Title: Southmead Hospital Redevelopment Project
1Southmead Hospital Redevelopment Project
2Bristol Health Services Plan
- Plan includes
- New acute and community hospital at Southmead
- Community healthcare facilities in Bristol
South Bristol, Eastville - Community healthcare facilities in South Glos
Frenchay, Thornbury, Yate, Cossham - Community healthcare facilities in North Somerset
Clevedon, Portishead - Centralisation of services across the city
3Site Location
4(No Transcript)
5View to Main Entrance
6VIEW FROM THE EAST
View Along Dorian Way
7Aerial View From North East
8Aerial View From North West
9View into main atrium
10View in main entrance concourse
11(No Transcript)
12Outpatient Waiting Areas
13sedum roof
1432 beds
15Ward Reception Waiting Area
16Ward Entrance Staff Base
17Single Bedroom
18Four bed bay
19(No Transcript)
20(No Transcript)
21Travel and Access
- 1.5 million over three years on public transport
in Bristol and South Gloucestershire - West of England Partnership accessibility study
- Bus routes through the site with dropoff at main
entrance - Cyclist and pedestrian facilities
- 1 million on road improvements in Bristol and
South Gloucestershire - Access changes on Dorian Road and A38
- Helipad
22Secondary Access Dorian Road
23Masterplan Development The Square
24Masterplan Development Square
25Masterplan Development Lime Tree Avenue
26Lime Tree Avenue Precedent Imagery
27The Square Precedent Imagery
28Key Issue Treatment of Beaufort House
29Sustainability
- 90 construction waste reused or recycled
- 20 target for renewable energy
- 85 target for local recruitment
- Improved cycle/bus routes and new change
facilities including Hour Bike Scheme - Waste composter and recycling facilities
available across site
3030 GJ/100m3
31(No Transcript)
32Project Timescales
- Reserved Matters application submitted July 2009
- Enabling Works start autumn 2009
- Planning Committee determination Oct/Nov 2009
- Financial close spring 10
- Main construction start spring 10
- New hospital opens 2014 (phase 1)
- Completion of external works 2015 (phase 2)