Launch Vehicle - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

Launch Vehicle

Description:

Material originates at the fairing rail separation plane, and disperses quickly ... Disposition of the EO-1/SAC-C payload fairing was deferred to a later date. ... – PowerPoint PPT presentation

Number of Views:77
Avg rating:3.0/5.0
Slides: 22
Provided by: davebree
Category:

less

Transcript and Presenter's Notes

Title: Launch Vehicle


1
Section 32 Launch Vehicle
. . . Dave Breedlove / M. Stowe / A.
Piloto Kennedy Space Center
2
Contents
  • Launch Vehicle Integration Status David Breedlove
  • Changes Since March Red Team Review
  • Mission Unique Hardware Status Merri Anne Stowe
  • Payload Fairing
  • Launch Vehicle Summary David Breedlove
  • Summary of RFA responses

3
Launch Vehicle Integration Status
4
(No Transcript)
5
Changes Since March Red Team Review
6
Mission Design Changes
  • The SAC-C injection orbit has changed from 705 km
    circular to 685x705 km
  • No impact to EO-1 mission

7
EO-1/SAC-C Boost Profile
8
EO-1/SAC-C Orbit Injection Profile
9
Performance Margin
IS
WAS
Based on Oct. 17 Launch
10
Launch Site
  • Astrotech awarded contract for S/C Processing
  • EO-1 requested to process in Astrotech
  • To reduce risk in moving Satellite from 836 to
    Astrotech
  • Provides schedule contingency for S-band
    integration
  • Requirements change is in work
  • Swales Team working with KSC, WTR, and Astrotech
  • SLC-2, Level-6 access platforms for EO-1 are in
    work
  • Design/implementation scheduled to meet Oct.
    launch date

11
EO-1/SAC-C ELV Mission Unique Hardware Status
12
Readiness Reviews
  • Meeting Location Date
  • Red Team Review GSFC 3/28-31/00
  • Pre-Vehicle On Stand (Pre-VOS) Huntington
    Beach 9/00
  • KSC Center Directors Launch Vehicle KSC TBD
  • Readiness Review (1-2 wks prior to MRR)
  • GSFC Spacecraft MRR GSFC TBD
  • Launch Site Readiness Review VAFB 1 day prior to
    S/C on stand
  • Flight Readiness Review VAFB TBD
  • Launch Management Coordination Meeting VAFB F-2
    Day
  • Mission Rehearsal VAFB F-2 Day
  • Launch Readiness Review VAFB F-1 Day

13
Applicable Launch Vehicle Issues
14
Applicable Launch Vehicle Issues
  • Payload Fairing Transportation Incident
  • Fairing has been repaired, Boeing and KSC
    Engineering are in agreement, formal closure
    pending ERB
  • Payload Fairing Acoustic Blanket Modifications
  • Modifications are complete
  • GN2 Purge Tube Replacement
  • Tubing inside the fairing has been replaced
  • Fluoroglide Contamination Concern
  • Covered in following charts

15
Payload Fairing Contamination Concern Background
  • At the time of payload fairing separation, some
    small debris was seen on video of the
    Globalstar-7 mission
  • Contamination appears as small, bright flakes and
    particles
  • Material originates at the fairing rail
    separation plane, and disperses quickly after
    separation
  • Possible contaminants investigated by Boeing
    include ice, rain intrusion, dust, aluminum tape
    used to tape over rivet heads, Sparesyl, charred
    paint, and Fluoroglide
  • Boeings investigation concluded that the most
    probable source of the contamination was
    Fluoroglide applied to the fairing separation
    rail bellows
  • GS-7s fairing bellows had received a second
    application of Fluoroglide due to installation
    difficulties. The EO-1/SAC-C fairing bellows
    received only one application.

16
Payload Fairing Contamination Concern Chronology
  • Engineering Review Board 00312KSC met on March 3,
    2000 concluded Fluoroglide was the only credible
    root cause of the contamination.
  • Disposition of the EO-1/SAC-C payload fairing was
    deferred to a later date.
  • The Board was of the opinion that a flight
    rationale could be developed for EO-1 since the
    EO-1/SAC-C fairing had received only one
    application of Fluoroglide vice the two
    applications on the GS-7 fairing, and fairing
    separation video of a single Fluoroglide
    application mission was available.
  • The EO-1 Program was given the ERB information
    and copies of the GS-5 and GS-7 videos to review.
    They were asked to identify which instruments
    had a view of the fairing splitline and to assess
    the acceptability of the contamination risk.
  • The instrument field of view information was
    provided on April 27.

17
Payload Fairing Contamination Concern Chronology
(continued)
  • On June 16, 2000, the EO-1 Program notified KSC
    via telecon that the contamination risk was not
    acceptable. An official memo followed on June
    20.
  • ERB 00312KSC was reconvened on June 19. It
    recommended that the EO-1/SAC-C payload fairing
    not be flown as-is for this mission
  • Fluoroglide contamination assessed as
    undetermined and S/C could not accept the risk.
  • Official notification of this decision was sent
    to Boeing at the end of June.

18
Payload Fairing Contamination Concern Chronology
(continued)
  • A telecon between KSC and Boeing was held on July
    17 to discuss alternative ways to get a
    flightworthy payload fairing for EO-1/SAC-C.
  • Boeing maintains that the videos do not show
    Fluoroglide being deposited on any spacecraft
    surfaces
  • Boeing maintains that risk of contamination to
    the S/C is very low

19
Payload Fairing Contamination Concern Resolution
  • The selected option for resolving the
    contamination concern is to install a shield
    along the part of the fairing splitline that is
    in the EO-1 instruments field of view.
  • The design details are still in work.
  • KSC will have an Engineering Review Board for the
    final design prior to fabrication.
  • The shield will be qualified by analysis for
    flight.
  • Installation will be done at Vandenberg AFB.
  • No impact to the launch schedule.

20
Shield Concept
  • Task
  • Drill through the heavy half separation rail and
    bolt on a debris shield from STA 397.57 forward.
    Coarse sun Sensor Side only (Quad II)
  • Touch up Sparesyl and paint

21
Launch Vehicle Summary
  • Changes Since The 3/30/00 Red Team Review
  • Minor change to SAC-C separation orbit, no impact
    to the EO-1 mission
  • Astrotech chosen for Spacecraft Processing
  • Hardware Status
  • DPAF is complete and qualified for flight
  • No change from the last review
  • A straightforward modification has been
    identified to allay concerns about possible
    contamination due to Fluoroglide on the payload
    fairing separation bellows
  • No impact on launch date
  • The EO-1/SAC-C launch vehicle will be ready to
    support the launch campaign
Write a Comment
User Comments (0)
About PowerShow.com