Title: XML Working Group
1XML Working Group
- Joan Ugljesa
- NDIA PMSCMay 3, 2006
949-609-2999jugljesa_at_aimcorp.biz
2Topics
- Background
- Review development steps and current plan
- Current work product
- Current events
- List of URLs
3Background
- Whats the purpose?
- Replace the existing ANSI X12 Electronic Data
Interchange (EDI) transaction sets (806 and 839)
with an XML equivalent - Provide means to exchange schedule, cost, and
related auxiliary data in a standard format - Address formal government contractual
requirements - Facilitate data exchange for all parties
subcontractors, prime contractors, customers,
program offices, internal management
4Whats the End Objective?
- A library of XML schedule, cost, and auxiliary
data components (XML schemas) that can be used by
the project management community - Formal, published international standard (ISO,
UN/CEFACT) that can be cited in contracts and
requirements - Software vendor neutral format
- Prevent new projects from reinventing the wheel
use standards based XML components in a web
services environment - Consistent, standard approach means you save time
and money
5UN/CEFACT Development Steps
- Project definition
- Use Case Description (participants, process)
- Use case as UML model (basis for data model), UML
activity diagram (sequence of events) - Business Requirements Specification with high
level data models - Requirements Mapping Specification (detailed data
description) - Add any missing core components (ISO standard)
- Harmonization
- Schemas generated based on CEFACT design rules
- Complete - In UN/CEFACT review process
6Development Plan
7Current Work Products
- Business Requirements Specification (BRS)
approved - Report approved status to XML.gov
- Requirements Mapping Specification (RMS) detail
data model, beginning harmonization process - Initial review May interim meeting
- Subsequent review August interim meeting
Purpose of XML.gov is to support the directives
in the E-Government Act of 2002, means the
schemas will eventually be part of their federal
database of registered components
8BRS - Business Process
- The Participants
- Customers
- Government Agency
- Contractor
- Internal Management
- Data Sources
- Supplier
- Contractor
- Government Agency Program Office
Types of data exchange interactive, data
subsets, and complete set
9BRS/RMS - Information Areas
- Produce targeted schemas for specific data
exchange purpose - Can be used alone or combined
- Includes
- Schedule data activities, milestones,
relationship details, resource assignment details - Cost data - Budget, actual, earned value,
estimate (cumulative/at complete or time phased) - Contract and project summary data
- Funding data
- Auxiliary data reporting structures, calendars,
resources, thresholds
10Current Events
- Have conducted in depth reviews of the Business
Requirements Specification and data model
contents with various project management software
vendors including - Artemis
- Business Engine (MPM)
- C/S Solutions
- Dekker
- Welcom/Deltek
- Also provided draft schemas for review and comment
Primavera is scheduled for May 11
11Current Events
- AIA eBusiness Steering Group (eBSG)
- Monitoring progress of standards development,
proof of concept activities - Offering assistance with adoption and
implementation - Normal process for this group
- Identify standards that the industry can use
- Recommend adoption
- Provide guidelines or recommendations on use
NDIA PMSC has the opportunity to assist in the
development of these guidelines
12AIA EEIC Standards Development Radar Screen
FIPS 201
Active AIA Project
EIA-927
TSCP
Adopt existing standard
SAML
AIA Guidelines
IADFA
PLCS
Certipath
Monitor external development
Position of unadopted blips is provisional
STEP
PKI
X12 EDI
GECA Template
GTPA Template
RFID
Supplier UID
UDEF
ebXML
PM/EVM
Adopted
Clickable GTPA
Participate in external development
AIA development
Candidate
Boost Aero
Track
As at 2006-02-27