Title: Comments on Quick Plans


1
Comments on Quick Plans Spring 2005
  • Generally good that people tried COCOMO as a high
    level estimating technique. However, some
    noticeable shortcomings are
  • How did you estimate LOC ? Try some variations in
    loc s.
  • Seemed to have some confusion on Effort vs Time
  • Time did not specify how many people are
    applied throughout the project. real project
    never need the same number of people from
    beginning to end.
  • For your project time estimate try dividing
    effort in person-months by number of persons and
    get of months. That gives a feel of schedule
    possibility.
  • 1 person-month means a person working normal
    hours (6 hours a day from Monday through
    Friday). So if you are using student
    person-month, you must define and recalibrate.
  • People tried to force a detailed schedule into a
    fixed end-date. Do not do that in a Quick plan
    --- show the known milestone dates. All others
    are desirable dates which, if you want to put
    in, must be explained.