Title: Launch Vehicle
1Section 32 Launch Vehicle
. . . Dave Breedlove / M. Stowe / A.
Piloto Kennedy Space Center
2Contents
- Launch Vehicle Integration Status David Breedlove
- Changes Since March Red Team Review
- Mission Unique Hardware Status Merri Anne Stowe
- Payload Fairing
- Launch Vehicle Summary David Breedlove
- Summary of RFA responses
3Launch Vehicle Integration Status
4(No Transcript)
5Changes Since March Red Team Review
6Mission Design Changes
- The SAC-C injection orbit has changed from 705 km
circular to 685x705 km - No impact to EO-1 mission
7EO-1/SAC-C Boost Profile
8EO-1/SAC-C Orbit Injection Profile
9Performance Margin
IS
WAS
Based on Oct. 17 Launch
10Launch Site
- Astrotech awarded contract for S/C Processing
- EO-1 requested to process in Astrotech
- To reduce risk in moving Satellite from 836 to
Astrotech - Provides schedule contingency for S-band
integration - Requirements change is in work
- Swales Team working with KSC, WTR, and Astrotech
- SLC-2, Level-6 access platforms for EO-1 are in
work - Design/implementation scheduled to meet Oct.
launch date
11EO-1/SAC-C ELV Mission Unique Hardware Status
12Readiness Reviews
- Meeting Location Date
- Red Team Review GSFC 3/28-31/00
- Pre-Vehicle On Stand (Pre-VOS) Huntington
Beach 9/00 - KSC Center Directors Launch Vehicle KSC TBD
- Readiness Review (1-2 wks prior to MRR)
- GSFC Spacecraft MRR GSFC TBD
- Launch Site Readiness Review VAFB 1 day prior to
S/C on stand - Flight Readiness Review VAFB TBD
- Launch Management Coordination Meeting VAFB F-2
Day - Mission Rehearsal VAFB F-2 Day
- Launch Readiness Review VAFB F-1 Day
13Applicable Launch Vehicle Issues
14Applicable Launch Vehicle Issues
- Payload Fairing Transportation Incident
- Fairing has been repaired, Boeing and KSC
Engineering are in agreement, formal closure
pending ERB - Payload Fairing Acoustic Blanket Modifications
- Modifications are complete
- GN2 Purge Tube Replacement
- Tubing inside the fairing has been replaced
- Fluoroglide Contamination Concern
- Covered in following charts
15Payload Fairing Contamination Concern Background
- At the time of payload fairing separation, some
small debris was seen on video of the
Globalstar-7 mission - Contamination appears as small, bright flakes and
particles - Material originates at the fairing rail
separation plane, and disperses quickly after
separation - Possible contaminants investigated by Boeing
include ice, rain intrusion, dust, aluminum tape
used to tape over rivet heads, Sparesyl, charred
paint, and Fluoroglide - Boeings investigation concluded that the most
probable source of the contamination was
Fluoroglide applied to the fairing separation
rail bellows - GS-7s fairing bellows had received a second
application of Fluoroglide due to installation
difficulties. The EO-1/SAC-C fairing bellows
received only one application.
16Payload Fairing Contamination Concern Chronology
- Engineering Review Board 00312KSC met on March 3,
2000 concluded Fluoroglide was the only credible
root cause of the contamination. - Disposition of the EO-1/SAC-C payload fairing was
deferred to a later date. - The Board was of the opinion that a flight
rationale could be developed for EO-1 since the
EO-1/SAC-C fairing had received only one
application of Fluoroglide vice the two
applications on the GS-7 fairing, and fairing
separation video of a single Fluoroglide
application mission was available. - The EO-1 Program was given the ERB information
and copies of the GS-5 and GS-7 videos to review.
They were asked to identify which instruments
had a view of the fairing splitline and to assess
the acceptability of the contamination risk. - The instrument field of view information was
provided on April 27.
17Payload Fairing Contamination Concern Chronology
(continued)
- On June 16, 2000, the EO-1 Program notified KSC
via telecon that the contamination risk was not
acceptable. An official memo followed on June
20. - ERB 00312KSC was reconvened on June 19. It
recommended that the EO-1/SAC-C payload fairing
not be flown as-is for this mission - Fluoroglide contamination assessed as
undetermined and S/C could not accept the risk. - Official notification of this decision was sent
to Boeing at the end of June.
18Payload Fairing Contamination Concern Chronology
(continued)
- A telecon between KSC and Boeing was held on July
17 to discuss alternative ways to get a
flightworthy payload fairing for EO-1/SAC-C. - Boeing maintains that the videos do not show
Fluoroglide being deposited on any spacecraft
surfaces - Boeing maintains that risk of contamination to
the S/C is very low
19Payload Fairing Contamination Concern Resolution
- The selected option for resolving the
contamination concern is to install a shield
along the part of the fairing splitline that is
in the EO-1 instruments field of view. - The design details are still in work.
- KSC will have an Engineering Review Board for the
final design prior to fabrication. - The shield will be qualified by analysis for
flight. - Installation will be done at Vandenberg AFB.
- No impact to the launch schedule.
20Shield Concept
- Task
- Drill through the heavy half separation rail and
bolt on a debris shield from STA 397.57 forward.
Coarse sun Sensor Side only (Quad II) - Touch up Sparesyl and paint
21Launch Vehicle Summary
- Changes Since The 3/30/00 Red Team Review
- Minor change to SAC-C separation orbit, no impact
to the EO-1 mission - Astrotech chosen for Spacecraft Processing
- Hardware Status
- DPAF is complete and qualified for flight
- No change from the last review
- A straightforward modification has been
identified to allay concerns about possible
contamination due to Fluoroglide on the payload
fairing separation bellows - No impact on launch date
- The EO-1/SAC-C launch vehicle will be ready to
support the launch campaign