Infrastructure Investment Management Mike Morrisroe Business Area Manager Water Networks - PowerPoint PPT Presentation

1 / 24
About This Presentation
Title:

Infrastructure Investment Management Mike Morrisroe Business Area Manager Water Networks

Description:

Optimise using risk - cost & service constraints. Continuous base data ... MWH Tim Watson, Chris Bros, Robert Gaskin. MWHSoft Paul Boulos. Acknowledgements ... – PowerPoint PPT presentation

Number of Views:47
Avg rating:3.0/5.0
Slides: 25
Provided by: nickgo1
Category:

less

Transcript and Presenter's Notes

Title: Infrastructure Investment Management Mike Morrisroe Business Area Manager Water Networks


1
Infrastructure Investment ManagementMike
MorrisroeBusiness Area ManagerWater Networks
2
Knowledge - Planning - Implementation
  • Water Waste Water Networks
  • Risk based assessment
  • Bottom up approach
  • Investment planned at asset level
  • Transparent process
  • Use of constraints
  • Supports Continuous improvement

Implement
Track costs and effects of implementation,
improve data
Infrastructure Risk Management (IRM)
Planning
Knowledge
Optimise using risk - cost service constraints
Continuous base data improvement
3
IRM is a modular approach to optimising
investment and serviceability
PROBABILITY
CONSEQUENCE
RISK


4
Burst probability modelSample of predictor
variables
  • Length (offset)
  • Material
  • Diameter
  • Region
  • Customer density (large variability)
  • Pressure (AZNP)
  • Customers/metre (large variability)
  • Temporal and environmental
  • Others not selected we started with 20!

5
Burst probability modelMaterial and age strongly
correlated
  • Two models were developed
  • Current state of pipes
  • Future deterioration

6
Burst probability modelGood correlation with raw
burst data
7
IRM is a modular approach to optimising
investment and serviceability
x

PROBABILITY
CONSEQUENCE
RISK
UITS Duration Model
Impact Methods
Burst Model

Serviceability
UITS Probability
Dependent Customers
Burst Rate
x

x
x

8
UITS modelsServicability score depends on UITS
duration
  • function of
  • UITS events gt 6 hours
  • UITS events gt 12 hours
  • UITS events gt 24 hours
  • Requires pipe-level probability of UITS duration
    to calculate overall Servicability

9
UITS modelsRepair durations follow lognormal
distribution
24
0
24
0
10
UITS modelsDuration function of material and size
1.0
0.2
0.6
11
IRM is a modular approach to optimising
investment and serviceability
x

PROBABILITY
CONSEQUENCE
RISK
UITS Duration Model
Impact Methods
Burst Model

Serviceability
UITS Probability
Dependent Customers
Burst Rate
x

x
x

12
MWHSoft Developed The InfoWater Pipe/Valve
Criticality Module (VCM)
The VCM module automatically assesses the
criticality of each asset on the network model
during a single batch run
13
Pipe/Valve Criticality Theory
  • Each valve can be operated to shut in an area of
    the network upstream or downstream of the valve
    (known as pounds)
  • The upstream or downstream pounds may have a
    different customer impact
  • If the valve fails to operate then both areas
    (combined pound) will need to be closed in to
    isolate the network

14
Identifies Affected Properties
Properties Affected By Valve Closures
Isolated, No Water Or Low Pressure
15
Assigning impact - five customer types
  • Five customer types
  • Geo-referenced
  • Assigned to mains
  • Grouped by pound (see later)
  • OPA Properties D1 D2 D3 D4 D5

16
Identify Critical Assets
HIGH IMPACT ASSETS AS A OF ALL ASSETS
Sum of Isolated, No Water Low Pressures
Properties Valves With Initial Flow And No Flow
10000
8000
All Assets Diameter gt 200mm Diameter gt 450mm
6000
NUMBER OF PROPERTIES AFFECTED
4000
2000
0
4.0
5.0
7.0
9.0
10.0
0.0
1.0
2.0
3.0
6.0
8.0
PROPORTION OF ALL ASSETS
17
IRM is a modular approach to optimising
investment and serviceability
x

PROBABILITY
CONSEQUENCE
RISK
UITS Duration Model
Impact Methods
Burst Model

Implement Plan gt Serviceability
Serviceability
UITS Probability
Dependent Customers
Burst Rate
x

x
x

18
Many GIS elements make a pipe string
  • Pipe strings
  • Same diameter
  • Same material
  • Same age
  • Same contractor
  • Same ground conditions
  • Same lifetime pressure
  • Connected elements
  • Same deterioration rate?
  • Same replacement date?
  • Intelligent cohorts?

19
Risk at GN pipe level
20
Selected Pipes (superstrings)
21
Superstrings are suboptimal but in reality
22
Optimised Capital Expenditure
Serviceability
Budget
23
Knowledge - Planning ImplementationBusiness as
Usual
Implement
Infrastructure Risk Management (IRM)
Planning
Knowledge
24
Infrastructure Investment ManagementMike
MorrisroeBusiness Area ManagerWater Networks
25
Acknowledgements
  • Scottish Water Mark Petrie, Greg Hay
  • Thames Water Rob Casey
  • MWH Tim Watson, Chris Bros, Robert Gaskin
  • MWHSoft Paul Boulos
Write a Comment
User Comments (0)
About PowerShow.com