Title: NPCC Review of Resource Adequacy
1NPCC Reviewof Resource Adequacy
- Presented to the
- Planning Advisory Committee
- May 4, 2005
- Westborough MA
- Peter K. Wong
- Manager, Resource Adequacy
2NPCC Document A-2 Basic Criteria for Design and
Operation Of Interconnected Power Systems
- Each Areas probability (or risk) of
disconnecting any firm load due to resource
deficiencies shall be, on average, not more than
once in ten years. Compliance with this criteria
shall be evaluated probabilistically, such that
the loss of load expectation LOLE of
disconnecting firm load due to resource
deficiencies shall be, on average, no more than
0.1 days per year. This evaluation shall make
due allowance for demand uncertainty, scheduled
outages and deratings, forced outages and
deratings, assistance over interconnections with
neighboring Areas and Regions, transmission
transfer capability, and capacity and/or load
relief from available operating procedures.
3NPCC Document B-8 Guidelines for Area Review of
Resource Adequacy
- NPCC has established a Reliability Assessment
Program to bring together work done by the
Council, its member systems and Areas relevant to
the assessment of bulk power system reliability.
As a part of the Reliability Assessment Program,
the Task Force on Coordination of Planning (TFCP)
is charged with conducting reviews of resource
adequacy of each Area of NPCC on an on going
basis.
4NPCC Document B-8 Guidelines for Area Review of
Resource Adequacy
- Assessment period 5 years.
- Comprehensive Review Every 3 years.
- Interim Review annual.
- CP 8 Working Group reviews assumptions and
results and make recommendation to TFCP regarding
the Area review. - Each area is to report its findings with a
presentation and a written report.
5NPCC Guidelines for Area Review ofResource
Adequacy
- Purpose
- The purpose of the presentation associated with
a resource adequacy review is to ascertain that
each Area's proposed resources are in accordance
with the NPCC Basic Criteria for Design and
Operation of Interconnected Power Systems
(Document A-2). - By such a presentation, the Task Force will
satisfy itself that the proposed resources of
each NPCC Area will meet the NPCC Resource
Adequacy - Design Criteria (as defined in Section
3.0 of NPCC Document A-2) over the time period
under consideration. This review by the Task
Force on Coordination of Planning does not
replace Area and/or company responsibility to
assess their systems in conformity with the NPCC
Basic Criteria.
http//www.npcc.org/PublicFiles/Reliability/Criter
iaGuidesProcedures/B-08.pdf
6NPCC Document B-8 Guidelines for Area Review of
Resource Adequacy
- Format of Presentation and Report Comprehensive
Review - Executive Summary
- Briefly illustrate the major findings of the
review. - Provide a summary of major assumptions and
results in table format. - Table of Contents
- Include listing of all tables and figures.
- Introduction
- Reference the previous Area review.
- Compare the proposed resources and load forecast
covered in this review with that covered in the
previous review.
7NPCC Document B-8 Guidelines for Area Review of
Resource Adequacy
- Resource Adequacy Criterion
- State the Areas resource adequacy criterion.
- State how the Area criterion is applied e.g.
load relief steps. - Summarize resource requirements to meet the
criteria for the study period. If tie benefits
are assumed, state their values. - If Area criterion is different from the NPCC
criterion, provide either an estimate of the
resources required to meet the NPCC criteria or a
statement as to the comparison of the two
criteria. - Discuss resource adequacy studies conducted since
the previous Area review, as appropriate.
8NPCC Document B-8 Guidelines for Area Review of
Resource Adequacy
- Resource Adequacy Assessment
- Evaluate proposed resources versus the
requirements to reliably meet - projected electricity demand assuming the Areas
most likely load forecast. - projected electricity demand assuming the Areas
high load growth scenario. - Discuss
- the impact of load and resource uncertainties on
projected Area reliability. - any available mechanisms to mitigate potential
reliability impacts.
