Title: Ryan Hamel


1
Erosion Control
  • Ryan Hamel
  • Frontier El Dorado Refining Company
  • KSU PPI Intern
  • Summer 2006

2
Outline of Presentation
  • Company Background
  • Researched Process
  • Scope of the Project
  • Recommendations
  • Potential Benefits and Cost Savings
  • Internship Pros and Cons
  • Questions

3
Company Background
  • FEDRC owned by Frontier Oil Corporation
  • Fortune 500 Company (496)
  • 7th best performing stock of all companies listed
    on the New York stock exchange (2005)
  • FEDRC employs 400 Frontier personnel and 100
    contractors

4
Company Background
  • FEDRC situated on 1,000 acre site, which has been
    in operation since 1917
  • Frontier Oil Corp. purchased El Dorado site in
    1999
  • Direct access to pipelines from Canada and
    Cushing, Oklahoma
  • FEDRC produces gasoline, diesel fuels, aviation
    fuels, asphalt, and other petroleum based products

5
Researched Process
  • Reducing Primary Sludge
  • Erosion Control in the Tank Farm
  • Flow of stormwater through tank farm
  • Frequency of flow
  • Connection between channels
  • Stormwater channel characteristics

6
(No Transcript)
7
(No Transcript)
8
Scope of the Project
  • Soil Lost 2500 cubic yards
  • ERE Maps, Tape Measure
  • Estimated Dimensions and Volume
  • Primary Sludge 25,000,000 lbs
  • 1 cubic yard soil weighs 2000 lbs
  • 1 lb soil creates 5 lbs primary sludge

9
Scope of the Project
  • Yearly Sludge Production 1,250,000 lbs
  • 25,000,000 lbs total
  • 50 of erosion occurred in past 10 years
  • 10 of WWTP Sludge in 2005
  • 2005 WWTP Sludge 13,540,022 lbs

10
Recommendations
  • Armor Stormwater Channels
  • Groundcover
  • Global Fill
  • Rock
  • Protecting Inlets and Outlets
  • Procedural Changes

11
Cost Estimate
  • Total Cost 170,000 - 300,000
  • High-Priority Areas (170,000 - 200,000)
  • Entire Area (250,000 - 300,000)
  • Soil makes up 95 of this cost
  • Cost varies according to material use

12
Benefits of Erosion Control
  • Decreased Primary Sludge Generation
  • Improved WWTP Efficiency
  • Increased Capacity to Recycle Other Sludge
  • Decreased Storage Needs
  • Improved Stability of Pipe Rack Foundations
  • SWP3 Compliance

13
Cost Savings
14
Project Results
  • Payback Period 1.2 to 1.7 years
  • Implement Erosion Control in Steps
  • Combine erosion control in the tank farm with
    other practices

15
Internship Pros and Cons
  • Gained experience in a field of interest
  • Worked in environmental department
  • Helped narrow my future career desires
  • Very complex project working primarily on my
    own

16
Questions?