Title: Summary of Blayer Replacement Workshop
 1Summary of B-layer Replacement Workshop
- October ATLAS Week 
- CERN, 10 October 2007 
- G. Darbo - INFN / Genova 
- Workshop page 
- http//indico.cern.ch/conferenceDisplay.py?confId
 20119
2B-Layer Workshop
http//indico.cern.ch/conferenceDisplay.py?confId
21107
- B-layer Replacement WS 
- Sept. 28-29, 2007 
- Workshop numbers 
- 1  1/2 days 
- 6 Sessions  round table 
- 56 registered participants 
3Why Pixel Replacement
- B-layer was designed to survive 3 years of LHC 
 nominal luminosity (1034cm-2s-1)
- NIEL fluence  1015 neq/cm2 (mainly from pions) 
- Ionising Dose  500 kGy (50 Mrad) 
-  Sensors 
- Not fully depleted at 600 V ? lower charge 
 collected, lower efficiency
- Leakage current (noise) 
- Charge trapping ? lower charge collected, lower 
 efficiency
- Electronics 
- Transistor VT shift due to charge trapping in 
 the gate oxide (Ionisig Radiation). FE and MCC
 tested to 500 kGy)
- New LHC machine scenario could move replacement 
 date into the future, but large unknowns on
 operation and cooling runaway may make it
 sooner.
- Target date for the Workshop studyWinter 
 shutdown 2012
4Replacement Constraints
- Aim of the replacement is to improve, or at least 
 restore, initial performance of the Pixel (ID)
 detector.
- This scenario involves improvements to 
 sensor/electronics design, to module and
 mechanical geometry.
- Hope for beam pipe radius reduction, such that a 
 3237 mm radius pixel detector can be inserted
 inside the existing detector.
- The new b-layer could be inserted together with 
 the beam pipe in this scenario.
- Two scenarios have been studied and analysed in 
 the workshop
- Add a small R b-layer  leave existing one 
 (having reduced efficiency)
- Add a small R b-layer  remove the existing one 
 (remove material)
- The additional constraint we used in the study 
 was the replacement date 2012 and the shutdown
 time 6 months
A
B 
 5Layout  Simulation Method and Software
- DC1 model of ID  upgraded pixel. 
- Latest xKalmanOO (tracking). 
- Private version of b-tagging software with 
 secondary vertices and recalibration for
 different trackerprocess configurations
- B-tagging software was not specifically tuned for 
 new setup (all track selection cuts were the same
 as for current pixel).
Ref. V. Kostyukhin, P. Nevski, A. Rozanov
Results presented for upgraded pixel with added 
layer (4L) and with modified single b-layer 
together with results obtained with current 
pixel detector (3L).
Modified layout with single b-layer
Layout with 4-layers L4
Rb1  37.0 mmRb2  absentR1  88.5 mmR2  
122.5 mm
Rb1 37.0mmRb2 50.5mm R1  88.5mmR2  122.5mm 
 6Material Studies  Performance
Modified layout with Single b-layer X0  1.2
New b-layer X0  1.2
Z resolution
-  Performance equivalences in old studies 
- Decrease of the b-layer radius from 5 cm to 4 cm 
 (20 effect)
- Decrease of the z-pitch in b-layer from 400 um to 
 200 um
- Decrease of the material in b-layer by 0.6 
- Loss of 1 / 2 pixel module/chip inefficiency in 
 b-layer
- Partial (2/3) missing the intermediate pixel 
 layer (R9cm)
- Pile-up of 1034 cm2s-1 without muon pointing to 
 primary vertex.
3L
4L
Ref. A. Rozanov 
 7 b-tagging u-jets
3d significance of primary-secondary vertices 
distance for vertices in u-jets (fake) 
Ref. V. Kostyukhin
Bigger tail for 4L pixel ? means problem for 
b-tagging.
3L 
 4L
for vertices in b-jets (real) 
Mean value should be inversely proportional to 
resolution ( B-particle decay is the same, 
resolution is better).In fact 3D resolution is 
not significantly better.
3L 
 4L 
 8 B-tagging Results
Ref. V. Kostyukhin
Preliminary!!!
WH(120)?uu(bb), no pileup, ATLFAST jets, 
reconstructed primary vertex.
- Tracking performance seems ok for 4 layers case 
 but b-tagging is worse comparing with current
 design. Track part of b-tagging is mainly
 responsible for worsening.
- Layout with new single b-layer at R37mm and 
 removed current b-layer gives significantly
 better performance with existing tracking
 software.
- Single b-layer at R37mm provides some increase 
 of b-tagging rejection at high ? region  weak
 point of existing pixel detector.
