Title: FUEL AND ASPHALT COST ADJUSTMENT PROVISIONS
1- FUEL AND ASPHALT COST ADJUSTMENT PROVISIONS
2Use of Cost Adjustment Provisions
- FHWA Technical Advisory Dec 10, 1980
- Price volatility of construction materials and
supplies . Can result in significant problems
for contractors in preparing realistic bids. - This leads to price speculation and inflated bid
prices to protect against possible price
increases.
3Development of Cost Adjustment Provisions
- Price adjustments should apply for both upward
and downward movement of prices - Price adjustments should be based on an index or
other economic barometer which is not susceptible
to manipulation - Price adjustments should be Triggered only by a
significant change in the index base price
4Development of Cost Adjustment Provisions
- Price adjustment computations should be performed
at specified intervals rather than as each change
in price occurs. Monthly is suggested. - The 1980 Tech advisory recommended against
optional selection of cost adjustment provisions
but FHWA later stated Since all bidders have the
same option, this is consistent with competitive
bidding principles
5Fuel Cost Adjustment Provisions
- Fuel is typically an incidental cost to the a
project - A methodology for basis of payment must therefore
be determined - CDOT methodology is Fuel Usage per Unit method
- This estimates the amount of fuel used in various
units of work under average conditions - Fuel factors were developed in cooperation with
Colorado Contractors Association
62001 CDOT Fuel Cost Adjustment Specification
- First implemented on May 31, 2001 Not optional
- Index was the spot price per barrel of West Texas
Intermediate crude oil as posted in the Wall
Street Journal - Trigger was 10
- Payment was based on the increased pay quantities
for three items - Excavation 0.29 Gal/CY
- HBP 1.06 Gal/Ton
- Concrete Pavement 0.03 Gal/SY/Inch Thickness
7Revised November 2005
- Revised November 14, 2005 - Optional
- Index was still the spot price per barrel of West
Texas Intermediate crude oil as posted in the
Wall Street Journal - Trigger was left at 10
- One more item was added
- Aggregate Base Course 0.29 Gal/CY
8Revised Again November 2006
- Revised on November 30, 2006 remained an option
to the contractor - Index was revised to Opis Denver 2 Diesel
- Trigger was revised to 5
- Additional items were added
- Fuel factors were revised
9Revised Again November 2006
- Items now include
- Removal of Asphalt 0.006 Gal/SY/Inch depth
- Excavation, Embankment, Borrow 0.29 Gal/CY
- Excavation (Rock) 0.39 Gal/CY
- Structure Excavation 0.29 Gal/CY
- Aggregate Base Course 0.85 Gal/CY (convert Tons
to CY 0.557 Tons/CY) - Lime Treated Subgrade 0.12 Gal/SY
- Full Depth Reclamation 0.06 Gal/SY
- HMA SMA 2.47 Gal/Ton
- Heating Scarifying 0.44 Gal/SY
- Cold Bituminous Pavement Recycle 0.01
Gal/SY/Inch depth - Concrete Pavement 0.03 Gal/SY/Inch depth
10WYDOT Fuel Adjustment Specification
- Optional for all WYDOT Projects
- Based on Index Prices posted by WYDOT on the Web
Page. Index is from OPIS. - Contains a 7.5 Buffer area
- Adjustments are Positive and Negative
11WYDOT Fuel Adjustment Specification
- Contractor submits Affidavit (Form E-12) with
their signed contract - Establish of Contract for Fuel items
- Based on affidavit and original contract total
- Computed
- (Affidavit Cost/Original Contract Cost) x 100
- For each product (Unleaded, Diesel, Burner)
- Will remain the same for the life of the contract
12Affidavit of Fuel Cost for Project
13WYDOT Fuel Adjustment Specification
- Unleaded and Diesel Fuels eligible for adjustment
at every Estimate - Burner Fuels eligible for adjustment only on
those Estimates where paving or crack sealing
happened
14WYDOT Fuel Adjustment Specification
- Adjustments are made only when the index price
changes by more than 7.5 - Base Fuel Index (BFI) established previously
- Current Fuel Index (CFI) price for month prior
to the date of the Estimate
15WYDOT Fuel Adjustment Specification
- If an adjustment is warranted, it will be
computed - Contract x Estimate Amount x (Change0.075)
- Adjustments are made on each Estimate
162009 ???
