Title: Shipping, Installation and Interfaces
1Shipping, Installation and Interfaces
RFCC Module Preliminary Design Review June 4,
2008
- Steve Virostek
- Lawrence Berkeley National Lab
2Topic Summary
- Module shipping logistics
- Delivery to RAL
- Module re-assembly at RAL
- Installation in MICE Hall
- Module interfaces
- Flanges and seals
- Base mounting
- RF feeds
- Utility requirements
3Module Shipping Logistics
- Cavities, couplers, coolers pumps removed
- Vacuum vessel/magnet mounted on short stand
- Short stand also used during assembly
- Coupling coil magnet shipped warm without
cryocoolers in place - Cavities and couplers will be packaged separately
to prevent damage - Vacuum vessel and cavities are to be blanked off
and backfilled with N2
4RFCC Module Shipping Configuration
Cryocoolers removed Cavities removed
Couplers removed Vacuum pumps removed
- Module short stand used for
- Initial module assembly
- Shipping to RAL
- Moving into MICE Hall
5Delivery to RAL
- Module arrives on short stand without cavities,
coolers or couplers installed - MICE Hall door height 3360 mm
- Module height on short stand 2844 mm
- Height is without cryocoolers installed
- Roller dollies w/forklift used to move into hall
100 mm tall Roller dollies
6MICE Hall Access
7Re-assembly of Module at RAL
- Unpack cavities, couplers, coolers, pumps
- Operating stand placed on lateral tracks
- Vacuum vessel/coupling coil is loaded onto
operating stand for final assembly - Portable clean room erected around module
- Cavities are installed using special lift fixture
- Couplers and tuner actuators are installed after
cavity is aligned and supported w/struts - Vacuum pumps are added to complete module
- Final alignment performed before translation
8Re-assembly of Module at RAL
Support stand in place on rail platform
9Empty module lifted over support
10Re-assembly of Module at RAL
Module lowered onto support
11Re-assembly of Module at RAL
Support stand gussets added
12Re-assembly of Module at RAL
Support stand gussets added
13Re-assembly of Module at RAL
Cryocooler(s) installed
14Re-assembly of Module at RAL
Cryocooler(s) installed
15Re-assembly of Module at RAL
RF cavities installed from either end
16Re-assembly of Module at RAL
Module with all four cavities installed
17Re-assembly of Module at RAL
Cavity tuner actuators added
18Re-assembly of Module at RAL
Cavity tuner actuators added
19Re-assembly of Module at RAL
Module vacuum pumps installed
20Re-assembly of Module at RAL
Module vacuum pumps installed
21Re-assembly of Module at RAL
RF couplers installed
22Re-assembly of Module at RAL
RF couplers installed
23Installation in MICE Hall
- Module assembled on lateral tracks
- Module aligned and shimmed to correct height
- Bellows on either end of module are pulled back
into open position and O-ring in place - Moved into position w/rails for final alignment
- Bellows are released and flanges are sealed
- Bellows are locked out using bridging bolts
- RF and utilities are connected to module
24Module Flange Connection
End flange O-ring seal
Formed bellows
Flange through holes
25Flanges and Seals
- Flanges designed to mate with AFC module
- AFC flanges are flat w/no grooves or bellows
- RFCC modules have bellows and O-ring grooves on
flanges at either end - Bellows have gt1 cm of total travel
- Bellows are locked out after installation to
provide a means of transmitting forces between
modules
26RFCC Bellows and Flange
Bellows pull back bolts
Elastomer or Helicoflex all-metal O-ring
Clamping bolts
MICE RF and Coupling Coil Module Summary of the
Design and Fabrication Plan
Page 26
Allan DeMello - Lawrence Berkeley National Lab
- June 4, 2008
27Module Joint Sealing Issues
- MICE module joints may need somewhat frequent
disassembly (reconfiguring, maintenance, repair) - O-rings will provide the most reliable and cost
effective (inexpensive and re-useable) solution - O-rings are acceptable for use in MICE
environment - But, MICE should demonstrate all technologies for
a future machine including the use of metal seals - The O-ring groove is design to accept a
Helicoflex all-metal O-ring for demonstration
purposes
MICE RF and Coupling Coil Module Summary of the
Design and Fabrication Plan
Page 27
Allan DeMello - Lawrence Berkeley National Lab
- June 4, 2008
28Module Base Mounting
- Module base connection to rails identical to that
used on the Spectrometer Solenoid - Six mounting plates are welded to the base of the
module support stand - Precise geometry and location of the mounting
plates to be coordinated w/RAL during CM21 - All magnetic loads are carried to the floor
through the mounting plates
29Module Mounting Provision
- Six mounting plates to be welded to the support
stand base for installation on rails - Similar to spectrometer solenoid mounting scheme
30Cavity RF Feeds
- Eight RF feeds/module use standard 4 RF coax
- Cooling water for loop is required (ltlt1 lpm each)
- Adapter on end of couplers isolates ceramic RF
windows from forces during installation - Location of coax interface w.r.t. module center
TBD
RF feeds
31Module Utility Requirements
- Cryomech Model PT-415 cryocoolers (2 or 4 each
total) - 50 Hz AC 10.5 kW _at_ 200/220 or 380/420 V, 3 phase
- Cooling minimum 12 lpm of water _at_ 80ºF max
- 300 A Power Supplies American Magnetics (2 ea
total) - 50-60 Hz AC 3.5 kW _at_ 208 V, 3?, forced air
cooled, rack mnt. - Vacuum 10-3 torr _at_ startup thru a 25 mm flanged
port - Cavity cooling water 8 lpm/per cavity
- Power for periodic getter pump regeneration (TBD)
- Liquid cryogens LN2 and LHe for cooldown (qty
TBD) - Instrumentation monitoring requirements
- Various voltages, temperature, He level, heaters,
pressure, vac.
32Cryocooler Compressor
- Dimensions
- 61x58x97 (LxWxH, cm)
- On 7 cm ? wheels
- Weight
- 223 kg
- He flex line length
- 20 meters
- Lifting eyes
- 4 ea on top (one/corner)
- 6 meters min. to magnets
33Summary
- Module to be shipped w/sensitive components
removed and packaged separately - Short shipping stand provides comfortable
clearance through MICE Hall door - Module re-assembly at RAL will require a portable
clean room - Installation in MICE Hall
- Module interfaces to be finalized soon
- Flanges and seals, base mounting, RF feeds
- Utility requirements have been established