9Radiation Protection at CERN 
 10Disconnect / Extract the Pixel
Ref. D. Giugni
TASKS in this ENVIROMENT Set up and align the 
DST, Extract the detector, Rotate the DST, Hook 
up the DST to the crane. DURATION, MANPOWER, 
INTEGRAL DOSE  84h, 3 people, 3.1mSv
lt50 µSv/h ? Simple controlled radiation area 
/ Low occupancy areas lt 2 mSv/h ? Limited stay 
area / Low occupancy areas 
- The area of the ATLAS beam line will be 
 classified as Controlled Radiation Area.
- Assuming that the Full Body Dose exceeds 50µSv/h 
 the area should also be classified as Limited
 Stay Area(lt 2mSv/h).
- This means that workers have a controlled access, 
 must wear a personal dosimeter  an operational
 dosimeter and be classified as Radiation
 Workers.
- This assumption is justified by the fact that 
 the calorimeter in front of the IDEP has zone
 with dose rate at 500mSv/h.
11On Surface in the SR1
TASKS in this ENVIROMENT Remove SQPs, Access 
the beam pipe, Remove the beam pipe, Remove and 
insert the B-layer, Connectivity Test DURATION, 
MANPOWER, INTEGRAL DOSE  600h (depending upon 
the scenario), 4 people present, 28.9mSv
Supervised Radiation AREA lt 15 µSv/h
ITT
Simple Controlled Radiation AREA lt50µSv/h
- Great attention has to be paid to avoid 
 radioactive contamination. Grinding and cutting
 activated material would cause a contamination in
 the airborne and on the surfaces.
Ref. D. Giugni 
 12Services - Additions
Intreferes with T0 Cables
OSP
Detector
ISP
Requires Removal Of all SQP on this side
Modify
BPSS
- (Some) critical issues 
- Service Panels (SQPs) are highly integrated both 
 electrically and mechanically
- Electrical modularity of services locked in 
 Mechanically
- Tight envelopes make re-arrangement of services 
 difficult
- Penetration at PP1 uses almost all real estate at 
 package ends
- Fibers case A requires new opto-fibers to be 
 re-routed (difficult) and remapping with new
 electronics, case B fiber reuse requires same
 nominal location of New Optical drivers
Ref. E. Anderssen 
 13What to Open
- Case AA-Side (to insert B-layer leaving existing 
 one)
- Need to install new cooling circuits, cant be 
 C-Side, not quite enough spare Holes
- Requires complete disassembly of at least 2 SQPs 
 to get at least 6 cooling circuits in
- Gives access to BPSS to install new PP0s 
- A lot of work, all after removal, likely on 
 critical path
- Case BC-Side (to remove existing B-layer and add 
 a new one)
- Need clear aperture to pass BP and new BL 
 incannot pass PP1 Cruciform
- Only required removal of T0 cables and enough 
 SQPs to be comfortable removing BPSS
- Remove SQPs but not dissassemble to modify for 
 cable routing of new PP0s
- Access to BPSS to install new PP0s 
- On Critical Path, but less work than A 
- Both require removal of BPSS and at least 2 SQPs 
 on one side.
- Schedule 
- Case A and B differ in the needed operations but 
 the total time will not differ greatly. Case B
 requires, in first analysis 9.5 months. Case A
 could be slightly faster.
- More detailed studies are needed.
Ref. E. Anderssen
Ref. D. Giugni 
 14Envelope Studies
- New beam pipe radius 
- Nominally reduced to R25, theoretically to R17 
 (instead of R29 now) but
- R17 will require feedback from future Atlas run 
 see Rays talk at
- Current B-layer envelope R45.5 to R74  28.5 mm. 
- Case A  IR35  OR41 
- Case B  IR35  OR71.5 
- Studies which might give more space 
- Insulation thickness between BP and B-Layer 
- Radial Adjustment of Beam-pipe 
- Assembly sequence/tooling which requires less 
 clearance
Ref. A. Catinaccio 
 15Layout Concepts Single Layer
Monolitic OD  88 mm ID  75 mm
- Developing directions 
- Made stave prototype (for SLHC upgrade test) with 
 carbon foams with good thermal conductivity but
 relatively high density (?0.55 g/cc).
- Thermal and FEA analysis. 
- Look to low density (?0.15 g/cc) foam or 
 nanotubes.
Ref. M. Gilchieriese, M. Garcia Sciveres
Stave - 2 OD  88 mm ID  70 mm
Stave - 1 OD  93 mm ID  70 mm 
 16Layout Concept Double b-layer
Ref. N. Wermes
incl. angle B2 6o incl. angle B1 10o
nom. radius B2 49 mm nom. radius B1 37 mm
envelope ok
 staves B2 20  staves B1 16
Wolfgan Dietsche, Walter Ockenfels 
 17Local Support Structure - Stave
Ref. K.W. Glitza
- Wuppertal stave studies 
- Use homogeneous structure all carbon based. 
