Title: Colombian Market Stress Experiences
1Colombian Market Stress Experiences
Luis Alejandro Camargo S. Wholesale Market
Manager XM S.A. E.S.P.
2Situation Terrorism on Power Lines
3Terrorist Attacks To The Transmission Grid
Terrorism against the National high voltage Grid
System
4We operated n- 55 in May of 2002
5Despite the attacks, no overall blackouts have
affected the market
Non-served demand (as a percentage of the annual
electricity demand)
6Rules To Guarantee Security
- Voltage should not be under 90 or over 110 of
nominal value (over 105 at 500 kV) - The reactive power on generation units must
follow their capacity curves - Establish specific voltage levels on different
special points/nodes on the system - The system should maintain operating even with a
three phase fault, cleared using the principal
protection - Generators must oscillate on a damp and
consistent way - If a grid element goes out, there should not be
additional trips, in order to avoid cascade events
7Reliability
- Current Probabilistic Method (formerly classic
N-1) - Outage Probability of Elements (1 year history)
- Rationing caused by outage of elements
- Electric-Area Reliability Criterion
- Information System to Gather Data
- Market participants must deliver information
- Gathering information through ISO
- Design strategies for
- High Availability of equipments
- Minimum of events
8ECONOMIC DISPATCH IN COLOMBIA
MARKET FUNCTIONS
OPERATION PLANNING FUNTIONS
Offer Price Curve for International
Transaction (TIE)
Day Ahead Dispatch
Price Offer's
IDEAL DISPATCH
REAL DISPATCH
Without Network Generations Technical
Characteristics
Network Generations Technical Characteristics
Marginal Price Congestions
FINAL DISPATCH
Reliability Signals
Current Day Dispatch
REAL TIME OPERATION
Settlement
9ESTYRA In House Application Development
- After the market dispatch is calculated, a
electric analysis team check the system security.
This can be done by - Conventional approach (DIgSILENT - Power
factory) - ESTYRA
- Transitory Stability Estimated
- Overload Estimated
- Redispatch
10Real Time Oscillation Monitoring
- Frequency measure
- Indication of Damping
- Possible Generation Changes
- Generations Control Settings Changes (Adjust PSS)
- Real time Detection of Oscillation
- Reinforcement of the National Grid
11Real Time Oscillation Monitoring
Frequency vs Damping
- Even though about 10.000 oscillations were
detected with the frequency and oscillation
network F_at_OSnet, 96 of them have remain below
60 seconds
Damping
0.70 Hz Coast-Central
0.45 Hz Colombia-Ecuador
0.22 Hz Colombia-Venezuela
InterArea modes
12Critical factors to deal with terrorism on Power
Lines
- Generating plants availability and coordination
- Reliability indexes calculation
- Development of international networks
- Probabilistic criteria for planning and operation
- Development of software for real time transient
stability analysis - Frequency and oscillation measurement network
- Development of AGC schemes for isolated areas
- Reconfiguring power lines procedures
- Fast restoration schemes
13Luis Alejandro Camargo S. lcamargo_at_xm.com.co