b) Juzhek is correct that EMPs are not required for the subprojects for which ... c) Juzhek would be correct to say that it is not necessary to prepare EMPs for ... – PowerPoint PPT presentation

Number of Views:30
Avg rating:3.0/5.0
Slides: 10
Provided by: WB1673
Category:

less

Transcript and Presenter's Notes

Title: Mini-Case / Quiz Topic: EA Categorization and EMP Requirements


1
Mini-Case / Quiz Topic EA Categorization and
EMP Requirements
Discussion Material For the Moldova Safeguards
Training Workshop October 28-31, 2008
By Victor B. Loksha ECA Safeguards Team Europe
and Central Asia Region The World Bank
2
Mini-Case
  • Please review carefully the following three
    slides. Make sure to assess each of the
    situations and statements critically. Remember
    that some of the characters involved in the case
    may be incorrect in their assumptions

3
1
  • Darko Juzhek, the PIU director of the Slovonia
    Coastal Environment Improvement Project, is
    giving the following instructions to Elvira
    Zagogullina who has just joined the PIU as the
    environmental specialist Our project has
    several investment components, including the
    construction of new public sewerage systems,
    wastewater treatment plants, and submarine
    outfalls in seven locations. An environmental
    specialist from the World Bank has told us that
    the project will likely fall into the
    environmental Category B according to the
    Banks classification. However, our project is
    beneficial for the environment as its very name
    indicates. Therefore, we would like to request
    the Banks TTL to give our project the category
    FI (Financial Intermediary) instead of Category
    B.

4
2
  • Juzhek goes on, We have discussed the
    applicability of the Environmental Impact
    Assessment (EIA) requirement with the Ministry of
    Environment. The Ministry requires the EIA only
    for one location the town of Zador where the
    treatment plant capacity exceeds 50,000 PE
    (population equivalent). We have a preliminary
    (feasibility phase) EIA report for Zador, which
    should get you started on the EMP. The rest of
    the project sites will be exempt from EIA. Since
    EIA for them is not required, we dont need to
    prepare EMPs for them.

5
3
  • Next week, a World Bank mission visits Slovonia
    and Ms. Zagogullina discusses the scope of the
    EMP with the Banks environmental specialist
    Steve Cohen. Mr. Cohen mentions that the only
    certain way to secure compliance of the project
    with the Banks EA requirements under OP 4.01 is
    to implement site-specific EMPs for all seven
    locations. The TTL is present in the meeting but
    leaves the issue for Cohen and Zagogullina to
    sort out.

6
Quiz
  • Question 1 Which one of the statements below is
    correct?
  • a) Category FI is not an available choice under
    OP 4.01 on Environmental Assessment.
  • b) Environmental assessment does not need to
    reflect beneficial impacts of the project on the
    environment, focusing only on its possible
    adverse impacts and their mitigation.
  • c) The choice between environmental categories
    B and FI depends on the extent and nature of
    the projects environmental impacts.
  • d) EA for Category FI projects requires a
    detailed description of the process followed by
    the borrower in implementing environmental
    assessments.

7
Quiz
  • Question 2 Which one of the statements below is
    correct?
  • a) Since the project is World Bank financed, the
    requirements of the Slovonian Ministry of
    Environment are irrelevant and OP 4.01
    requirements must be applied instead.
  • b) Juzhek is correct that EMPs are not required
    for the subprojects for which the Slovonian
    legislation does not require an EIA.
  • c) Juzhek would be correct to say that it is not
    necessary to prepare EMPs for the subprojects for
    which national legislation does not require an
    EMP.
  • d) An EMP may be prepared by the borrower and
    accepted by the World Bank even if the EIA report
    is not considered final in Slovonia.

8
Quiz
  • Question 3 Which one of the statements below is
    most accurate?
  • a) If the project is assigned category FI,
    site-specific EMPs for all seven subproject
    locations need to be implemented to meet the
    World Banks EA requirements.
  • b) If the project is assigned category FI, one
    comprehensive EMP for the project as a whole is
    sufficient to meet the World Banks EA
    requirements.
  • c) Site-specific EMPs need to be implemented for
    all seven locations if project activities with
    potential adverse environmental impacts are
    expected in all seven locations.
  • d) One site-specific EMP for the town of Zador is
    sufficient to meet the World Banks EA
    requirements because it is the only site for
    which the Banks environmental category B is
    appropriate based on the size of the treatment
    plant.