9NPCC Document B-8 Guidelines for Area Review of
Resource Adequacy
- Proposed Resource Capacity Mix
- Discuss
- any reliability impacts resulting from the
proposed resources fuel supply and/or
environmental restrictions. - available mechanisms to mitigate any potential
reliability impacts of resource capacity fuel mix
and/or environmental restrictions.
10NPCC Document B-8 Guidelines for Area Review of
Resource Adequacy
- Appendix
- Section A Description of Resource Reliability
Model - Load Model
- Load model and basis for period load shape.
- How load forecast uncertainty is handled.
- How the demand for energy of interconnected
entities within the Area that are not members of
the Area are addressed. - How the effects (demand and energy) of
demand-side management programs are addressed. - Resource Unit Representation
- Unit Ratings
- Definitions.
- Procedure for verifying ratings.
11NPCC Document B-8 Guidelines for Area Review of
Resource Adequacy
- Resource Unit Representation (continued)
- Unit Unavailability Factors Represented
- Type of unavailability factors represented e.g.
forced outages, planned outages, partial
deratings, etc. - Source of each type of factors represented and
whether generic or individual unit history and
provide basis for existing and new units. - Maturity considerations including allowance for
in-service date uncertainty. - Tabulation of typical unavailability factors.
12NPCC Document B-8 Guidelines for Area Review of
Resource Adequacy
- Resource Unit Representation (continued)
- Purchase and Sale Representation
- Describe characteristics and level of
dependability of transactions. - Retirements
- Summarize proposed retirements.
- Representation of Interconnected System in
Multi-Area Reliability analysis - Which Areas and regions are considered.
- Interconnection capacities assumed.
- How expansion plans of other Areas and regions
are considered. - Modeling of Limited Energy Resources
13NPCC Document B-8 Guidelines for Area Review of
Resource Adequacy
- Modeling of Demand Side Management
- Description should include
- In-service date uncertainty,
- Rating,
- Availability,
- Performance and duration.
- Modeling of all Resources
- Description should include
- In-service date uncertainty,
- Capacity Value,
- Availability,
- Emergency assistance,
- Scheduling and delivarability.
- Other Assumptions if applicable
- Internal transmission limitations.
- Maintenance over-runs.
- Environmental constraints.
14NPCC Document B-8 Guidelines for Area Review of
Resource Adequacy
- Appendix
- Section B Other Factors, If Any, Considered in
Establishing Reserve Requirement Documentation - Presentation of summaries of studies performed
within each Area, including references to
applicable reports, summary of reports, or
submissions made to regulatory agencies.
15TFCP Follow Up Procedure
- Prepare brief summary of key issues discussed
during presentation. - Note where further information was requested and
the results of such further interrogations. - Note the Specific items that require additional
study and indicate responsibility for undertaking
these studies. - After the completion of the resource adequacy
review, report on the Areas plans to the
Reliability Coordinating Committee.
16New England Resource Adequacy Review 2005
Schedule
- Last Triennial Review was presented to NPCC in
2002. - 2005 Triennial Review is targeted for submission
to NPCC late summer. - Study results will be presented to PAC in June.
- Draft Triennial Review report targeted for July.
17NPCC Review of Resource Adequacy Cases
- 4 cases will be investigated
- Reference Load Forecast (April 2005 CELT)
- Reference Case Resources and transmission
according to RSP05 assumptions - Sensitivity Case Delay of proposed transmission
upgrade (and generating resource attritions)? - High Load Forecast (higher economic growth)
- Reference Case
- Sensitivity Case
18NPCC Review of Resource Adequacy Scenarios
- Comments regarding the Sensitivity Case
- All proposed transmission projects delayed beyond
the study period (2010) - The Sub-area load increase/effective capacity
decrease incremental curves will serve to show
the impact of unit attrition for sensitivity
purposes. Therefore, may be unit attrition
assumptions are not necessary.
19Questions?