1Schedule toward the SC-ECAL Beam Test _at_ DESY
Dec 2006
Jan 2007
Feb 2007
1
2
3
4
1
2
3
4
1
2
3
4
KEK
ACFA
Beam Test _at_ DESY Feb 26 Mar 30
Shipping Feb-14
Delivery of 500 MPPCs
Delivery of 500 MPPCs
Ship MPPCs to KNU
Direct-readout megastrip source scan Install LED
Prepare MPPC mass check system
MPPC numbering Mass check
MPPC mass check.
MPPC soldering
MPPC soldering
Test assembly Install LED/Temp. monitor
system Prepare shipping
WLSF megastrip source scan
Megastrip bench test
Megastrip assembly
Fabrication of megastrip layer components
Finalize module design
Fabrication of Frame / light shielding structure
Establish LED / Temperature monitoring system
Prepare Trigger / Veto counters
MPPC study (response curve)
Analysis code / Event display
Contact DESY (DC gas, safety issue, etc)
2Jobs toward the SC-ECAL Beam Test _at_ DESY
- Measure MPPC response curve, check variation
- ECAL module construction
- Make mega-strip layer assembly
- ECAL frame and light shield construction
- MPPC mass measurement
- Mega-strip source scan
- Establish / install LED monitoring system
- Establish / install temperature monitoring system
- Shipping
- Settle MPPC operation voltages, prepare table for
voltage adjustment - Trigger counters / Veto counter (need
positive-polarity signal) - Make measurement plan / schedule
- Contact DESY (stage, drift chamber )
3Jobs during the Beam Test
- DAQ ace
- Data analysis software / ntuplization
- Drift chamber operation and analysis
- MIP calibration analysis
- Gain calculation (MPPC and electronics
inter-calibration) - Online data monitoring (check pedestal, dead
channel, etc) - Quick result of energy spectra / resolution
- Temperature / LED monitoring data, correction
- Event display
- MPPC dose test