • Independent method to measure fast orbit drifts
    due to failures
  • Does not require collimators to have correct
    settings
  • Can be made fast (lt 1ms)
  • Beam dump before particles are lost
  • Limited complexity
  • MINUS
  • Is it practical ? False Beam Dumps ?
  • Setting of thresholds delicate
  • What to do during injection, during kicks for
    Q-measurements, to be studied
  • Only for beam orbit changes, not for emittance
    growth
  • Studies needed

38
Fast beam current decay monitoring
  • Very fast beam current monitor, could detect
    losses within short time
  • Measuring proton losses with, say, ?N / ?t
    1010 protons
  • Interlock condition
  • if (?N / ?t gt Nthreshold(E) 1010) THEN BEAM
    DUMP
  • ?t could be as short as one turn
  • Nthreshold decreases with energy to be always
    efficient
  • For start of LHC operation, when intensity is
    limited, resolution should be no problem
  • Challenge must be fast and accurate
  • First discussions with experts - looks promising

39
Fast beam current decay monitoring
  • PLUS
  • Independent method to measure beam losses
  • Does not require collimators to have correct
    settings
  • Fast for reduced accuracy (lt 1ms)
  • Slow for high accuracy (gt 10ms)
  • Limited complexity one instrument
  • MINUS
  • Needs to be demonstrated if practical
  • Setting of thresholds required
  • Not sufficient for all LHC operation modes and
    for shortest accidental beam losses time
    constants
  • Could be ok for 450 GeV, not for 7 TeV
  • Studies needed

40
Protection and redundancy at 450 GeV
41
Protection and redundancy at 7 TeV
42
Conclusions
  • Protection for LHC starts before extraction from
    SPS
  • Protection is required during the entire cycle
  • Large redundancy in protection
  • Availability of the machine due to the complex
    protection is an important issue
  • Large energy stringent protection required - too
    few interlocks could lead to severe damage of the
    LHC
  • Unprecedented complexity too conservative
    interlocking of the machine protection systems
    could prevent efficient LHC exploitation
  • Initial operation with part of the protection
    systems
  • Commissioning of other protection systems during
    initial operation

43
Some questions to the workshop..
  • Fast beam current decay monitoring
  • Fast beam position change monitoring
  • What can be achieved?
  • Who has experience?
  • Where else might such systems be required?

44
Acknowledgements
  • The presentation is based on the work that was
    performed in many groups in several CERN
    Departments, as well as collaborators from other
    labs (Fermilab, GSI, Protvino, Triumf, .)
  • Contributions of many colleagues are
    acknowledged, in particular for the discussions
    in the Machine Protection WG, Collimation WG and
    Injection WG
  • particular thanks for R.Assmann, H.Burkhardt,
    E.Carlier, B.Dehning, B.Goddard, E.B.Holzer,
    J.B.Jeanneret, V.Kain, B.Puccio, J.Uythoven.
    M.Zerlauth

45
  • Recent question in MPWG Can we dump the beam in
    time after a quench of a dipole magnet?
  • Beam is to be dumped before the current in the
    dipoles starts to decay
  • The sequence of following actions has to be
    determined
  • beam loss causes the magnet to quench
  • the voltage builds up and exceeds the threshold
    of the quench detector
  • the quench detector detects the voltage after
    some time
  • the quench detector fires quench heaters or
    triggers the energy extraction
  • at the same time, the PIC is informed
  • PIC sends a dump request to the BIC
  • the heaters become efficient
  • the BIC sends a dump request to the beam dumping
    system
  • the voltage exceeds the diode voltage, and the
    current starts to bypass the magnet
  • the switch opens, and the current in the string
    of magnets decays
  • The Powering Interlock Controller is the only
    system sending (direct) beam dump request after
    powering failures
  • Secondary protection with collimators, BLM
    (possibly BPM / beam lifetime)

Defined sequence
Whos quickest?
46
Hardware configuration (main dipole circuit) and
signal transmission
Quench Loop stretching over the arcs
Beam Dump Request
Beam Interlock Controller
Beam Dump Request
Beam Dumping System
Quenching (dipole) magnet in the arc
47
The PIC process times
  • Interlock Controller is based on a PLC controlled
    process, monitoring and controlling up to 45
    electrical circuits (gt200 signals)
  • For time (beam) critical circuits -gt configurable
    hardwired matrix in parallel

PIC Controller (PLC) Process time lt 5ms
Power Converters
Quench Protection System
Power Permit, Powering Failure, Discharge
Requests
Quench Signals, Discharge Requests
For main circuits Hardware Matrix (CPLD) Process
time lt 0.2ms
Beam Dump Requests
48
The Timescales
Decay starts somewhat before the complete arc
extinction due to resistive arc // resistor
Diode becomes conductive gt 80ms
Current in dipole circuit
lt 15 µs
lt 100 µs
5..7 ms
T1 EE system reads Quench signal
Mechanic opening arc extinction
T3 Last branch open, arc is extinct Current in
dipole magnets decays
T2 Switch Opening
lt 100µs
0.2 5ms
lt 270µs
lt 15 µs
lt 100 µs
PIC process
T2 PIC reads signal
T3 PIC issues beam dump
T5 Completion of beam dump
T0 Quench signal
T4 Beam dump is received by the BIC
T1 Quench Loop Controller Receives signal
49
Conclusions
  • Due to the delay in the switch opening of the
    13kA energy extraction system, the beam is dumped
    before the current in the magnet starts decaying
  • also true in case of self triggering of EE
  • For all other sc magnets the time constraints are
    less critical
  • For time critical signals (mainly main dipole and
    quadrupole circuits due to large effects on the
    circulating beams), a hardwired matrix within the
    PIC can be configured in parallel to the PLC
    process
  • What to do for nc magnets?!
Write a Comment
User Comments (0)
About PowerShow.com