INTRODUCTION TO FEMAS ENVIRONMENTAL PLANNING - PowerPoint PPT Presentation

1 / 36
About This Presentation
Title:

INTRODUCTION TO FEMAS ENVIRONMENTAL PLANNING

Description:

... to have any impact on the environment, barring extraordinary circumstances. ... the environment, barring extraordinary circumstances, as long as ... – PowerPoint PPT presentation

Number of Views:48
Avg rating:3.0/5.0
Slides: 37
Provided by: booza65
Category:

less

Transcript and Presenter's Notes

Title: INTRODUCTION TO FEMAS ENVIRONMENTAL PLANNING


1
INTRODUCTION TO FEMAS ENVIRONMENTAL PLANNING
HISTORIC PRESERVATION (EHP) COMPLIANCE
REQUIREMENTS
2
FEMAs EHP Review
  • It is FEMAs policy to integrate environmental
    and historic preservation considerations into its
    emergency preparedness, hazard mitigation,
    disaster planning, and response and recovery
    activities.
  • This work is accomplished through FEMAs
    Environmental Planning and Historic Preservation
    (EHP) Compliance Requirements process.

3
What are potential EHP compliance considerations?
  • Endangered Species
  • Cultural Resources
  • historic properties districts
  • archaeological sites
  • Air water quality
  • Habitat
  • Fish Wildlife
  • Floodplains
  • Wetlands
  • Coastal Zones
  • Agricultural Lands
  • Geology
  • Environmental Justice
  • Land Use
  • Hazardous Materials
  • Traffic

4
Potential Environmental Impacts
  • New ground disturbance activities
  • Air/water pollution
  • Habitat destruction
  • Impacts to breeding
  • feeding areas or patterns
  • Altered viewsheds
  • Alteration of historic properties districts

5
FEMAs EHP Compliance Review
  • Overseen by FEMAs Office of Environmental
    Planning and Historic Preservation (OEHP)
  • HQ office in Washington, DC
  • Ten Regional offices
  • Regional Environmental Officer some support
    staff
  • EHP compliance is the responsibility of FEMA
    Grant Programs OEHP serves as a technical
    support office

6
Who is OEHP
  • FEMAs Office of Environmental Planning and
    Historic Preservation (OEHP) engages in a review
    process to ensure that FEMA-funded projects and
    activities comply with various Federal laws to
    include
  • National Environmental Policy Act (NEPA)
  • National Historic Preservation Act (NHPA)
  • Endangered Species Act (ESA)
  • Clean Water Act (CWA)
  • Clean Air Act (CAA)
  • Coastal Zone Management Act (CZMA)
  • Coastal Barrier Resources Act (CBRA)
  • Migratory Bird Treaty Act (MBTA)
  • Magnuson-Stevens Fishery Conservation and
    Management Act (MSA)
  • Executive Order 11988 Floodplains Management
  • Executive Order 11990 Wetland Protection
  • Executive Order 12898 Environmental Justice

7
EHP Laws and Executive Orders The basis for
FEMAs EHP Review
Endangered Species Act
Executive Orders
Environmental Justice
National Historic
Floodplains
Preservation Act
Wetlands
NEPA
Clean Air Act
Coastal Barrier
Clean Water Act
Resources Act
Resource Conservation
Coastal Zone
Recovery Act
Management Act
8
FEMAs EHP Compliance Review
  • Is required by Federal laws, regulations and
    Executive Orders
  • Ensures FEMA actions, including grant-funded
    projects, are in compliance with EHP requirements
  • Review must be complete before work is initiated
    and any project is funded
  • Grantee must comply with any conditions placed on
    project as result of EHP review

9
FEMAs EHP Compliance Review
  • The goal of the environmental compliance
    requirements is to protect our nations water,
    air, coastal, fish and wildlife, agricultural,
    historical, and cultural resources, as well as to
    minimize potential adverse effects to children,
    low-income, and minority populations
  • Submitted environmental requests assists the
    federal government in making informed decisions

10
FEMAs EHP Compliance Review
  • May require consultation with resource and
    regulatory agencies, including
  • State Historic Preservation Office
  • US Fish and Wildlife Service
  • US Army Corps of Engineers

