Title: Competition Commission Appeal decision for Modification Proposals 0116V
1Competition Commission Appeal decision for
Modification Proposals 0116V 0116A
2Context
- CC was pretty deferential to Ofgem.
- Short timescales precluded detailed analysis of
many issues. - CC assessment based largely on Decision and FIA.
- Industry support and BGT intervention essential
to make CC listen. - Raising procedural concerns helped sow the seeds
of doubt. - Process favours economic rather than legal
arguments - CC asked NGG for their views on key points.
- Appeal was upheld based on certain key points.
- Many points were unproven or no firm conclusion
reached. - Cost of appeal thought to be in excess of 1m.
Both 0116V and 0116A decisions quashed CC
findings useful reference for Review Group but
NOT DEFINATIVE
3E.ON UKs Grounds of Appeal
- Pre-judgement
- Modification 116V had a substantially negative
CBA (gt28m) - The decision understates the negative CBA
- Incorrect analysis of qualitative benefits
- Non-discrimination
- Adverse impact on competition
4The main issues considered by CC
- The Role of GEMA
- User Commitment
- Interruptibility Transmission Access Regulation
1775 - Flexibility Capacity
- Cost- benefit analysis
- Procedural matters
- Remedies
5The Role of GEMA
- Consensus on statutory duties and objectives.
- Not helpful to consider these in a hierarchical
manner. - GEMA does not have power to propose modifications
- GEMAs directions must comply with Transmission
Access Regulation 1175/2005. - GEMA does not have a specific duty to promote
promote non-discrimination, although this may be
a legitimate policy objective in pursuit of GEMAs
other objectives. -
6User Commitment
- Consider 4 years rather than 1 year provides more
robust basis for investment decisions. - Did not accept the E.ON argument that reliance on
user commitments will have a chilling effect on
NTS investment. - Barriers to entry not considered material.
- CC omitted to consider the flexibility of current
ARCA user commitments, e.g. rescheduling first
gas date. - GEMA mistakenly believed current arrangements
allow for capacity reductions on 1 months notice.
GEMAs position upheld
7Interruptibility and Transmission Access
Regulation 1775
- GEMA argued that they could not approve 116A as
this was illegal as current charges for
interruptible services do not reflect the
probaility of interruption. - GEMA criticised for not stating this in their
Decision. E.ON given permission to amend its
grounds of appeal. - E.ON countered stating that the withdrawal of the
up-front long-term (greater than 1 year)
interruptible service under 116V was illegal.
CC concluded that neither 116A or 116V were
incompatible with the Regulation
8Interruptibility
- GEMA argued that current firm users
cross-subsidise interruptible users as such users
are rarely interrupted. - GEMA said there was a risk of a flight from
firm. - E.ON demonstrated that charges for interruptible
users cover variable cost and make a contribution
to fixed cost and facilitate the efficient use of
spare capacity. - E.ON argued that interruptible users do not drive
new investment (capacity cost) and no evidence
of a flight from firm. - CC did not conclude the current arrangements are
discriminatory or potentially discriminatory.
CC conclude that 116V could deliver competition
and efficiency
However this is contingent on incentives for the
release of interruptibe capacity (note this did
not form part of 116V)
9Flexibility
- BGT/E.ON emphasised the additional costs of
complexity - E.ON/BGT argue there is no current shortage of
flexibility the new arrangements likely to create
artificial scarcity. - GEMA argued for pre-emptive action and potential
risk of future scarcity. - CC not convinced about the risk of future
scarcity, the need for action now and whether
benefits claimed will be realised - GEMA based their Decision on two errors of fact
namely- GDNs currently purchase NTS
flexibility- TCCs are subject to no restrictions
in how they vary their offtake. - E.ON argue that flexibility was not a real
product. - CC did not grasp the difference between
flexibility capacity and linepack.
10Flexibility Continued
- GEMA criticised for inadequate competition
analyisis e.g. competition between a price
regulated part (GDN) and an unregulated party
(shipper). - CC says GDNs and shippers are relevantly similar
wrt to offtake capacity as they place the same
demands i.e. the same costs on the system.
CC erred in its analysis of the benefits of the
flexibility product as these may only arise if it
become scarce
11Cost Benefit analysis
- E.ON said the cost pf 116V closer to 120m rather
than 28m, that up-front transporter and Irish
cost were wrongly omitted (the later contrary to
European Law). - BGT identified the cost of flexibility alone to
be 45m by comparison between 116V and 116CVV. - E.ON/BGT stated it was implausible that
speculative benefits of the flexibility product
could offset the negative cost of 45m. - CC concluded that GEMA erred in its approach to
transporter costs but it was not unreasonable to
ignore Irish costs. - CC said cost benefit analysis of the flexibility
product was flawed given inadequate explanation
of nature and extent of benefits. - CC considered confusion in the Decision between
principles of non-discrimination may have led
to double counting of benefit.
GEMA made a number of errors in its cost-benefit
analysis
12Cost benefit CC deferentialPara
6.156Unless the regulator has erred in logic
or principle, theCC will be slow to overturn the
regulators quantificationof that cost and
benefit.
13Procedural matters
- E.ON evidence included reference to conditional
licence condition, sunset clause and other
irregularities. - Disclosure of GEMA papers showed decision was
finely balanced. - Ofgem admitted it was the progenitor of the of
the proposal. - However, the CC did not find GEMA had prejudged.
- CC expressed concerns about the effectiveness of
the modification procedures where GEMA is the
effective pregenitor of a proposal given this may
give the appearance of pre-judgement. (para.
6.192) - It found GEMA had failed to have proper regard to
the principle under which regulatory activities
should be transparent under section 4AA95A) of
the Gas Act 1986. - Decision was unaffected by errors of fact made by
GEMA.
Decision not procedurally flawed but misgivings
highlighted
14Key findings
15Remedies
- Quashing order for 116V and 116A Decisions.
- GEMA and E.ON agree that there were more than one
decision. - CC keen not to close-off option for further
reform. - CC seem to believe that other proposals 116BV,
116CVV and 116D are back in the table - Note notices of non-implementation were issued
for each of the modification proposals 116A,
116BV, 116CVV and 116D. - Despite the quashing order the Joint Office on
behalf of transporters have yet to revoke the
implementation notice for 116V.
16Suggested matters for further consideration
- User commitments must be flexible and allow
reservation more than 6 months in advance. - Access arrangements should take into account the
different needs of different offtake points
whether these are generators or other large
users, shippers, GDNs, storage or
interconnectors. - Interruption service design must take into
account the cost such users place on the system
and be compatible with Regulation 1775Do such
users make use of peak capacity? What
contribution (if any) do they make to fixed
costs?Do such users drive investment?Should the
service be offered up-front?What is its function
as an anti-hording device (use-it-or-lose-it
capacity)?What about back-up supplies?