Integration and validation of the ATV Control Center - PowerPoint PPT Presentation

1 / 20
About This Presentation
Title:

Integration and validation of the ATV Control Center

Description:

TTFEE: The Telemetry & Telecommand Front End Equipment, in charge of the real ... TFEE: Front. End. OA: Office Automation. AGCS: ATV. Simulator. FCC : FAS ... – PowerPoint PPT presentation

Number of Views:33
Avg rating:3.0/5.0
Slides: 21
Provided by: murielle4
Category:

less

Transcript and Presenter's Notes

Title: Integration and validation of the ATV Control Center


1
Integration and validation of the ATV Control
Center
  • Véronique VALETTE, Carole LARIGAUDERIE,
    Christophe HUGONNET, Patrick CHARLOT
  • Centre National dEtudes Spatiales
  • Centre Spatial de Toulouse, 18 avenue Edouard
    Belin,
  • 31401 Toulouse Cedex 9
  • FRANCE

2
Integration and validation of the ATV Control
Center
  • ATV Project
  • ATV-CC Environment
  • ATV-CC Architecture
  • AIV Strategy and Presentation of the Tests
  • Verification Process
  • Assembly, Integration Verification team
  • Process Schedule

3
ATV Project
  • ATV Automated Transfer Vehicle, Jules Verne,
    will be the first ESA space vehicle to rendezvous
    and dock with the International Space Station
    (ISS).
  • Support the logistics maintenance of the ISS
    through dry and wet cargo delivery and disposal,
    and support ISS on-orbit control through its
    re-boost capability.
  • Launched on an Ariane 5 and will remain attached
    to the Russian Segment of ISS (ISS-RS), for up to
    6 months, before de-docking and performing a
    destructive re-entry into the Earths Atmosphere.
  • The ATV Control Center (ATV-CC) is an ESA
    project developped by CNES as prime contractor
    and is located in CNES facilities in Toulouse.

4
(No Transcript)
5
(No Transcript)
6
ATV Control Center Environment
  • The ATV control center is integrated in a
    pre-existant network of manned-space control
    centers and has many interfaces with external
    partners sites
  • WS GS White Sand Ground Stations for the TDRSS
    satellites to receive ATV telemetry,
  • MCC-H Mission Control Centre of Houston for
    ISS,
  • Redu EET and ARTEMIS MCF Mission Control Centre
    of Redu for Artemis satellite to receive ATV
    Telemetry,
  • MCC-M Mission Control Centre of Moscow for ISS,
  • Col-CC Columbus Control Centre (IGS management
    control facility, Central Dass server for
    processed data),
  • ATV EGSE / FSF at Les Mureaux or ESTEC,
  • EST (Engineering Support Team, vehicle experts)
    off-site  at Les Mureaux
  • Kourou  A5 CVI and ATV EGSE using ICARE (CNES
    operational data network).

7
Icare
8
ATV-CC Architecture
  • ATV-CC is split into 9 subsystems
  • ATV-CC Infrastructure and Lans,
  • Monitoring Control sub-system in charge of all
    the functions related to the monitoring and
    control of the ATV performing the real time
    analysis of the received telemetry and preparing
    and sending the telecommands.
  • TTFEE The Telemetry Telecommand Front End
    Equipment, in charge of the real-time data
    exchanges with TDRS or Artemis ground terminals.
    This equipment is split into three parts the
    main equipment within ATV-CC, and a remote
    element within ESA Gateway at MCC-H in Houston
    and at Artemis Ground Station in Redu.
  • Flight Dynamics sub-system in charge of all the
    flight dynamics functions during all phases of
    the mission (preparation, execution and mission
    assessment)

9
ATV-CC Architecture
  • Data Gateway sub-system, which is in charge of
    all the data exchange between the real-time
    Operations world and the off-line Office
    Automation world, restricted to all non
    real-time external exchanges.
  • Office automation sub-system provides office
    tools and also procedures management using MOIS
    tool and Flight Operational Plan tool.
  • OCT, Operational Complementary Tools, including
    Memory Image Management, housed by Office
    automation sub-system.
  • Voice sub-system.
  • Video distribution sub-system.

