The Gateway Review Process in an Australian Government context - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

The Gateway Review Process in an Australian Government context

Description:

How does today's presentation fit with the focus of this conference? ... Gateway Review Process. Questions? The Gateway Unit is contactable at: gateway_at_finance.gov.au ... – PowerPoint PPT presentation

Number of Views:41
Avg rating:3.0/5.0
Slides: 19
Provided by: SWA62
Category:

less

Transcript and Presenter's Notes

Title: The Gateway Review Process in an Australian Government context


1
The Gateway Review Process in an Australian
Government context
  • Robert Higgins
  • Branch Manager
  • Gateway Unit

2
Gateway Review Process
  • How does todays presentation fit with the focus
    of this conference?
  • - Developing a project management culture.
  • - Providing practical / operational support to
    project mangers.
  • - Designed to stimulate dialogue.

3
Gateway Review Process
  • What is the Gateway Review Process (Gateway)?
  • - Gateway was developed by the United Kingdoms
    Office of Government Commerce.
  • - Gateway is an expert, time limited and
    confidential peer review conducted throughout the
    life-cycle of certain projects by an independent
    review team.
  • - The focus is on issues that will make the
    project successful.
  • - A short, focussed and useable report is
    produced.

4
Gateway Review Process
  • What is the Gateway Review Process? (cont.)

5
Gateway Review Process
  • What is the Gateway Review Process? (cont.)
  • - Review planning is consultative and aims to
    maximise the potential benefits.
  • - Gateway involves a cooperative relationship
    between the Review Team, Senior Responsible
    Official (SRO) and the Project team to assist
    delivery against the projects established
    outcomes.
  • - Gateway is based on open and honest
    communication.

6
Gateway Review Process
  • What is the Gateway Review Process? (cont.)
  • - Short duration, reviews usually take 4-5 days.
  • - Project progress is not delayed.
  • - Review reports are action-orientated.
  • - Reports are confidential and provided to the
    SRO.
  • - Gateway reviews are not audits.

7
Gateway Review Process
  • What is has been the experience in other
    jurisdictions that use the Gateway Review
    Process?
  • - Gateway has been used in the United Kingdom
    and Victoria since 2000 and 2003 respectively.
  • - Over 1000 reviews completed in the UK and over
    100 completed in Victoria.
  • - Applying this methodology has demonstrably
    improved on-time, on-budget project delivery.
  • - Strong positive feedback from SROs, project
    teams and reviewers.

8
Gateway Review Process
  • What are the key benefits of the Gateway Process?
  • - Best available skills and experience deployed
    in the review.
  • - Increased stakeholder understanding of key
    success criteria, scope, outcomes,
  • - Repeated deficiencies corrected.
  • - Knowledge transfer and application of best
    practice occurs.
  • - Gateway may improve supplier confidence.
  • - Increased success of outcomes.
  • .

9
Gateway Review Process
  • Why adopt the Gateway Review Process?
  • - This methodology has a proven track record
    in similar jurisdictions.
  • - Gateway sits well with the Australian
    Government accountability framework.
  • - Reviews are fast, focussed and actionable.
  • - The Gateway Review Process will help improve
    project management skills.

10
Gateway Review Process
  • What projects will Gateway apply to?
  • - Government has decided that Gateway will apply
    to projects by FMA Act agencies that are
  • - IT projects costed at 10m or more
  • - procurement and infrastructure projects
    costed at 20m or more
  • where warranted by risk.
  • - Risk is assessed by using the Gateway
    Assessment Tool

11
Gateway Review Process
  • Example of the Gateway Assessment Tool

12
Gateway Review Process
  • What projects will Gateway apply to? (cont.)
  • - Gateway will be phased-in as part of the
    2006-07 Budget process.
  • - Projects above the financial threshold are
    required to complete the Gateway Assessment Tool.
  • - The Prime Minister and Finance Minister will
    agree a small cross-section of high risk projects
    to undertake a business case review.
  • - Reviews are likely to commence from late March
    2006.

13
Gateway Review Process
  • What projects will Gateway apply to? (cont.)
  • - For the 2007-08 Budget and subsequently all
    projects that are above the financial thresholds
    and are high risk will be required to undertake a
    business case review.
  • - This review is to be completed and addressed
    before the project is considered by Government.
  • - Gateway will apply to medium risk projects
    from the 2008-09 Budget forward.

14
Gateway Review Process
  • Who conducts the reviews?
  • - Reviews are only as good as the review team.
  • - Reviews are conducted by 3-4 suitably
    qualified reviewers with relevant skills that
    have completed accredited Gateway training.
  • - Reviewer skills include, IT, project
    management, financial analysis, procurement among
    others.
  • - Reviewers are from both the public and private
    sectors.

15
Gateway Review Process
  • Who conducts the reviews? (cont.)
  • - The review team works closely with SROs and
    the Project Team, eg providing daily briefings.
  • - Reviews are lead by experienced Team Leaders.
  • - Reviewers aim to support project success and
    add value. Knowledge transfer is also a goal.
  • - The aim is a high quality, usable review.
  • - Reviewers provide a report to, but are not
    working for, the SRO.

16
Gateway Review Process
  • What is in a Gateway Review Report?
  • Reports are short, tightly-focussed and
    action-oriented.
  • They contain
  • A summary of conclusions
  • Key recommendations
  • A statement on potential for success
  • Observations on readiness for the next phase
  • A list of interviewees
  • The report is produced on a no surprises basis.
  • The report is expected to be candid and
    independent.
  • A traffic light system indicates the projects
    overall position.

17
Gateway Review Process
  • What is the role of the Gateway Unit?
  • The Gateway Unit is responsible for
  • developing the Gateway Assessment Tool
  • producing guidance and standard documentation
  • facilitating the training of reviewers
  • organising review teams
  • managing a database of reviewers
  • paying for high risk reviews and
  • ensuring that lessons learnt are shared.
  • Oversight by a Gateway implementation Committee.

18
Gateway Review Process
  • Questions?
  • The Gateway Unit is contactable at
  • gateway_at_finance.gov.au