Summary of Open Work Orders and Recent Problem Reports - PowerPoint PPT Presentation

1 / 9
About This Presentation
Title:

Summary of Open Work Orders and Recent Problem Reports

Description:

Number Closed out = 1119 (98.7% closure rate) Number open = 14 (as of 8/4/00) ... Work In Closure Process = 16 (Procedure error and database update) 1 (EGSE) ... – PowerPoint PPT presentation

Number of Views:26
Avg rating:3.0/5.0
Slides: 10
Provided by: bryant4
Category:

less

Transcript and Presenter's Notes

Title: Summary of Open Work Orders and Recent Problem Reports


1
Section 8 Summary of Open Work Orders and Recent
Problem Reports
. . . Mark Perry EO-1 Spacecraft Systems
Engineer, Swales Aerospace, Inc.
2
Work Order Status
  • Total number generated from start through 8/4/00
    1133
  • Number Closed out 1119 (98.7 closure rate)
  • Number open 14 (as of 8/4/00)
  • Work In Process 1
  • Problem Reports 2 (S-Band Transponder 1)
    ( Hyperion CAL Lmap 1)
  • Redbook Item WOAs 5 (each discussed in depth)
  • WOAs in closure process 6

3
60 PRs During the T/V Test
  • 8 PRs relating to hardware problems
  • 7 PRs for the S-band Transponder (AGC anomaly)
  • 1 PR for degradation of the Hyperion primary
    calibration lamp
  • 29 nominal conditions initially perceived as an
    error
  • Includes noisy A/D converter data, limit
    violations, high temperatures, TSM tripping,
    error counters, telemetry delays, event messages,
    low voltages
  • 12 errors, including 8 procedure errors and 4
    operator errors
  • 3 GSE problems ASIST, FEDS, and UPS
  • 1 database PSE half-voltage FDC calibration
  • 7 still under investigation (PR number in
    parentheses)
  • Cold X-band (1099-20-2)
  • LEISA telemetry drop-out (1099-20-12)
  • 3 WARP S/W bus error counters (1099-20-15,
    1101-20-9, 1102-20-5)
  • S-band RF temperature telemetry momentarily went
    to maximum value (1101-20-4)
  • Momentarily low voltage on Hyperion 5-volt supply
    (1102-20-8)
  • None of the PRs under investigation are
    considered significant

4
Open Problem Report Status
  • Total number generated from start through 8/4/00
    1696
  • Total number generated since Red Team Review
    124
  • Number Closed out 1664 (98.0 closure rate)
  • Number open 32 (as of 8/4/00)
  • Work In Closure Process 16 (Procedure error and
    database update)
    1 (EGSE)
  • Test verification required 9 (S-Band
    Transponder)
  • To be resolved 1 (TRW CAL Lamp Problem)
  • Redbook Items 5
  • WOA 468-20-4 IRU Helium Exposure (see ACS
    Subsystem)
  • WOA 512-150-1 X-Band Frequency Shift (see RF
    subsystem)
  • WOA 572-30-10 Bus Chassis Current Exceeding
    .925mA (see Electrical Subsystem)
  • WOA 770-20-3 One Time Event Chassis Current
    during EMC Testing (see Electrical Systems)
  • WOA 837-20-1 One Time Event LVPC Current Red
    Limit (see Power Subsystem)

5
Quality Assurance Spacecraft Bus ElementsSummary
of Open PRs as of 8/4/00
  • Hardware
  • S-Band AGC anomaly (9 separate PRs generated)
  • Degradation of the primary calibration lamp on
    Hyperion (1 PR generated)
  • Procedure Error / IT Database Problem
  • 16 PRs will be closed once the paper work is
    completed.
  • 1 PR EGSE (In process of closure)
  • Redbook Items
  • 5 PRs as discussed earlier
  • Negligible residual risk due to the open PRs

6
Quality Assurance Spacecraft Bus Elements
Pre TV 2
Open Problem Reports
7
Quality Assurance Spacecraft Bus ElementsOpen
Problem Reports (continued)
8
Quality Assurance Spacecraft Bus ElementsOpen
Problem Reports (continued)
9
Closure Plan
  • All WOAs and PRs to be closed before shipment to
    the launch site.
  • Exception will be the WOAs and PRs related to the
    S-Band AGC anomaly and Redbook items.
  • Continue use of the WOA and PR system at the
    launch site.
  • Any new PRs to be closed before launch, or added
    to the Redbook with concurrence of GSFC and
    Swales quality teams.
Write a Comment
User Comments (0)
About PowerShow.com