10
ATV-CC Architecture
  • The ATV-CC is composed of
  • a nominal center in which all the subsystems are
    redunded
  • a backup center
  • 40 Unix servers, 40 Unix clients,
  • 8 windows application servers, 110 windows
    clients,
  • 20 printers dispatched
  • 3 networks and 3 DMZs per control center (nominal
    and backup).
  • All the interfaces are technically described in
    the ATV-CC External and Internal Interfaces
    Definition Document which represents about 120
    external interfaces and 100 internal interfaces.

11
ATV-CC Architecture
12
AIV Strategy and Presentation of the Tests
  • The AIV process includes the following tests
    activities
  • Subsystems acceptance tests, which are technical
    and contractual tests between CNES and its
    sub-contractors
  • Internal Assembly tests (IAT), which validate the
    internal interfaces between subsystems two by
    two.
  • ATV-CC standalone system validation tests ,
    functional tests with all the integrated
    subsystems
  • Ground segment interface tests (IT) and End to
    End ground tests to validate all the external
    interfaces of the ATV-CC
  • ATV system validation tests (SVT) to test the On
    board/Ground interfaces

13
(No Transcript)
14
Sub-Systems acceptance
  • Verify the correct implementation of all
    requirements as described in the subsystem
    requirements document and to accept the
    sub-contractor deliveries
  • Splitted into Factory acceptance and On-site
    acceptance
  • The acceptance plan and the individual test
    procedures are elaborated by the sub-contractor
    and shall be approved by CNES.

15
Integration Assembly tests
  • Verify and test the internal interfaces between
    the subsystems
  • The subsystems are integrated two by two, ans all
    the interfaces between the two subsystem are
    verified
  • The integration test specifications and
    procedures are written and executed by CNES
    integration team
  • Iterative process run at each new version of a
    subsystem leading to ATV-CC versions

16
Standalone verification
  • The standalone verification aims to validate the
    entire integrated ATV-CC including the switches
    between nominal and backup centers
  • The test procedures are written by CNES
    validation team and approved by ESA. All tests
    are performed by CNES team under ESA supervision.
  • These tests are the last step before the ESA
    ATV-CC Qualification Acceptance review

17
Interface Tests
  • Validation of each external interface of the
    ATV-CC on a technical basis, without taking into
    account operational aspects. The responsibility
    of these tests is shared between partners under
    ESA leadership
  • The Interface tests are conducted on a 2 by 2
    basis and defined as follows
  • IT1 Connectivity
  • IT2 Telemetry exchange
  • IT3 Telecommand
  • IT4 Voice
  • IT5 Video
  • IT6 File exchange
  • IT7 Archived data retrieval
  • IT8 Operation, preparation, planning
  • IT9 Security
  • IT10 Redundancy

18
Verification Process
  • The coverage of the ATV Ground Segment
    requirements will be demonstrated by ensuring
    the traceability between the ATV-CC system
    specification and the ATV-GS SRD which is the ESA
    ground segment specification
  • The traceability link is managed using an ACCESS
    database and requests
  • The Verification Control Document (VCD) will
    summarise the verification results with regard to
    the GS SRD.
  • A coverage matrix of all the internal and
    external interfaces is also constructed as part
    of the Interfaces Validation Reports.

19
AIV Team
  • The size and composition of the test team
    ,depends on the type of test.
  • For IAT, the AIV team is composed of the core
  • AIV manager,
  • 2 AIV support,
  • 2 integration supports (1 for each subsystem)
  • Operating System, OA administrator,
  • Software Quality Assurance Manager

20
Process schedule
  • The Assembly, Integration and validation process
    of the ATV Control Center has begun Mid 2003 with
    the acceptance of the first subsystem and is
    still going on . We have performed about 45 two
    by two integration tests between sub systems,
    which represents about 2/3 of the identified
    integration tests. Two major versions of each
    Monitoring and Control and Flight dynamics
    subsystems are still to be accepted and
    integrated.
  • The Integration Tests have begun end 2004 and are
    at about 90 completed.
  • The standalone validation is going to be run
    during the next monthes.
Write a Comment
User Comments (0)
About PowerShow.com