Title: C
1 CI SYSTEMS IN INDIAN NUCLEAR POWER PLANTS
- A. K. Chandra
- Assoc. Dir. (RD-ES, IT)
- Nuclear Power Corporation of India Ltd.
- IAEA Technical Meeting on Impact of Modern
Technology on NPP IC Systems
2The Present NPP Scenario in India
- 15 operating NPPs with a total capacity of 3360
MWe - 8 plants under construction with a total capacity
of 3920 MWe including 5 PHWRs, 2 PWRs (VVERs) and
1 PFBR.
3 4(No Transcript)
5(No Transcript)
6Main Control Room Philosophy in TAPP-34
- Main Control Room employs hybrid systems.
- System wise panels in the background and operator
consoles in front. - Panels for different plant functions contain
discrete control devices and displays. - Comprehensive Plant Status available on COIS
screens on each panel. - Operator consoles provide displays and
interaction facilities for individual system.
7Evolution of Computer Based Systems in Indian
NPPs
- Computerization of Monitoring functions began
from MAPS (1987) - - Channel Temperature Monitoring System
- Control Functions NAPS (1990)
- - Reactor Regulating System
- - Control of on-power refueling machines
- - Control Room Computer System
- - Digital Recording System
- Protection function KAPS (1993)
- - Programmable Digital Comparator System
- KGS-1,2 RAPS-3,4
- - Programmable Logic Comparator
- - Process Control System
8Evolution of Computer Based Systems in Indian
NPPs (Contd.)
- All major Control, Monitoring, Test
Surveillance and Operator Information functions
in TAPP-3, 4 are CBS. - Some protection functions use microprocessors
- Information from these systems and from stand
alone controllers recorders sent to a
Computerized Operator Information System (COIS)
through Gateways - Information from COIS sent over VSAT to HQ
9Technology Employed for Computer Based Systems
- All CBS employed for IC are custom built
- All CBS are designed and developed indigenously
by NPC and other organizations - Hardware manufacture, integration and
installation by Electronics Corporation of India. - Verification and Validation carried out by an
independent IV V Committee.
10TAPP-3,4 Systems Developed At NPCIL
- ECCS Test Facility
- Instrumented Channel Monitoring System
- Test and Monitoring System - 2
- Reactor Parameter Display System
- COIS Gateway
- Portable Recording System
- Neutronic Trip Unit
- Centralized Operating Plant Information System
11TAPP-3,4 Systems Developed By Other Organizations
- Reactor Regulating System
- Process Control System
- Prog Digital Comparator System Safety
- Prog Digital Comparator System Control
- Channel Temperature Monitoring System
- Flux Mapping System
- Test and Monitoring System 1
- Computerized Operator Information System
- Programmable Logic Comparator
12Support Issues for CBS
- Systems are required to be supported for their
life span - Changes are required due to
- Operational feedback
- Regulatory requirements
- Hardware obsolescence
- Original developers move on to other challenges
13The Challenge Ahead
- Large numbers of Operating stations of differing
vintage to be supported - Large numbers of plants under construction
- Implementation of the system for the same
function varies with station reflecting the state
of the art at that time
14The Challenge Ahead (Contd.)
- Prototypes are required to be maintained in the
laboratory to ascertain behaviour of system under
postulated conditions - Large variety of prototypes are required because
of differing implementations at various stations - Leads to high resource requirements Cost, Space,
Manpower
15The Challenge Ahead (Contd.)
- In addition, development work is to be carried
out for the CBS CI for the new power plants
under construction
16Current Development Work for RKnew
- Reactor Regulating System
- Process Control System
- Prog Digital Comparator System Safety
- Prog Digital Comparator System Control
- Channel Temperature Monitoring System
- ECCS Test facility
- Reactor Parameter Display System
- COIS Gateway
- Digital Recording System
- Electrical. SCADA (R-5,6)
- RMU
17Meeting the Challenge
- Establishment of in-house facilities for support
and development and testing - STANDARDIZATION !
- Across the systems
- Across the stations
18Meeting the Challenge (Contd.)
- STANDARDISATION OF ARCHITECTURES
- STANDARDISATION OF HARDWARE
- STANDARDISATION OF SOFTWARE
- STANDARDISATION OF H S I
- STANDARDISATION OF DOCUMENTATION
19Standardisation Of Architectures
- Reduction in overall development time for all
systems. - Reduction in amount of documentation
- Reduced time required for VV
- Reduction in requirement for support to be
provided to systems in stations.
20Operator Interface Unit
Server
RTU
21Standardisation of Architectures (Contd.)
- Develop systems for all new plants using generic
architecture - Retrofit the same in operating stations at an
appropriate opportunity
22Engineering Procedures defined to
- Introduce standardization in development process
- Achieve (repeatable) quality
- Conform to AERB SG-D25
- Standardize development contracts
23Engineering Procedures cover
- Work Methods for design, development, testing and
commissioning of CBS - Documents to be produced at various stages of
life cycle (and the nature and structure of
information content of the same) - Methodology for preparation, review and approval
of documents
24Precise and Exhaustive Documents are required to
be produced because systems will be reviewed,
used and supported by people other than those who
designed the system.
25 REGULATOR
USER
DESIGNER
DEVELOPER
MANUFACTURER
REVIEWER
INTERNAL QA VV
AGENCIES IN LIFE CYCLE
26 Independent V V in NPCIL
- Design Basis Report (DBR), approved by AERB, is
the baseline document. - The reviews are carried out at each stage of
system development - For each system, a Task Force is responsible for
the entire review process - Full documentation with IVV reports are
submitted for licensing with AERB
27