RHIC 250 GeV Polarized Proton Run 09 Status - PowerPoint PPT Presentation

About This Presentation
Title:

RHIC 250 GeV Polarized Proton Run 09 Status

Description:

RHIC 250 GeV Polarized Proton Run 09 Status. Mei Bai ... Softwares for polarimeter control as well as polarization measurement are under development. ... – PowerPoint PPT presentation

Number of Views:19
Avg rating:3.0/5.0
Slides: 8
Provided by: mbai7
Learn more at: https://www.c-ad.bnl.gov
Category:

less

Transcript and Presenter's Notes

Title: RHIC 250 GeV Polarized Proton Run 09 Status


1
RHIC 250 GeV Polarized Proton Run 09 Status
  • Mei Bai
  • RUN website http//www.cadops.bnl.gov/AP/Spin2009

2
Run plan
  • Dry run mid of January
  • 3 weeks of machine setup
  • Injection setup one week
  • Commission new LLRF and 9 MHz cavity
  • Ramp development 2 weeks
  • Commission new LLRF and 9 MHz cavity
  • 250 GeV ramp development
  • Store setup

3
Machine Preparation Status
  • Lattice development
  • Injection and store lattice are developed
  • Injection beta 7.5m
  • Store beta_at_IP68 0.7m, others 7.5m
  • Ramp lattice development is in working progress
  • A new second order chromaticity correction
    algorithm was developed
  • Magnets around snakes were re-aligned.

4
Instrumentation preparation BPM
  • All the broken feed-throughs were replaced
    including the ones for the bpms next to the
    snakes
  • A major failure mode was identified and a
    software solution was tested and result is
    promising.

5
Instrumentation preparation tune feedback
  • Tune/decoupling feedback system
  • BBQ system had a dry run before the lead
    engineers departure.
  • BBQ documentation was done
  • Documentations for other key components in
    working progress
  • Procedures on how to operate the BBQ
  • Procedures on how to set up the coupling feedback
  • Controls

6
Instrumentation preparation CNI polarimeter
  • All the parts are ready
  • Chambers installation in working progress. Expect
    to be done at the end of Nov
  • Targets and detectors will be installed beginning
    of January and vacuum pumping then starts
  • Softwares for polarimeter control as well as
    polarization measurement are under development.
    Expect to be ready in the early part of Dec.
  • Dec will be testing/debugging the system without
    the actual targets and detectors

7
RHIC Spin Flipper for Blue
  • Will be installed in sector 9 between Q4 and Q3.
  • 4 DC dipoles were measured and stands are ordered
  • DC dipole power supply was tested and ready
  • 2 AC dipole ceramic chambers were received and
    are getting coated
  • 2 AC dipole coils expected to be here at the end
    of Nov.
  • AC dipole resonant circuit designed and
    capacitors as well as other parts ordered. Expect
    to receive around the end of Dec.
  • Installation of DC dipoles and ceramic pipes in
    Dec.
  • Installation of AC dipole magnets mid of Jan.