Title: Chart showing existing status of the utilities
1South Asia Energy Regulation Partnership
Executive Exchange Program October 7-9,
2002 Thimpu, Bhutan. Power Sector Regulation and
Regulatory Policy in Bangladesh An
Overview Presented by 1. Md. Mokhlesur
Rahman Khandker, Director General, Power
Cell, Power Division, MEMR, Govt. of
Bangladesh 2. A.S.M. Alamgir Kabir,
Director(Planning Tariff) Power Cell, Power
Division, MEMR, Govt. of Bangladesh 3. K.H.
Masud Siddique, Deputy Secretary, Power
Division, MEMR, Govt. of Bangladesh.
2(No Transcript)
3Present Structure of Power Sector
- Owner Regulator
- Power Division, Ministry of Energy Mineral
Resources - Generation
- Bangladesh Power Development Board (BPDB)
- Private Power Generation Companies (IPPs)
- Transmission
- Bangladesh Power Development Board
- Power Grid Company of Bangladesh Ltd. (PGCB)
- Distribution
- Bangladesh Power Development Board
- Dhaka Electricity Supply Authority (DESA)
- Dhaka Electric Supply Company Ltd. (DESCO)
- Rural Electrification Board through Rural
Electric - Co-operatives
4Bangladesh Power Sector Present Structure
5Present Power System
- INSTALLED CAPACITY 4260 MW
- GENERATION CAPACITY 3300 MW
- MAXIMUM PEAK DEMAND SERVED 3218 MW
- TRANSMISSION LINES (230 132 KV) 3799 KM
- GRID SUB-STATION CAPACITY (132 66 KV) 6595
MVA - DISTRIBUTION LINES (33 KV BELOW) 1,93,196 KM
- SYSTEM LOAD FACTOR 66
- SYSTEM LOSS (TD) 29.60
- CONSUMER NUMBER 6.54 Million
- AVERAGE GROWTH (LAST 10 YRS.) 8
- PER CAPITA GENERATION 136 kWh
- GENERATION MIX
- GAS 90.16
- HYDRO 4.56
- LIQUID FUEL 5.28
- CONSUMPTION
- INDUSTRIAL 44
- COMMERCIAL 7
- DOMESTIC 42
6Current State of Electricity Regulation
- GOB/Power Division Functions as Regulator under
Electricity Act 1910 - Approves investment program
- Monitor performance of the public sector
entities/utilities - Approves Tariff
- Appoint key personnel of the utilities
- Appoint Electrical Advisor and Chief Electrical
Inspector
7Current State of Electricity Regulation (Contd.)
- Chief Electrical Inspector perform duties as
regulator on behalf of the govt. in the following
areas - Provides supply license
- Provides approval for captive generation
- Setup security safety standards and approves
electrical installations in respect of safety
measures - Performs testing inspection function of
electrical installations in respect of security
safety - Presently no provision of stake holders
participation like public hearing in the tariff
approval process by the Govt. - No scope of appeal to the court against Govt.
decision
8Key Constraints of Power Sector Development
- Scarcity of resources hinders development of the
sector - High system losses and accounts receivable
affecting the financial viability of the
utilities - Lack of clear goals, adequate financial and
commercial autonomy and adequate incentive
hinders development - Lack of differentiation of responsibilities for
generation, transmission and distribution is
hindering segment specific corrective measures - Lack of cost and asset accounting system by units
and absence of effective performance evaluation - Existing Tariff lower than cost reflective tariff
9Reform Measures in Recent Years
- GOB has undertaken a series of reform measures
- The National Energy Policy was prepared and
adopted in 1996 - Power Cell was created in 1995 to design,
facilitate and drive reform measures - Private Sector Power Generation Policy was
developed and adopted in 1996, to introduce
competition, induct foreign private capital and
increase power supply - Policy has been adopted in 1998 to promote
small-scale generation in the private sector - REB/PBS started buying electricity from private
sectors
10Reform Measures in Recent Years (Cont.)