11
FEMAs EHP Review
  • May require preparation of written analyses or
    agreements required under EHP laws, including
  • - Environmental Assessment (NEPA)
  • - Biological Assessment (ESA)
  • - Memorandum of Agreement (NHPA)
  • Some EHP laws and EOs require public involvement
    a public comment period

12
Environmental Review Conditions
  • An environmental review must be completed prior
    to the initiation or completion of any project
    work.
  • Initiating work before an environmental review is
    completed may result in a non-compliance finding
    and the withholding of grant funds.
  • All changes to the scope of work (SOW) of a
    project must be resubmitted for environmental
    review.
  • If an approved project has a change in the SOW,
    the grantee must stop work and wait for the
    environmental review to be completed and approved
    on the new SOW before re-initiating work.

13
Consequences of Non-Compliance
  • Project delays
  • Denial of funding
  • De-obligation of funding
  • Negative publicity
  • Civil penalties
  • Lawsuits

14
Environmental Review Process
  • Grantee submits project request through the
    SAA/FA/Tribal Government/Private Entity
  • SAA/FA/Tribal Government/Private Entity reviews
    project request and submits electronically to PA
  • PA ensures all necessary documentation is
    included in grant application and submits a
    complete file to GPD/EHP liaison with EHP
    Documentation Memo
  • GPD/EHP liaison reviews documentation and
    confirms likely environmental impact, if any
  • If project/action does not require further
    environmental review (i.e equipment, training),
    grant will be approved as a Categorical Exclusion
    (CATEX) and PA is notified and given approval
    documentation or by email
  • If project/action does require further
    environmental review it will be forwarded to EHP
    which will work with the REOs.
  • GPD/EHP liaison will notify applicants PA of
    EHPs decision
  • If approved, PA will be given approval
    documentation for communication to grantee
  • If additional documentation is requested, grantee
    will be notified by PA

15
Projects that can be CATEXd
  • Project types/actions that are not likely to have
    any impact on the environment, barring
    extraordinary circumstances.
  • Purchases of equipment including vehicles, boats,
    ID cards, hand-held or portable equipment,
    navigation or communication equipment, or other
    supplies for mobile units. (Note Please provide
    information on how the equipment will be
    installed)
  • Classroom and web-based training, conferences and
    workshops conducted within enclosed facilities.
  • Personnel, administrative, fiscal and management
    activities that involve no resources other than
    manpower and/or funding.

16
CATEXs (Continued)
  • Installation of security measures on mobile units
    (buses, train cars, ferries, etc.) that are less
    than 50 years old and are not national landmarks.
  • Development, revision, documentation, and/or
    distribution of regulations, directives, manuals,
    information bulletins, and other guidance
    documents.
  • Technical assistance activities that involve no
    resources other than manpower and/or funding.
  • Field-based training activities and exercises
    that use existing facilities, established and
    approved procedures, and conform with existing
    land use designations.

17
Projects requiring initial review then CATEXd
  • Project types/actions that are not likely to have
    any impact on
  • the environment, barring extraordinary
    circumstances, as long as
  • certain project conditions are met (i.e. no
    ground disturbance). If
  • those conditions are not met or extraordinary
    circumstances exist, then
  • the project must be submitted for EHP review.
    General conditions are
  • listed below, followed by specific project types
    and their conditions.
  • Project does not directly or indirectly involve
    any new ground disturbing activities such as
    utility/sewer/electric lines or other underground
    conduits, fencing, gates, poles, foundations,
    etc.
  • Project does not involve new construction
    (Emergency Operations Center EOC, guard
    station, fire station, equipment shed,
    dock/wharf, communication tower, etc.).

18
Preparedness Project Types that Trigger EHP Review
  • Communication towers
  • New construction
  • New ground disturbance activities
  • Modification of buildings and structures 50
    years old impacts on historic districts

19
Communication Towers
  • Consider all elements of project
  • Tower location, height and design
  • (lattice or guy wires)
  • Use of aviation lighting
  • Security fencing and lighting
  • Equipment building
  • Access road
  • Equipment staging area


20
New Construction
  • Examples
  • Security guard building
  • Dock/pier
  • Boat house
  • Road
  • Towers

21
New ground disturbance activities
  • Examples
  • Installation of physical security enhancements
    including fencing, lighting,
    cameras, pedestrian or vehicle
  • barriers, etc.
  • In particular
  • Does the project involve new ground
  • disturbance activities?

