FUEL AND ASPHALT COST ADJUSTMENT PROVISIONS - PowerPoint PPT Presentation

1 / 28
About This Presentation
Title:

FUEL AND ASPHALT COST ADJUSTMENT PROVISIONS

Description:

Fuel is typically an incidental cost to the a project ... Dennis Largent, P.E. Project Development Branch, Area Engineer. dennis.largent_at_dot.state.co.us ... – PowerPoint PPT presentation

Number of Views:31
Avg rating:3.0/5.0
Slides: 29
Provided by: colora8
Category:

less

Transcript and Presenter's Notes

Title: FUEL AND ASPHALT COST ADJUSTMENT PROVISIONS


1
  • FUEL AND ASPHALT COST ADJUSTMENT PROVISIONS

2
Use of Cost Adjustment Provisions
  • FHWA Technical Advisory Dec 10, 1980
  • Price volatility of construction materials and
    supplies . Can result in significant problems
    for contractors in preparing realistic bids.
  • This leads to price speculation and inflated bid
    prices to protect against possible price
    increases.

3
Development of Cost Adjustment Provisions
  • Price adjustments should apply for both upward
    and downward movement of prices
  • Price adjustments should be based on an index or
    other economic barometer which is not susceptible
    to manipulation
  • Price adjustments should be Triggered only by a
    significant change in the index base price

4
Development of Cost Adjustment Provisions
  • Price adjustment computations should be performed
    at specified intervals rather than as each change
    in price occurs. Monthly is suggested.
  • The 1980 Tech advisory recommended against
    optional selection of cost adjustment provisions
    but FHWA later stated Since all bidders have the
    same option, this is consistent with competitive
    bidding principles

5
Fuel Cost Adjustment Provisions
  • Fuel is typically an incidental cost to the a
    project
  • A methodology for basis of payment must therefore
    be determined
  • CDOT methodology is Fuel Usage per Unit method
  • This estimates the amount of fuel used in various
    units of work under average conditions
  • Fuel factors were developed in cooperation with
    Colorado Contractors Association

6
2001 CDOT Fuel Cost Adjustment Specification
  • First implemented on May 31, 2001 Not optional
  • Index was the spot price per barrel of West Texas
    Intermediate crude oil as posted in the Wall
    Street Journal
  • Trigger was 10
  • Payment was based on the increased pay quantities
    for three items
  • Excavation 0.29 Gal/CY
  • HBP 1.06 Gal/Ton
  • Concrete Pavement 0.03 Gal/SY/Inch Thickness

7
Revised November 2005
  • Revised November 14, 2005 - Optional
  • Index was still the spot price per barrel of West
    Texas Intermediate crude oil as posted in the
    Wall Street Journal
  • Trigger was left at 10
  • One more item was added
  • Aggregate Base Course 0.29 Gal/CY

8
Revised Again November 2006
  • Revised on November 30, 2006 remained an option
    to the contractor
  • Index was revised to Opis Denver 2 Diesel
  • Trigger was revised to 5
  • Additional items were added
  • Fuel factors were revised

9
Revised Again November 2006
  • Items now include
  • Removal of Asphalt 0.006 Gal/SY/Inch depth
  • Excavation, Embankment, Borrow 0.29 Gal/CY
  • Excavation (Rock) 0.39 Gal/CY
  • Structure Excavation 0.29 Gal/CY
  • Aggregate Base Course 0.85 Gal/CY (convert Tons
    to CY 0.557 Tons/CY)
  • Lime Treated Subgrade 0.12 Gal/SY
  • Full Depth Reclamation 0.06 Gal/SY
  • HMA SMA 2.47 Gal/Ton
  • Heating Scarifying 0.44 Gal/SY
  • Cold Bituminous Pavement Recycle 0.01
    Gal/SY/Inch depth
  • Concrete Pavement 0.03 Gal/SY/Inch depth

10
WYDOT Fuel Adjustment Specification
  • Optional for all WYDOT Projects
  • Based on Index Prices posted by WYDOT on the Web
    Page. Index is from OPIS.
  • Contains a 7.5 Buffer area
  • Adjustments are Positive and Negative

11
WYDOT Fuel Adjustment Specification
  • Contractor submits Affidavit (Form E-12) with
    their signed contract
  • Establish of Contract for Fuel items
  • Based on affidavit and original contract total
  • Computed
  • (Affidavit Cost/Original Contract Cost) x 100
  • For each product (Unleaded, Diesel, Burner)
  • Will remain the same for the life of the contract