- Ashuganj power station corporatization process
started - Govt. approved Haripur (99 MW) Baghabari 100 MW
Power Station to convert into Strategic Business
Unit (SBU) - Draft legislation for setting up of a Regulatory
Commission approved by the Cabinet - Government adopted a well specified power tariff
formula to protect the tariff in terms of real
value - Power Cell completed tariff study and its under
consideration of the govt - Under the Company Act 1994
- Power Grid Company of Bangladesh set up
- DESCO set up as distribution company
- Mixed sector generation company RPC set up
- SBU activities adopted in 47 nos. distribution
divisions of BPDB and DESA - As a part of reforms and restructuring West Zone
Power Distribution Company under BPDB
11Governments Vision
- Long term goals for the power sector
- To make electricity available for all by 2020
- To ensure reliable and quality supply of
electricity - To provide electricity at a reasonable price
12Reforms Objectives
- To bring entire country under electricity service
by the year 2020 - Making the power sector financially viable and
able to facilitate economic growth - Increasing the sectors efficiency
- Making the sector commercial
- Improving the reliability and quality of
electricity supply - Using natural gas as the primary fuel for
electricity generation and exploring the
possibility for export of power to augment and
diversify foreign exchange earnings - increasing private sector participation to
mobilise finance - ensuring reasonable and affordable price for
electricity by pursuing least cost options - promoting competition among various entities
13Reform Strategy
- Segregation of generation, transmission and
distribution into separate services - Corporatization and commercialization of emerging
power sector entities - Creation of Regulatory Commission
- Private Sector Participation
- Introduction of cost reflective tariff structure
- Development of demand management including energy
efficiency measures to conserve energy - Development of alternative/ renewable energy
sources
14Reform Strategy (Contd.)
- Generation
- Separating out all existing power generation
units through a corporatized entity - Under construction and future power stations may
be incorporated as independent company - Generation projects be selected at least cost
option - Generation capacity would be sought through a mix
of public private source - Transmission
- Transmission network will be owned, operated,
planned and developed by a corporatized entity in
the public sector
15Reform Strategy (Contd.)
- Distribution
- Highest in the agenda is to improve the
commercial and financial performance of different
entities. Specific measures to be considered are
- Introduction of consumer voice and organizational
accountability in the form of citizen/ client
charter - The existing distribution system of BPDB and DESA
be transformed into a number of new corporatized
entities - Private capital and management participation in
distribution companies - The rural electric co-operatives (PBSs) under REB
to continue functioning and additional PBSs to be
formed as and when
16Industry Structure of Power Sector After Reforms
17Single Buyer Model
- Single buyer model be adopted as market structure
- The Single Buyer shall be a public sector entity
- Planning of least cost generation expansion
- Arrange establishment of private power generating
stations as per generation expansion plan - Purchasing electricity from generators (both
public and private) and selling to distributors
under Power Purchase and power Sales Agreements - Power system operation including economic
dispatch of generation
18Market Structure of Power Sector After Reforms
19Regulation of the power sector after
establishment of the Energy Regulatory Commission
- Establish an independent Regulatory Commission
- The Regulatory Commission cover electricity, gas
and petroleum sector - The Regulatory Commission to
- Protect consumers interests
- Protect industry interests
20Regulation of the power sector after
establishment of the Energy Regulatory Commission
(Contd.)
- The Commissions functions
- Approval of the utilities tariff proposal
following GOBs policy directives - Set Enforce Codes Standards of Operation
- Issue, repeal amendment of licenses -
- Generation (Electricity)
- Transmission
- Distribution
- Supply
21Regulation of the power sector after
establishment of the Energy Regulatory Commission
(Contd.)
- Approval of expansion investment plan of the
utilities to ensure least cost options - Ensure better customer service and protect
consumers interest - Promote competition by ensuring level playing
field
22Regulation of the power sector after
establishment of the Energy Regulatory Commission
(Contd.)
- Tariff
- Commission will approve the Tariff on the basis
of the policy directives issued by the govt. - Public hearing will be made during tariff setting
- Appeal against the decision of the Commission
- Aggrieved person may appeal against the decision
of the Commission to the High Court Division of
the Supreme Court
23Proposed Electricity Pricing Policy
- The tariff setting be consistent with the
financial requirements of the power sector
institution - Meets operating expenses
- Earns adequate return for self investment in
future expansion - The tariffs take into account-
- Load Management and energy conservation
- Efficiency improvement
- The GOBs policy objectives be addressed in
tariff setting and recommendations especially on
social commitments. - Tariff to each Consumer class reflects the cost
of supply - PBSs be subsidised by direct transfer from the
GOB with the aim of promoting rural development
24Proposed Electricity Pricing Policy (Contd.)
- Gradual withdraw of subsidy for agriculture
consumers - Gradual withdraw of subsidy for domestic
consumers except those fall in the life line slab
(0-100 units presently) - In the interim subsidies to domestic and
Agriculture Consumers be supported through the
national budget - Automatic price adjustment due to change of the
following using a well specified formula - Exchange Rate
- Consumer/industrial price index
- Fuel price
25Proposed Electricity Pricing Policy (Contd.)
- Impact
- Make public sector utilities financially viable
- Increase ability of the public sector utilities
to self-finance - Reduced requirement of GOB assistance/subsidies
for development of the sector - Brings competition and increase private
participation both foreign and local - Note
- Tariff increase/rationalization be made along
with the recommended power sector reform/
restructuring, otherwise it cant bring desired
financial viability of the sector.
26THANK YOU
C/Parvez/Kabir Sir/2002/Country Paper/Energy
Regulation in Bangladesh-For Bhutan.ppt