22
Modification of Buildings Structures 50 Years
Old
  • Examples
  • Equipment installation (e.g. physical
    security/access controls) on, in, or in the
    vicinity of historic buildings, piers, bridges,
    ferries, rail cars, etc.
  • Building renovation/hardening (e.g. doors, gates,
    windows)


23
Tips for a Timely EHP Review
  • Take EHP considerations into account during
    project planning and budgeting
  • Easier to avoid or resolve issues if identified
    early
  • Reach out to state resource agencies early
  • Provide detailed project Statement of Work to
    FEMA
  • See Information Bulletin 271
  • What work is being proposed, where will it take
    place, and how will it be carried out?

24
Tips for a Timely EHP Review
  • Be aware that EHP review may increase timeline
    for project implementation
  • Grant funds may be used for preparation of EHP
    reports
  • Notify FEMA if Ports Master Plan included
    previous environmental analysis or public
    involvement, and provide any such documentation
    to FEMA

25
Project Planning
  • The following factors affect the amount of time
    it takes to complete the EHP Review
  • completeness of the project Statement of Work
    (SOW)
  • complexity of the project
  • project location the types of resources
    affected
  • whether consultation with SHPO, FWS. etc.
    (required under certain laws) is needed

26
Roles and Responsibilities
  • FEMAs Grant Programs Directorate
  • Incorporates EHP compliance requirements into
    grant programs and processes
  • Conducts initial screening of projects for EHP
    considerations (i.e. identification of potential
    impacts to natural or biological resources or
    historic properties)
  • Submits complex projects to FEMAs Office of
    Environmental Planning and Historic Preservation
    (OEHP) for further review, if appropriate


27
Roles and Responsibilities
  • FEMAs Office of Environmental Planning
    Historic Preservation
  • Conducts and documents the EHP compliance review
    of those GPD-funded projects with potential to
    impact the environment or historic properties
  • Consults with resource and regulatory agencies
  • Provides policy guidance and subject matter
    expertise to support GPDs EHP compliance
    responsibilities
  • Identifies opportunities to improve integration
    of EHP requirements into FEMA programs


28
EHP Review of Port Security Grant Program (PSGP)
Projects
  • Since integration into FEMA in April 2007
  • 70 FY04-07 PSGP projects submitted to OEHP for
    review
  • 45 reviews completed


29
Information Bulletin No. 271
  •  TO All State Administrative Agency Heads
  • All State Administrative Agency Points of Contact
  • All State Homeland Security Directors
  • Transit Security Chiefs
  •  
  • FROM Tracey Trautman, Director
  • Grant Development and Administration, Grant
    Programs Directorate
  •  
  • SUBJECT Environmental Planning and Historic
    Preservation Requirements for Grants
  •  
  • This Information Bulletin (IB) provides general
    guidance to grantees on environmental planning
    and historic preservation (EHP) requirements for
    grant funded projects involving communication
    towers, physical security enhancements, new
    construction, renovation, and modifications to
    buildings and structures that are 50 years old or
    older. This IB applies to all such projects
    (regardless of Fiscal Year award) funded by the
    Homeland Security Grant Program (HSGP), the
    Infrastructure Protection Program (IPP), and the
    Emergency Management Performance Grants Program
    (EMPG). These projects have the potential to
    affect environmental resources and historic
    properties through ground disturbance, impact to
    wetlands, floodplains, coastal zones, and other
    water resources, alteration of historically-signif
    icant properties, and impact to threatened and
    endangered species and migratory birds.
    Consequently, FEMA engages in a compliance review
    process to ensure proposed projects comply with
    applicable federal EHP laws, regulations, and
    Executive Orders.

