Title: Accelerator Readiness Review October 31, 2006


1
Accelerator Readiness ReviewOctober 31, 2006
  • Quality Assurance
  • Darren S. Marsh
  • Stanford Linear Accelerator Center

2
Outline
  • Major Areas of Quality Assurance
  • Quality Program Management
  • Technical Requirements
  • Design Reviews
  • Manufacturing, Inspection and Test Control

3
Quality Assurance Program
  • LCLS QA Program will be conducted in accordance
    with LCLS Quality Implementation Plan
  • Lessons learned from other programs will be
    utilized
  • The implementation relies upon the controlled
    application of plans, procedures, and requirements
  • Objectives
  • Clear, formal communications of specifications
  • Clear, formal definition of interfaces and
    responsibilities
  • Verification that specifications have been met

4
Technical Specifications
5
Technical Baseline Design Definition
Requirements Summary
6
Requirement Documents Tracking
  • Requirement documents status reviewed at LCLS
    Management Meetings
  • Applicable requirements document updated based on
    CCB action or requirement change

7
Design Review Program
  • Design reviews are essential to good engineering
    practice and are used as a quality assurance
    metric to ensure the successful construction of
    the LCLS.
  • ESD 1.1-324 establishes guidelines for design
    reviews conducted by the LCLS Subsystems.
  • It describes the material to be covered, the
    documentation requirement and the process for
    closure of all action items.
  • Reviews based upon the appropriate selection from
    the following reviews
  • System Concept Review (SCR)
  • Preliminary Design Review (PDR)
  • Final Design Review (FDR)
  • Readiness Review (RR)

8
Technical Design Reviews
  • gt100 design reviews have taken place
  • 50 design reviews have taken place in last six
    months

9
Work Processes
  • Manufacturing, Assembly and Installation
    Activities
  • Work processes are planned and controlled
  • Activities are performed in accordance with
    prescribed instructions, procedures and drawings
  • Items are designed and changes controlled using
    sound engineering practices, analyses and
    configuration management
  • Inspection and Test
  • Items are inspected and tested to verify
    conformance to specified requirements

10
Inventory Database
Drawing from SLAC document control
Serial , Barcode , Alias name
Optics name
11
Summary
  • LCLS Quality Assurance Program well established
  • Quality Assurance processes are in place to plan,
    perform, assess, and improve work
  • Based on the development and maintenance of the
    integrated LCLS Total Management System
  • Performance Oriented
  • Infrastructure elements in place for successful
    integration/installation, checkout and
    commissioning of system hardware
  • The LCLS Project is ready to begin commissioning
    activities