Title: NDA Higher Activity Waste Programme Update to RWIN Lisa Hughes HLW


1
NDA Higher Activity Waste Programme Update to
RWINLisa HughesHLW ILW Strategy
Development Engineer28 May 2008
2
Scope of presentation
  • Introduction and aim
  • Work programmes
  • Interim storage
  • Geological Disposal Facility (GDF) scheduling
  • Graphite
  • MRWS process

3
Waste Hierarchy and Lifetime Plans
4
Governments MRWS programme
5
CoRWMs recommendations
  • Published July 2006
  • - after significant public and stakeholder
    engagement
  • - 15 recommendations
  • Geological disposal
  • Interim storage
  • Voluntarism and partnership approach

6
CoRWM recommendation 2
  • A robust programme of interim storage must play
    an integral part in the long-term management
    strategy. The uncertainties surrounding the
    implementation of geological disposal, including
    social and ethical concerns, lead CoRWM to
    recommend a continued commitment to the safe and
    secure management of wastes that is robust
    against the risk of delay or failure in the
    repository programme.

7
CoRWM recommendation 2
  • Due regard should be paid to
  • reviewing and ensuring security, particularly
    against terrorist attacks
  • ensuring the longevity of the stores themselves
  • prompt immobilisation of waste leading to
    passively safe waste forms
  • minimising the need for repackaging of the
    wastes
  • the implications for transport of wastes

8
Governments response
  • Defra and Devolved Administrations
  • - responded October 2006
  • Accepted primary recommendations
  • NDA to implement
  • Nirex to be integrated into the NDA
  • - maintain skills and experience

9
Governments response
  • Security of stores is paramount - SLCs are
    regulated and advised by OCNS on all security
    matters.
  • Design of new stores will allow for a period of
    interim storage of at least 100 years to cover
    uncertainties associated with the implementation
    of a geological repository.
  • Government and regulators agree wastes should be
    made passively safe as soon as practicable to
    avoid future repackaging of wastes.
  • In developing its storage and disposal strategy
    the NDA will consider the implications for waste
    transport and keep under review the packaging
    requirements, to minimise the possibility that
    waste will have to be repackaged whilst in
    storage.

10
UK waste storage review
  • NDA has carried out a UK review of waste storage
    on behalf of Government
  • Storage regimes for solid ILW (raw and
    immobilised) and for HLW (liquid and vitrified)
  • Include storage of non-immobilised wastes in
    various legacy facilities
  • Spent fuels and nuclear materials excluded

11
UK waste storage review
  • Significant support from sites
  • Reviewed existing and proposed interim stores
  • Report sent to Government in May
  • Recommendations made both to Government and to
    sites
  • Further package of work proposed to address
    recommendations and Regulator feedback
  • Public domain report produced

12
GDF Scheduling
  • Work package arose from the LCBLi project
  • Previous LTPs assumed every site disposed of
    waste from 2040
  • Resulted in a demand of over twice the import
    rate capacity in 2040
  • Through discussion of the issues the sites
    amended their own LTPs fair share approach
  • Now have a credible baseline but still room for
    optimisation

13
Provisional GDF filling schedule
14
Provisional GDF filling schedule
15
Provisional GDF filling schedule
16
National waste modelling
  • NDA compiles the UK waste and nuclear materials
    inventory
  • Plan to move to near real time inventory
  • Currently using waste accountancy template
    reports to monitor waste-related hazard reduction
  • Planning a holistic UK model waste production,
    storage, transfers, GDF filling (cf the Magnox
    Operating Plan)
  • Flex the model for new build waste, different GDF
    locations, changes to cleanup schedule, etc

17
Graphite
  • Significant inventory
  • Irradiated graphite contains relatively high
    concentrations of C-14 and Cl-36.
  • Areas of interest
  • Graphite characterisation
  • Graphite treatment technologies current
    workable solutions
  • Reuse possibilities
  • Waste volume reduction technologies
  • Alternative disposal methods to deep GDF

18
2008 White Paper
  • Public consultation up to Nov. 2007
  • Responses published Jan. 2008
  • Broad support for governments approach
  • Government MRWS White Paper June 2008?
  • Local authorities will be invited to express
    interest (in being a volunteer host community)
  • Information packs to be made available
  • Proposals for siting process to be consulted upon

19
Baseline repository schedule
20
NDAs role
  • Support MRWS generally
  • Support community engagement and site selection
    (where Government will lead)
  • Interact with CoRWM
  • Implement the geological disposal project
  • Track skills and supply chain issues
  • Engage with Regulators (eg Disposal System Safety
    Case and NDAs organisational arrangements)
  • Make organisational changes (eg RWMD as shadow
    SLC organization)

21
Summary
  • Number of work streams ongoing covering waste
    generation through to treatment and disposal
  • Only a snapshot presented
  • All work streams depend upon some form of
    engagement with the sites (input/review of
    output)
  • Where possible updates are published on NDA
    website
  • Detailed findings will be communicated via site
    teams

22
Any questions?