30
Information Bulletin No. 271 Continued Statement
of Work
  • Statement of Work
  • A Statement of Work (SOW) is required to be
    developed and submitted to FEMA prior to the
    initiation of projects referenced in this IB.
    Essential elements and information to include in
    the SOW are
  • Basic project information (name of project, name
    of grant and grantee, grant award number, fiscal
    year, overall purpose and scope of the project,
    estimated cost, etc.).
  • Precise location of the project (street address,
    city, and state, or latitude and longitude
    coordinates).
  • Visual documentation (site/structure photographs
    plans/drawings that define the size and precise
    location of proposed work US Geological Survey
    topographic, flood and wetlands maps aerial
    photographs, etc.).
  • Description of the project, including (as
    applicable)
  • Dimensions/acreage/square footage of structure
    and/or land affected, with height and structural
    support information for all communication towers.
  • Extent and depth of ground disturbance for new
    construction and structure modification,
    including trenching for utility lines,
    installation of fencing and light posts, tower
    footings and pads, etc.
  • Special elements of the project, including
  • Special equipment that will be used, staging
    areas, access roads, easements, etc.
  • Extent of structural modification.

31
Information Bulletin No. 271 Continued Statement
of Work
  • Year affected building/structure was built (if
    applicable).
  • Information about features, resources, and
    potential adverse impacts at or near the site,
    including
  • Water bodies (rivers, lakes, streams, wetlands,
    etc.).
  • Floodplains.
  • Historic and cultural resources (historic
    districts, buildings, landscapes, bridges, piers,
    dams, archaeological sites, etc.).
  • Migratory birds.
  • Threatened and endangered species and/or critical
    habitat.
  • Vegetation, including general types of plants,
    trees, or lack thereof.
  • Geologic features.
  • Tribal cultural and religious sites.
  • Special areas (forests, wildlife refuges,
    reserves, etc.).
  • Any recent or relevant studies, reports, or
    surveys that were prepared for other agencies or
    purposes and provide information on environmental
    resources and/or historic properties in the
    project area.

32
Information Bulletin No. 271 Continued EHP
Requirements
  • Site selection is a key factor that can affect
    the number and complexity of EHP issues that may
    need to be addressed for a project. Grantees are
    responsible for identifying environmental
    resources and historic properties in the project
    area, which may require coordination with
    appropriate local, State and/or Federal resource
    agencies. This information should be included in
    the SOW and submitted to FEMA in the initial
    stage of project formulation.
  • Based on the review of the SOW, FEMA may
    determine that projects with the potential to
    have significant adverse impacts to EHP resources
    and/or public controversy require additional
    evaluation and documentation, and FEMA will
    notify the grantee accordingly. Documents
    required to fulfill compliance responsibilities
    under Federal EHP laws must be prepared by
    qualified professionals with EHP expertise and
    may require a public comment period. Grantees are
    responsible for the preparation of such documents
    as well as for the implementation of any
    mitigation measures identified during FEMAs EHP
    review that are necessary to address potential
    adverse impacts. Costs associated with the
    preparation of EHP documents are allowable grant
    expenditures.
  • Inadequate project descriptions and/or
    documentation of the presence of environmental
    resources and historic properties in a project
    area may cause significant delays in the
    timeliness of the review and affect the projects
    implementation. Failure of the grantee to meet
    all Federal, State and local EHP requirements,
    comply with project conditions established during
    FEMAs EHP review, and/or obtain applicable
    permits and approvals may result in project
    delays or the denial of funding.

33
Information Bulletin No. 271 Continued FEMA EHP
Review Process
  • Grantees must submit SOWs electronically through
    their authorized State SAA (or designee) to their
    FEMA preparedness officer. Preferred submission
    formats are those supported by Microsoft Office
    (doc files), and Adobe Acrobat (pdf files).
    JPEG is the preferred picture format but other
    widely supported file types may be used. Project
    reviews may take several weeks or months to
    complete, so sufficient time and resources must
    be incorporated into the project planning process
    to accommodate EHP requirements. Grantees must
    receive written approval from FEMA prior to the
    use of grant funds for project implementation.
  • Additional information regarding EHP compliance
    requirements for FEMA-funded grant projects is
    available on the FEMA website at
    http//www.fema.gov/plan/ehp/ehp-applicant-help.sh
    tm. Questions may be directed to your designated
    preparedness officer or to the Centralized
    Scheduling and Information Desk at 1-800-368-6498
    or via email at askcsid_at_dhs.gov.

34
Sources of EHP Guidance
  • A variety of information is available at


http//www.fema.gov/plan/ehp
35
Helpful Resources
  • Questions?
  • For more information contact
  • Jeff Hall (202) 786-9778 or jeffrey.hall1_at_dhs.gov

36
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com