INTRODUCTION TO POWER PROCUREMENTPOWER PURCHASE AGREEMENTS - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

INTRODUCTION TO POWER PROCUREMENTPOWER PURCHASE AGREEMENTS

Description:

An offer has to be made by one party and accepted by the other party; ... Contract for supply or erection vis- -vis a contract for services over a period of time. ... – PowerPoint PPT presentation

Number of Views:29
Avg rating:3.0/5.0
Slides: 16
Provided by: Neha9
Category:

less

Transcript and Presenter's Notes

Title: INTRODUCTION TO POWER PROCUREMENTPOWER PURCHASE AGREEMENTS


1
INTRODUCTION TO POWER PROCUREMENT/POWER
PURCHASE AGREEMENTS
  • by
  • K Venugopal
  • Member, DERC
  • 04th July, 2007
  • IIT (Kanpur)

2
What is a Contract?
  • An Agreement signed by two parties who are
    competent to enter into a contract
  • Contract Indian Contracts Act, 1872
  • Who is Competent?
  • - a major person
  • - of sound mind
  • and the Contract is for a consideration
  • It spells out the rights and obligations of the
    two parties

3
For a Contract
  • An offer has to be made by one party and accepted
    by the other party
  • The consideration is to be decided at the time of
    acceptance.
  • Contract for supply or erection vis-à-vis a
    contract for services over a period of time.

4
Distinction between a Supply, Erection, Testing
and Commissioning Contract and a Power Purchase
Agreement
  • The first one is for supply erection, testing and
    commissioning and handing over of the plant and
    equipment to the buyer. The buyer operates the
    plant
  • Ownership changes at this point of time
  • In a PPA, the power plant is owned by the
    developer for the entire term of the PPA and only
    power is sold for a consideration
  • Contd.

5
  • The PPA sets out the rights and obligations of
    the buyer and seller over a time horizon of 15 or
    20 or 25 or 35 years, as the case may be.
  • PPA is all about allocation of risks between
    buyer and seller
  • Allocate risks to the party which can better
    manage the risk
  • If the risks are allocated wrongly, it will add
    to the costs.
  • Contd.

6
  • PPA decides the revenue stream of the project
  • In case of non-recourse financing, the project
    and project documents like PPA are the only
    covenants
  • Other assets of the developer/promoter will not
    act as covenants to the project being developed
    on non-recourse basis
  • The Lenders would evaluate the PPA to ascertain
    the financial strength of the project.

7
Typically, a PPA comprises of the following
Chapters
  • Preamble
  • Definitions and interpretation
  • Conditions precedent
  • Term of the PPA
  • Development stage
  • Construction period
  • Commissioning and entry into Commercial service
  • Contd.

8
  • Plant operation, maintenance and fuel supply
    management
  • Availability declaration
  • Measurement of capacity, availability and energy
    metering.
  • Capacity charge and payment
  • Energy charge payments
  • Billing procedures and terms of payment
  • Insurance
  • Changes in law, including tax laws
  • Contd.

9
  • Force Majeure
  • Termination and Buy-out provisions
  • Governing law/dispute resolution
  • Liability/indemnity
  • Confidentiality
  • Representation
  • Notices
  • Miscellaneous

10
Schedules appended to the PPA
  • Description of Power Station
  • Clearances
  • Development milestones
  • Inter-connection and transmission facilities
  • Commissioning and testing
  • Metering Standards and Testing
  • Dispatch Procedures
  • Tariff Schedule
  • Capacity payment
  • Energy payment

11
Role of SERC
  • Section 86 (b) The State Commission shall
    discharge the following function namely
  • regulate electricity purchase and procurement
    process of distribution licensees including the
    price at which electricity shall be procured from
    the generating companies or licensees or from
    other sources through agreements for purchase of
    power for distribution and supply within the
    State

12
Process
  • Demand forecast by DISCOM
  • Supply availability
  • Gap
  • How to fill up the gap
  • - Long term contracts
  • - Short term contracts
  • - Procurement through day ahead Power
    Exchange
  • - Drawal from the Grid within IEGC limits?

13
  • Section 62 (1)
  • The Appropriate Commission shall determine the
    tariff in accordance with the provisions of this
    Act for
  • (a) supply of electricity by a generating company
    to a distribution licensee
  • Provided that the Appropriate Commission may, in
    case of shortage of supply of electricity, fix
    the minimum and maximum ceiling of tariff for
    sale or purchase of electricity in pursuance of
    an agreement, entered into between a generating
    company and a licensee or between licensees, for
    a period not exceeding one year to ensure
    reasonable prices of electricity

14
  • Section 63
  • Notwithstanding anything contained in Section
    62, the Appropriate Commission shall adopt the
    tariff if such tariff has been determined through
    transparent process of bidding in accordance with
    the guidelines issued by the Central Government.
  • Guidelines issued by the Central Government from
    time to time for
  • Long-term Power Procurement 25 years
  • Medium-term Power Procurement Less than 7 years

15
THANK YOU
Write a Comment
User Comments (0)
About PowerShow.com