- CDOT and CCA have had discussions regarding
revising the Fuel Cost Adjustment specification
again. - CCA is currently researching fuel factor data for
the existing items and any additional items they
may wish to request
17CDOT Asphalt Cement Cost Adjustment
- Joint Task Force with CDOT, FHWA and CAPA worked
to develop a specification - First implemented in 2007 as a pilot project as
an option to the Contractors on 6 projects - Index was the spot price per barrel of Western
Canadian Select Crude Oil as published by Encana - Trigger was 5
- Payment based on the quantities for HMA and SMA
18CDOT Asphalt Cement Cost Adjustment
- In 2007 none of the Contractors optd In and no
data was gathered - In 2008 the specification was again offered as a
pilot until July. - In July 2008 as a response to the asphalt cement
price volatility CDOT implemented the Asphalt
Cement Cost Adjustment specification as a
Standard Special Provision on all projects with
HMA or SMA. The cost adjustment specification is
mandatory, not at the contractors option. - No change in the index or trigger from the pilot
specification has been made.
19WYDOT Adjustment for Performance Graded Asphalt
Binder
- Current Specification implemented in 2009
- Reaction to extreme escalation in price
- Also reaction to supply issues within the state
- Includes adjustment for Chip Seal oils
20WYDOT Adjustment for Performance Graded Asphalt
Binder
- Mandatory for all WYDOT Projects with PG Binders
and Chip Seal oils - Based on Index Prices posted by WYDOT on the Web
Page. Index based on wholesale prices. - Contains a 10 Buffer area
- Adjustments are Positive and Negative
21WYDOT Adjustment for Performance Graded Asphalt
Binder
- The Contractor provides an Affidavit (Form E-14)
and a confidential bid price at the beginning of
the project.
22Affidavit of PGAB Price
23WYDOT Adjustment for Performance Graded Asphalt
Binder
- Adjustments are made only when the index price
changes by more than 10 - If an adjustment is warranted, it will be
computed - (PPI-BPI) x 0.90 x Tons of Binder
- Adjustments are made on each Estimate
24WYDOT Adjustment for Performance Graded Asphalt
Binder
- Additional adjustments are allowed for projects
that go beyond one construction season. - Adjustment is based on Confidential Bid Price
received from the Contractor (AAF) - If an adjustment is warranted, it will be
computed - AAF x (PPI-BPI) x 0.90 x Tons of Binder
25Sharing of the Risk
- Cost adjustment specifications not designed for
the DOT to assume all of the risk - Contractors still have to bid risk at least up to
the trigger - Also have to consider downward movement of the
price - CDOT index still based on crude oil price, not
asphalt cement price, as requested by CAPA - Cost adjustment only on HMA or SMA, not
emulsified items
26Sharing of the Risk
- DOTs advertise projects in winter to allow
contractors and suppliers to plan their work for
the next construction season - The longer the period between bid and actual
construction the greater the risk the index will
fluctuate the greater the risk to both parties
27WYDOT Specifications and Formswww.dot.state.wy.us
- Information Central
- Manuals and Publications
- 2003 Standard Specifications
- Supplemental Specifications
- Working With WYDOT
- Contractor Information
- Contractor Forms
- or
- 3. Base Index Prices
28Questions?
Dennis Largent, P.E. Project Development Branch,
Area Engineer dennis.largent_at_dot.state.co.us
Mark W. Ayen P.E. WYDOT Construction Staff
Engineer mark.ayen_at_dot.state.wy.us