- Reduce material  carbon foam for the cover ( 
 density  0.50.9 g/cm³) thermal conductivity
 (in plane 140 W/mK out of plane 70 W/mK)
- Material and stability woven carbon pipes 
sensor
cover
base
base
pipe
Prototype 
 18SENSORS WORKING GROUP List of requirements
- radiation hardness figure greater than 3e15 
 neutrons/cm2
- electrical characteristics 
- noise, leakage currents - expected s/n figure 
- mechanical characteristics 
- thickness, material budget, dead area at edges 
- preferred module size 
- present size or 
- 16.5x17.5 mm2 62x250 mm 2x500mm x 350x50mm 
 single or multiple chips (as the present design)
- cooling options 
- present and future large scale production 
 capability
- time scale for production for the b-layer 
 replacement
- cost estimate per 100 wafers (6) 
19Sensors
- Basically all technologies covered by 
 presentations
- N-on-n is the Pixel proven technology 
- P-on-n gives the same radiation tolerance than 
 n-on-n, but single-side process cheaper and with
 higher yield
- Thin sensors lower material, lower leakage 
 current, lower charge
- Diamonds works at room temperature, pCVD 
 (spatial resolution?) and scCVD (large enough
 sensors?). Work at room temperature, low noise,
 high cost.
- 3D sensors high level of radiation hardness 
 (highest collected charge after irradiation),
 active edge, but cost.
- Gossip gaseous detector, many interesting 
 features, but still on RD stage.
20Electronic Framework
- Electronics designed for higher occupancy, 
 radiation tolerance, SEU
- Larger FE chip increases module live fraction 
 (70 ? 90)
- Feasible single chip (active edge) modules or 
 standard multi-chip
21System Architecture
- Remove MCC from module and have a SCC at stave 
 end.
- Serial links along the stave to connect FE ? SCC 
- Opto-links use same SIMM/GRIN fibers but at 
 higher speed.
22Front-end Chip - FE-I4
- Laboratories involved Bonn, CPPM, Genova, 
 Nikhef, LBNL.
- Very spread collaboration, difficult organize 
 common effort.
- Submission planned 12/2008. 
23Workshop Outcome
- The Workshop was quite successful, attracted more 
 than 70 people and was the first serious attempt
 to look into the b-layer replacement.
- It was the first time we did substantial study 
 in
- Simulating the b-tagging performance of the 
 replacement scenarios.
- Analyzing the impact of activation in the 
 operations to be made to replace the detector.
- Evaluating the impact on the schedule of 
 different scenarios.
- We have been somewhat surprised 
- Reduction of material is probably more important 
 than reduction of the radius
- Scope is bigger than foreseen for short time 
 scale. Services are on the critical path.
 Reconnect services cannot be done in short time.
 Replace services could be faster than
 disconnecting and connecting again, but cost
 would exceed that of the funded project (34
 MSF).
- Threshold to change is higher sensors and 
 electronics could survive longer and risk of the
 intervention (in complexity and time scale) are
 higher than foreseen.
24What to do next
- Develop a more precise and comprehensive analysis 
 of the lifetime issues for the present B-layer
- Effect of the reduced collected charge from the 
 sensors has to be studied throughout electronics
 signal generation and finally to b-tagging
 efficiency.
- Define some "thresholds" that would imply risks 
 we are willing to take, or timescales we are
 willing to consider for replacements.
- B-layer is the unique layer, in the whole ID, 
 which its reduced performance would have such a
 major effect on Physic achievements (basically,
 destroying or seriously degrading b-tagging).
- Develop a more complete plan, in collaboration 
 with TC/PO for the complete replacement
 operation, to understand the timescales and
 projections for allowed shutdowns.
- Push RD to reduce material budget. This must 
 happen mainly in the fields of sensors,
 electronics and integrated support structures
 (staves).
- Study ways of extending lifetime of present 
 detector cooling, operating sensors for longer
 life (limit bias current to keep them cooler).
25Last but not Least (Conclusions)
- The B-layer replacement, at a modest scope (no 
 more than about 34 MSF CORE equivalent) is a
 funded project, though not approved in detail.
- it is not only a necessary intermediate step 
 before going to a 1035 upgrade but should extend
 the secondary vertex related physics reach for
 ATLAS (or maintain it for longer).
- The timescale must fit with the SLHC, although 
 that is not an approved project with a
 schedule.
- We will gain critical experience (pixel hookup 
 and closing ATLAS) in next months so more natural
 time to reach a conclusion on baseline
 replacement option is again summer 2008.
- More engineering manpower will be released from 
 the present priority task of Pixel detector
 completion and will be directed to the study of
 the new detector.