Title: Booster Rep Rate and Intensity Issues Beyond Proton Plan
1Booster Rep Rate and Intensity Issues Beyond
Proton Plan
- Eric Prebys, FNAL Accelerator Division
2Limits to Proton Intensity
- Total proton rate from Proton Source
(LinacBooster) - Booster batch size
- 4-5E12 protons/batch, depending on beam quality
requirements - Booster repetition rate
- 15 Hz instantaneous
- Prior to shutdown 7.5Hz average (injection
bumpRF) - Beam loss
- Damage and/or activation of Booster components
- Above ground radiation
- Total protons accelerated in Main Injector
- Maximum main injector load
- Six slots for booster batches (3E13)
- Up to 11 with slip stacking (4.5-5.5E13)
- Possible RF stability limitations (under study)
- Cycle time
- 1.4s loading time (1/15s per booster batch)
Historically our biggest worry
3Some Numbers to Keep in Mind
- At 120 GeV, 100 kW is roughly
- 1E20 protons/year
- 1 Booster Hz _at_5E12
- 2E16 peak proton intensity out of Booster
- ABSOLUTE limit of this Proton Source
- 5E12 batches _at_ 15Hz
- 1.5MW _at_ 120 GeV
- 1.5E21 protons/year
- 3E16 pph out of Booster
- This is about 2x the present proton plan
not including prepulses.! Add 2Hz/(MI cycle) for
total rate
4Rep Rate Issues in Proton Plan
- Proton Plan Mandate
- Slip stack to NuMI and pBar
- Maintain about 2E20 protons per year to the 8 GeV
line - This requires the Booster to go to about 9Hz
- Identify rate limitations
- If something needs to be replaced or
significantly modified to achieve 9Hz, do the
incremental work to make it 15 Hz compatible. - Identify and roughly cost out remaining issues to
go from 9Hz to 15Hz.
5Summary Significant Elements of Proton Plan
- Linac
- Stockpile two year supply of spare 200 MHz power
amplifier tubes (7835s), in the event of an
interruption in supply - Characterize and improve Low Energy Linac Low
Level RF - Booster
- Replace and reconfigure injection bump (ORBUMP)
system. - Relocate 8 GeV dump from Booster tunnel to MI-8
transfer line - Make Booster robust to 9 Hz, and understand
requirements to go to 15 Hz - Design, build, and install new corrector system
- Main Injector
- Replace seven quadrupoles with increased aperture
versions, to reduce injection and extraction
losses. - Operationally develop multi-batch and multi-batch
slip stacked operation - Design and install collimation system, both in
the MI-8 line and in the MI ring - Modify injection kicker to allow multi-batch slip
stacked operation - Characterize and perhaps make improvements to RF
system, to support high intensity operation.
Red to be completed this shutdown
6History of Booster Rate Limitations
solved
- MP02 extraction septum
- 2 Hz
- Replaced 2003, now 15Hz
- MP01 extraction septum
- 5Hz
- Replaced 2004, now 15 Hz
- ORBUMP magnets and power supply
- 7.5Hz
- Being replaced this shutdown -gt 15 Hz
- RF cavity drift tube cooling
- 7.5 Hz
- Installing cooling this shutdown -gt 15 Hz
- 13.8 kV transformers
- Questionable reliability at gt 7.5 Hz
- Being replaced this shutdown -gt 15 Hz
- Bottom line
- After this shutdown, Booster will be OK to 9Hz
- Done as far as the Proton Plan is concerned.
Being solved this shutdown
7Whats needed for SNuMI?
- At the end of the Proton Plan, the Booster will
be capable of - Peak proton rates based on beam loss of about
1.8E17 protons per hour - Sustained operation at 9Hz
- This will limit the actual output to 1.3E17,
depending on the details of the supercycle. - This roughly accommodates the baseline Nova
recycler retasking scheme - 11 booster batches into Recycler ever 1.4
seconds. - 700 kW to NuMI
- NO addition protons available for MiniBooNE,
SciBooNE, or SY120. - Anything beyond this will involve Booster
modifications beyond the Proton Plan - This includes alternative approaches to 700 kW
involving small MI loads with a short cycle time!
8Going Beyond 9Hz
- After this shutdown, the only thing limiting the
Booster rate will be the RF drive system. - Half the RF bias supplies have transformers which
would need to be upgraded. - Significant effort and lead time.
- Cost few hundred K
- 480 distribution system
- Being investigated
- On the order of 100K to upgrade, if necessary.
- Feeder from substation
- Probably OK.
- 250K if its not
- Total cost
- Still being determined
- Of order 0.5-1M
9Beam Quality at High Intensity
- All Proton Plan projections assume slip stacking
no more than 4E12 batches - Although Booster capacity is speced out for 5E12
batches. - As the Booster goes up in intensity, the beam
quality degrades - Have demonstrated 6E12 batches single batch
- However, when slip stacking was implemented
regularly in early 2005, there were problems
related to Booster beam quality above 3.5E12 - This became one of the central issues for the
Stacking Rapid Response Team - Jim Steimel in charge of Booster part, working
with booster personnel. - See McGinnis March Review talk for details
10RRT Steps to Improve Booster Beam
- Reduction of longitudinal emittance growth at
transition - Quadrupole Mode 0
- Bunch Rotation at Extraction
- Longitudinal Dampers
- Dipole Mode 0, 1, 2, 52
- RF Cavity balancing
- Results
11Effect Booster Quadrupole Damper
Quad Damper on
Quad Damper off
12Future Improvements Higher Intensity
- Transverse emittance can be controlled with
appropriate sextuple compensation - We are building a bunch by bunch transverse
damper system - Lots of bunches -gt lots of bandwidth
- Sweeping delay
- New Booster corrector system will have sextupoles
at ever subperiod (2007 and 2008) - Other Solutions for Booster Longitudinal
Emittance Blowup - Gamma-t jump currently problematic
- Large orbit shift confuses cogging
- New gamma-t system will be installed along with
correctors in 2008 - RF Step at Transition (pre-focus)
- Calculations finished look very promising
- Requires large voltage step