Title: AT
1ATT Mobility Network Optimization
- Michael Van Weelden
- Director SCM ATT Mobility
- July 14, 2007
2ATT Mobility Network OptimizationArchitecture
Example
Cell Site
DS1/DS3 Channel Termination
Mobility Switch
OC/DS3 Channel Termination
M13
LEC/CLEC LSO
LEC MTSO SWC
ATT Mobility Leased/Owned Ring Service
Mobility Switch
DS1/DS3 Channel Termination
LEC MTSO SWC
M13
OC/DS3 Channel Termination
LEC/CLEC LSO
OC/DS3 Channel Mileage
Cell Site
3Mobility Network OptimizationProcess Flow
Planning, Capacity Analysis,Implementation, and
Tracking
- NPE
- Capacity availability
- Augment capital estimate
- Network Engg
- Finalize design
- Finalize schedule
- Coordinate service
- Data for optimization analysis
PLANNING
Capacity analysis and capital cost
Preliminary opportunity
- Program Mgmt
- Review target plan
- Work w/ NPE on capacity requirements
- Term Liability impacts
Bill Tamer and Granite inventory information
Deliver price
Manage data sources
- Program Mgmt
- Develop financial impact
- Manage Mobility relationship
CAPACITY ANALYSIS
Preliminary plan and capital estimate used for
pricing
- Access Suppliers
- Data for optimization analysis
A
- Tracking
- Track new service
Billing data
New service tracking data
disconnect tracking data
- Provisioning
- Provision new PL service
IMPLEMENTATION
Issue PL Order
Coordinate w/ Network Engineering
- Provisioning
- Place new Local PL service orders
- Issue disconnects
- Program management of vendor and Mobility
resources
- Access Suppliers
- Place orders for new service
- Issue Disconnect
Facility assignment information
A
4ATT Mobility Network Optimization
- Network Optimization Objectives
- Reduce Mobility Transport Expense
- Secure high quality, reliable transport services
- Promote redundancy/survivability in core
network - Maximize circuit utilization
- Optimize internal and external resources
- Anticipate future capacity requirements