12
Affidavit of Fuel Cost for Project
13
WYDOT Fuel Adjustment Specification
  • Unleaded and Diesel Fuels eligible for adjustment
    at every Estimate
  • Burner Fuels eligible for adjustment only on
    those Estimates where paving or crack sealing
    happened

14
WYDOT Fuel Adjustment Specification
  • Adjustments are made only when the index price
    changes by more than 7.5
  • Base Fuel Index (BFI) established previously
  • Current Fuel Index (CFI) price for month prior
    to the date of the Estimate

15
WYDOT Fuel Adjustment Specification
  • If an adjustment is warranted, it will be
    computed
  • Contract x Estimate Amount x (Change0.075)
  • Adjustments are made on each Estimate

16
2009 ???
  • CDOT and CCA have had discussions regarding
    revising the Fuel Cost Adjustment specification
    again.
  • CCA is currently researching fuel factor data for
    the existing items and any additional items they
    may wish to request

17
CDOT Asphalt Cement Cost Adjustment
  • Joint Task Force with CDOT, FHWA and CAPA worked
    to develop a specification
  • First implemented in 2007 as a pilot project as
    an option to the Contractors on 6 projects
  • Index was the spot price per barrel of Western
    Canadian Select Crude Oil as published by Encana
  • Trigger was 5
  • Payment based on the quantities for HMA and SMA

18
CDOT Asphalt Cement Cost Adjustment
  • In 2007 none of the Contractors optd In and no
    data was gathered
  • In 2008 the specification was again offered as a
    pilot until July.
  • In July 2008 as a response to the asphalt cement
    price volatility CDOT implemented the Asphalt
    Cement Cost Adjustment specification as a
    Standard Special Provision on all projects with
    HMA or SMA. The cost adjustment specification is
    mandatory, not at the contractors option.
  • No change in the index or trigger from the pilot
    specification has been made.

19
WYDOT Adjustment for Performance Graded Asphalt
Binder
  • Current Specification implemented in 2009
  • Reaction to extreme escalation in price
  • Also reaction to supply issues within the state
  • Includes adjustment for Chip Seal oils

20
WYDOT Adjustment for Performance Graded Asphalt
Binder
  • Mandatory for all WYDOT Projects with PG Binders
    and Chip Seal oils
  • Based on Index Prices posted by WYDOT on the Web
    Page. Index based on wholesale prices.
  • Contains a 10 Buffer area
  • Adjustments are Positive and Negative

21
WYDOT Adjustment for Performance Graded Asphalt
Binder
  • The Contractor provides an Affidavit (Form E-14)
    and a confidential bid price at the beginning of
    the project.

22
Affidavit of PGAB Price
23
WYDOT Adjustment for Performance Graded Asphalt
Binder
  • Adjustments are made only when the index price
    changes by more than 10
  • If an adjustment is warranted, it will be
    computed
  • (PPI-BPI) x 0.90 x Tons of Binder
  • Adjustments are made on each Estimate

24
WYDOT Adjustment for Performance Graded Asphalt
Binder
  • Additional adjustments are allowed for projects
    that go beyond one construction season.
  • Adjustment is based on Confidential Bid Price
    received from the Contractor (AAF)
  • If an adjustment is warranted, it will be
    computed
  • AAF x (PPI-BPI) x 0.90 x Tons of Binder

25
Sharing of the Risk
  • Cost adjustment specifications not designed for
    the DOT to assume all of the risk
  • Contractors still have to bid risk at least up to
    the trigger
  • Also have to consider downward movement of the
    price
  • CDOT index still based on crude oil price, not
    asphalt cement price, as requested by CAPA
  • Cost adjustment only on HMA or SMA, not
    emulsified items

26
Sharing of the Risk
  • DOTs advertise projects in winter to allow
    contractors and suppliers to plan their work for
    the next construction season
  • The longer the period between bid and actual
    construction the greater the risk the index will
    fluctuate the greater the risk to both parties

27
WYDOT Specifications and Formswww.dot.state.wy.us
  • Specifications
  • Forms Index Prices
  • Information Central
  • Manuals and Publications
  • 2003 Standard Specifications
  • Supplemental Specifications
  • Working With WYDOT
  • Contractor Information
  • Contractor Forms
  • or
  • 3. Base Index Prices

28
Questions?
Dennis Largent, P.E. Project Development Branch,
Area Engineer dennis.largent_at_dot.state.co.us
Mark W. Ayen P.E. WYDOT Construction Staff
Engineer mark.ayen_at_dot.state.wy.us
Write a Comment
User Comments (0)
About PowerShow.com