Title: UWP SOLAR System v 8'9 Upgrade Schedule


1
UWP SOLAR System v 8.9 Upgrade Schedule
2006/2007
  • Planning Phase Major Activities
  • Define project objectives, scope, approach
    schedule
  • Establish project team, roles, responsibilities
    budget
  • Define project standards and administration
    processes
  • Develop project communications, testing,
    training quality assurance plans
  • Monitor track project schedule, issues,
    change, cost, progress, results quality
  • Transition Phase Major Activities
  • Perform full system testing 11/6/06 to 11/17/06
  • Correct all system test issues and problems
  • Perform 2nd move to production test
  • Perform full integration testing12/5/06 to
    12/12/06
  • Correct all integration test issues and problems
  • Perform 3rd move to production test
  • Perform parallel testing 12/19/06 to 12/22/06
  • Correct all parallel test issues and problems
  • Perform 4th move to production test (as needed)
  • Develop and conduct end user demos training
  • Structure Phase Major Activities
  • Prepare certify technical environment
  • Prepare package UWP database for Oracle
    Upgrade Lab
  • Assess packaged delivered UWP custom
    functionality to be implemented
  • Evaluate business technical process changes
  • Finalize and conduct project team new
    functionality training/mentoring
  • Finalize end user training objectives, scope,
    approach and schedule
  • Deploy Phase Major Activities
  • Conduct end user demos training
  • Freeze SOLAR System access 1/4/07 (430 pm) to
    1/9/07
  • Perform move to production 1/4/07 to 1/8/07
  • Perform Go-Live testing 1/9/07
  • Correct all issues and problems
  • SOLAR System access resumed 1/10/07
  • Provide post Go-Live Support
  • Construct Phase Major Activities
  • UWP database upgraded at Oracle Upgrade Lab
  • UWP database upgraded on-site in UWP technical
    environment
  • Functional staff assess, refine validate
    package functional setup configuration
  • Technical staff assess, refine, recode test
    package data access application code
  • Security staff assess, refine validate
    application security
  • Technical staff assess, refine, test validate
    custom functionality 3rd party interfaces
  • Finalize testing plans, approach and test cases
    for all levels of testing
  • Install and setup end user training tools
    environment
  • Freeze upgraded database refresh with current
    SOLAR System data

2
System v 8.9 Upgrade Project Overview
  • Critical Dates Events
  • System Testing - 11/6 through 11/17
  • Integration Testing - 12/5 through 12/12
  • Demo Days Web Based Tutorial Information
    Sessions 12/4 through 12/13
  • Faculty, Students Staff take Web Based
    Tutorials 12/5 through 1/9 as available and
    personal schedules permit
  • Parallel Testing - 12/9 through 12/22
  • SOLAR v 8.0 unavailable 430 PM 1/4/2007
    through 1/9/2007
  • Go-Live Testing 1/9/2007
  • SOLAR v 8.9 access resumed 1/10/2007