Shipping, Installation and Interfaces - PowerPoint PPT Presentation

1 / 33
About This Presentation
Title:

Shipping, Installation and Interfaces

Description:

MICE RF and Coupling Coil Module PDR Shipping, Installation ... MICE module joints may need somewhat frequent disassembly (reconfiguring, maintenance, repair) ... – PowerPoint PPT presentation

Number of Views:22
Avg rating:3.0/5.0
Slides: 34
Provided by: steve799
Category:

less

Transcript and Presenter's Notes

Title: Shipping, Installation and Interfaces


1
Shipping, Installation and Interfaces
RFCC Module Preliminary Design Review June 4,
2008
  • Steve Virostek
  • Lawrence Berkeley National Lab

2
Topic Summary
  • Module shipping logistics
  • Delivery to RAL
  • Module re-assembly at RAL
  • Installation in MICE Hall
  • Module interfaces
  • Flanges and seals
  • Base mounting
  • RF feeds
  • Utility requirements

3
Module Shipping Logistics
  • Cavities, couplers, coolers pumps removed
  • Vacuum vessel/magnet mounted on short stand
  • Short stand also used during assembly
  • Coupling coil magnet shipped warm without
    cryocoolers in place
  • Cavities and couplers will be packaged separately
    to prevent damage
  • Vacuum vessel and cavities are to be blanked off
    and backfilled with N2

4
RFCC Module Shipping Configuration
Cryocoolers removed Cavities removed
Couplers removed Vacuum pumps removed
  • Module short stand used for
  • Initial module assembly
  • Shipping to RAL
  • Moving into MICE Hall

5
Delivery to RAL
  • Module arrives on short stand without cavities,
    coolers or couplers installed
  • MICE Hall door height 3360 mm
  • Module height on short stand 2844 mm
  • Height is without cryocoolers installed
  • Roller dollies w/forklift used to move into hall

100 mm tall Roller dollies
6
MICE Hall Access
7
Re-assembly of Module at RAL
  • Unpack cavities, couplers, coolers, pumps
  • Operating stand placed on lateral tracks
  • Vacuum vessel/coupling coil is loaded onto
    operating stand for final assembly
  • Portable clean room erected around module
  • Cavities are installed using special lift fixture
  • Couplers and tuner actuators are installed after
    cavity is aligned and supported w/struts
  • Vacuum pumps are added to complete module
  • Final alignment performed before translation

8
Re-assembly of Module at RAL
Support stand in place on rail platform
9
Empty module lifted over support
10
Re-assembly of Module at RAL
Module lowered onto support
11
Re-assembly of Module at RAL
Support stand gussets added
12
Re-assembly of Module at RAL
Support stand gussets added
13
Re-assembly of Module at RAL
Cryocooler(s) installed
14
Re-assembly of Module at RAL
Cryocooler(s) installed
15
Re-assembly of Module at RAL
RF cavities installed from either end
16
Re-assembly of Module at RAL
Module with all four cavities installed
17
Re-assembly of Module at RAL
Cavity tuner actuators added
18
Re-assembly of Module at RAL
Cavity tuner actuators added
19
Re-assembly of Module at RAL
Module vacuum pumps installed
20
Re-assembly of Module at RAL
Module vacuum pumps installed
21
Re-assembly of Module at RAL
RF couplers installed
22
Re-assembly of Module at RAL
RF couplers installed
23
Installation in MICE Hall
  • Module assembled on lateral tracks
  • Module aligned and shimmed to correct height
  • Bellows on either end of module are pulled back
    into open position and O-ring in place
  • Moved into position w/rails for final alignment
  • Bellows are released and flanges are sealed
  • Bellows are locked out using bridging bolts
  • RF and utilities are connected to module

24
Module Flange Connection
End flange O-ring seal
Formed bellows
Flange through holes
25
Flanges and Seals
  • Flanges designed to mate with AFC module
  • AFC flanges are flat w/no grooves or bellows
  • RFCC modules have bellows and O-ring grooves on
    flanges at either end
  • Bellows have gt1 cm of total travel
  • Bellows are locked out after installation to
    provide a means of transmitting forces between
    modules

26
RFCC Bellows and Flange
Bellows pull back bolts
Elastomer or Helicoflex all-metal O-ring
Clamping bolts
MICE RF and Coupling Coil Module Summary of the
Design and Fabrication Plan
Page 26
Allan DeMello - Lawrence Berkeley National Lab
- June 4, 2008
27
Module Joint Sealing Issues
  • MICE module joints may need somewhat frequent
    disassembly (reconfiguring, maintenance, repair)
  • O-rings will provide the most reliable and cost
    effective (inexpensive and re-useable) solution
  • O-rings are acceptable for use in MICE
    environment
  • But, MICE should demonstrate all technologies for
    a future machine including the use of metal seals
  • The O-ring groove is design to accept a
    Helicoflex all-metal O-ring for demonstration
    purposes

MICE RF and Coupling Coil Module Summary of the
Design and Fabrication Plan
Page 27
Allan DeMello - Lawrence Berkeley National Lab
- June 4, 2008
28
Module Base Mounting
  • Module base connection to rails identical to that
    used on the Spectrometer Solenoid
  • Six mounting plates are welded to the base of the
    module support stand
  • Precise geometry and location of the mounting
    plates to be coordinated w/RAL during CM21
  • All magnetic loads are carried to the floor
    through the mounting plates

29
Module Mounting Provision
  • Six mounting plates to be welded to the support
    stand base for installation on rails
  • Similar to spectrometer solenoid mounting scheme

30
Cavity RF Feeds
  • Eight RF feeds/module use standard 4 RF coax
  • Cooling water for loop is required (ltlt1 lpm each)
  • Adapter on end of couplers isolates ceramic RF
    windows from forces during installation
  • Location of coax interface w.r.t. module center
    TBD

RF feeds
31
Module Utility Requirements
  • Cryomech Model PT-415 cryocoolers (2 or 4 each
    total)
  • 50 Hz AC 10.5 kW _at_ 200/220 or 380/420 V, 3 phase
  • Cooling minimum 12 lpm of water _at_ 80ºF max
  • 300 A Power Supplies American Magnetics (2 ea
    total)
  • 50-60 Hz AC 3.5 kW _at_ 208 V, 3?, forced air
    cooled, rack mnt.
  • Vacuum 10-3 torr _at_ startup thru a 25 mm flanged
    port
  • Cavity cooling water 8 lpm/per cavity
  • Power for periodic getter pump regeneration (TBD)
  • Liquid cryogens LN2 and LHe for cooldown (qty
    TBD)
  • Instrumentation monitoring requirements
  • Various voltages, temperature, He level, heaters,
    pressure, vac.

32
Cryocooler Compressor
  • Dimensions
  • 61x58x97 (LxWxH, cm)
  • On 7 cm ? wheels
  • Weight
  • 223 kg
  • He flex line length
  • 20 meters
  • Lifting eyes
  • 4 ea on top (one/corner)
  • 6 meters min. to magnets

33
Summary
  • Module to be shipped w/sensitive components
    removed and packaged separately
  • Short shipping stand provides comfortable
    clearance through MICE Hall door
  • Module re-assembly at RAL will require a portable
    clean room
  • Installation in MICE Hall
  • Module interfaces to be finalized soon
  • Flanges and seals, base mounting, RF feeds
  • Utility requirements have been established
Write a Comment
User Comments (0)
About PowerShow.com