Title: MUNICIPAL SYSTEM IMPROVEMENT GRANT (MSIG) MSIG PERFORMANCE PRESENTATION TO SELECT COMMITTEE OF FINANCE (July 2006
1MUNICIPAL SYSTEM IMPROVEMENT GRANT (MSIG) MSIG
PERFORMANCEPRESENTATION TO SELECT COMMITTEE OF
FINANCE(July 2006 Jan 2007) 26 February
2007
2Overview of Presentation
- Purpose of presentation
- Background
- 2006/07 MSIG Framework Outputs
- Financial/Quantitative Performance (Jul 06 Jan
07) - Reason for Variance
- Overall progress
- Quarterly Review Assessment
- Corrective measures
- Ongoing Response strategy to challenges
- Conclusion
3Purpose
- To report to Select Committee on Finance
regarding the performance of the Municipal
Systems Improvement Grant (MSIG) during the
period July 06 to Jan 2007
4Background
- Allocations made to Districts, Local and Metro
municipalities - Allocation for 2006/07 is R 200 million and funds
were transferred to receiving municipalities - MSIG allocations from 2006/07 focused mainly to
Project Consolidate municipalities - Total coverage of receiving municipalities
increased from 198 to 211 municipalities - All 211 municipalities submitted activity plans
for their allocated amounts
52006/07 MSIG Framework outputs
- 1. Local Economic Development and Spatial
Development - - The development of Spatial Development
Frameworks, LED strategies, - procedures and policies
- 2. Financial Viability
- - Support the pilot Project Consolidate
initiative to develop holistic customer - care (billing) systems and specific
revenue enhancement initiatives. - - Annual Financial Statements support -
municipalities that have failed to do - so over the past two years.
-
- 3. Institutional Transformation and development
- - Support to PIMS Centers.
- - Implementation of Section 78 of MSA - division
of powers and functions - - Implementation of Performance Management
Systems - - Review of IDPs and alignment with Budgets and
Provincial Growth - Development Strategies
- - Skills development
- 4. Good Governance
6Quantitative Performance as at Jan 2007
Prov No of munics Allocated (millions) Transferred 06/07 (millions) Actual Exp (millions) Exp in
E.C 35 28,244 28,244 6,526 23.1
FS 18 17,172 17,172 5,741 33.4
GT 8 9,034 9,034 5,411 59.9
KZN 45 39,886 39,886 11,377 28.5
Limp 22 22,148 22,148 9,584 43.3
MP 21 23,742 23,742 12,960 54.6
NC 27 20,910 20,910 5,771 27.6
NW 19 21,542 21,542 4,644 21.6
WC 16 17,322 17,322 6,242 36
Total 211 200 000 200 000 68,256 34.1
7Reasons for variance
- Difference in the timing of the projects
capacity building projects allocated different
implementation timeframes within the financial
year across all municipalities ie some projects
to be executed between Feb 2007 and June 2007 - Some projects are continuing over from 2005/06
and payments made from that financial year
allocation delays the starting of 2006/07
projects implementation/expenditure
8Overall Progress LED Spatial Dev
- GIS system completed eg. Knysna LM
9Overall Progress Financial Viability
- Municipalities are implementing the first phase
of the Municipal Property Rates Act appointing
valuers, development of rates policies, data
cleansing and land audit - Conversion to GRAP eg Moqhaka, Emakhazeni,
Thabazimbi etc - Implementation of the billing systems ie Nelson
Mandela Metro, Greater Kokstad - Improvement of indigent registers to cover the
rural areas eg. Richmond LM - Compiled financial management policies such as
cash and investment policies, tariff etc
Thulamela, KSD, Emalahleni, Merafong, Matjhabeng,
etc - Appointed service providers and financial
technicians to complete and review the Annual
Financial Statement eg. Nkandla, Cederberg
10Overall Progress Institutional Transformation
Development
- Some municipalities completed the IDP reviews for
the next five years eg. Overberg District
municipalities - Municipalities using the funds to develop
anti-corruption strategies - Supporting the implementation of PIMS centres
workplans in all the Districts.
11Overall Progress Good Governance
- Training of ward committees all the
municipalities in all provinces
12Quarterly Review Assessments
- There is overall capacity to spend the allocation
but municipalities indicate the lack of capacity
to report - Interoperability of units within the municipality
remains a challenge with regards the MSIG
projects implementation and accountability - Some planned projects linked to other funding
sources thus resulting in duplication and
non-expenditure of MSIG allocation
13Corrective measures
- Letters of non-compliance continually sent to all
non reporting municipalities - Opened opportunity for municipalities to revise
their approved activity plans - Standardised MSIG as an item of the LG CFO forums
to communicate and encourage reporting
presentation on the DoRA and MFMA requirements - Sharing of information with provinces and
districts MSIG Activity plans and reports - Promotion of shared services approach ie Audit
Committees, Property valuation - Using of Service Delivery Facilitators (SDFs) to
improve implementation of MSIG projects and
reporting
14Ongoing Response strategy to challenges
- Redesign the reporting regime on the grant
- Monthly Expenditure reports not to serve only the
purpose of NT reporting but designed to capture
progress on projects identified in the activity
plans - Introduce productive and participative mechanisms
and processes - Mainstream Provincial MSIG Activity Plans
workshops facilitated by LG Depts - Re-introduce Quarterly Review Workshops
facilitated by LG Depts and the dplg output
managers - Strict application of the DORA in terms of
withholding of allocations in case of material
non-compliance ie not reporting on the progress
and expenditure
15Conclusion
- Quarterly review workshops are instrumental to
improving progress and interaction amongst dplg,
province and municipalities - The MSIG performance is satisfactory and
improving on a monthly basis.
16