Title: CARE-ASAS%20Action%20Plan


1
CARE-ASASAction Plan
  • Francis Casaux
  • CARE-ASAS Action Manager
  • on behalf of EUROCONTROL

2
Reference Documents
  • CARE Document
  • January 4, 2000
  • CARE Framework Agreement
  • version 3
  • CARE-ASAS Action Plan
  • CARE-ASAS/99-001 - Version 3.1 - January 3, 2000
  • General Procedure for Calls
  • CARE-ASAS/99-001 - Version 1.2 - January 11, 2000
  • CARE Web Site
  • http//www.eurocontrol.be/projects/eatmp/care/

3
CARE-ASAS Objectives
  • Promote co-operative work on ASAS within Europe
  • Establish a common view on ASAS applications
  • Support the validation of the strategic line of
    action related to transfer of separation
    responsibility to the cockpit identified in the
    ATM Strategy for 2000
  • Make the best use of the wide range of
    competencies which are required to address all
    the issues
  • Avoid the duplication of RD efforts

4
Levels of Co-operation
  • Level 1 - Exchange
  • Direct contacts between people at the working
    level
  • Technical Interchange Meetings, Workshops, RD
    Network
  • Projects are run independently
  • Calls for Proposal
  • Level 2 - Co-operation
  • Avoid duplication of efforts
  • Results of RD work are re-used
  • Projects are inter-related
  • Calls for Interest
  • Level 3 - Collaboration
  • Working together on the same project
  • Common funding is necessary
  • Calls for Tender

5
Management
  • CARE-ASAS Action Management
  • Francis Casaux action manager
  • Mick van Gool (DSA/PPM) CARE manager
  • Ed Bailey (DSA/AMN) technical secretary
  • CARE-ASAS Action Management Board
  • composed of ASAS experts
  • who advise the action manager
  • they initiate the work
  • they follow the progress
  • they evaluate the work conducted within the action

6
Call for Proposal
  • Mechanism for the exchange of information
  • Proposals for topics, lectures, results of
    studies
  • Technical Interchange Meetings for people
    working on ASAS RD studies
  • Workshops open to people outside RD
    organisations
  • No identified CARE-ASAS budget
  • Mechanism for Organisations to propose new
    CARE-ASAS activities requiring a co-operative
    approach

7
Call for Interest
  • Calls for Interest are issued after a decision
    from the Eurocontrol RD Review Group
  • The aim is to gather Organisations working on a
    CARE-ASAS activity
  • The work is funded by the budget of the
    participating Organisations
  • The first tasks are to elaborate an agreed work
    plan and to define a working structure
  • And then to produce the activity deliverables

8
Call for Tender 1/2
  • Calls for Tender for activities are issued after
    a decision from the Eurocontrol RD Review Group
  • Calls for Tender for work-packages within an
    activity are issued after a decision from the
    CARE-ASAS Action manager
  • The aim is to select an Organisation or a
    Consortium to achieve the work and to provide the
    deliverables identified within the activity or
    the work-package
  • The work is funded by the CARE budget

9
Call for Tender 2/2
  • Calls for Tender will be issued following the
    Eurocontrol Standards
  • Replies shall include
  • a technical proposal
  • a financial proposal
  • a management plan
  • CARE is a co-operative initiative
  • Replies by Consortium are preferable (more than
    one Organisation)
  • Within a Consortium a leader shall be identified

10
Activity 0 - Communications
  • Objectives
  • Exchange of information between organisations
  • Dissemination of the RD results
  • Inputs
  • Results of RD projects and studies
  • Progress reports on on-going projects and studies
    including the CARE-ASAS Action
  • Work content
  • Technical Interchange Meetings for RD people
  • Workshops open to stakeholders
  • Exchange of information through a CARE RD network

11
Activity 1 - Problem Dimensions
  • Objectives
  • Review of the existing work on ASAS
  • Analysis of the degree of validation achieved so
    far
  • Identification of areas needing further work
  • Inputs
  • Results from past and on-going European RD
    projects and studies related to ASAS
  • Deliverables A report
  • Procedure Call for Tender (1 man-year)

12
Activity 1 - Tentative schedule
  • February 10, 2000 the Call for Tender is issued
  • March 9, 2000 Replies are received
  • Selection process
  • April 14, 2000 The contract is signed
  • April 21, 2000 Kick-off meeting
  • September 8, 2000 The interim report is
    available
  • September 28, 2000 Activity 1 workshop
  • October 27, 2000 The final report is available

13
Activity 2 - Validation Framework
  • Objectives
  • Comparison of studys results
  • Development of an approved validation framework
  • Inputs
  • Existing work on ASAS validation
  • Similar work conducted within CARE-INTEGRA
  • Deliverables
  • Scenarios
  • Metrics (safety, capacity, efficiency)
  • Tools for ASAS validation
  • Procedure Call for Interest

14
Activity 2 - Schedule
  • January 21, 2000 The Call for Interest is
    issued
  • February 18, 2000 Replies are received
  • March 14, 2000 Activity 2 workshop in Haren
  • Work to be carried out
  • Activity 2 work plan
  • Activity 2 working structure
  • Initial co-operative work
  • September 14, 2000 Activity 2 review

15
Activity 3 - Airborne Separation Minima
  • Objectives
  • Phase 1 influencing parameters and first attempt
    of quantification
  • Phase 2 Define airborne separation minima (which
    are dependent on ASAS applications and
    technologies)
  • Inputs
  • Work on separation minima
  • ASAS application procedures
  • Deliverables A report
  • Procedure Call for Interest for phase 1 (1 or 2
    man-year)

16
Activity 3 - Schedule
  • January 21, 2000 The Call for Interest is
    issued
  • February 18, 2000 Replies are received
  • March 15, 2000 Activity 3 workshop in Haren
  • Work to be carried out
  • Activity 3 work plan
  • Activity 3 working structure
  • Initial co-operative work
  • September 15, 2000 Activity 3 review

17
Activity 4 - ASAS Application Selection
  • Objectives
  • Phase 1 Selection of ASAS applications and
    delegation of separation assurance issues
  • Phase 2 Study of two or three ASAS applications
  • Phase 3 Study of other ASAS applications
  • Inputs
  • AIRSAW-TF work
  • Results of activities 1, 2 3
  • Deliverables A report
  • Procedure TBD

18
Activity 5 - Implementation Programme
  • Objectives
  • Elaborate an ASAS work programme to implement the
    selected ASAS applications within the framework
    of EATMP
  • Inputs
  • Results of activities 1, 2, 3 4
  • OCD and ATM Strategy for 2000
  • Deliverables A report
  • Procedure TBD

19
FAA/EurocontrolAction Plan 1
  • RD co-operation between the FAA and Eurocontrol
  • Action Plan 1 is dedicated to ASAS
  • The objectives are
  • to promote a mutual understanding on ASAS
  • to identify areas for practical co-operation on
    the development of ASAS
  • to examine the longer term issues related to the
    advanced capabilities of air and ground equipment
  • Strong co-ordination between CARE-ASAS and Action
    Plan 1 will be maintained

20
Concluding Remarks
  • Activity 1 is to be launched through a call for
    tender
  • Activity 2 3 are launched through calls for
    interest
  • Success will depend on Organisations involvement
  • provision of internal resources to support
    co-operation and to progress the work
  • replies to the various calls
  • impact on internal RD projects
  • CARE is a challenging initiative
  • See you next year to assess the results