Title: Bond Construction Update Citizens Oversight Committee
1Bond Construction UpdateCitizens Oversight
Committee
Cordoba Corporation
- Long Beach Community College District
- January 28, 2008
BUILDING ? TOMORROW ? TODAY
2Agenda
- Completed Construction Projects
- Current Upcoming Construction Projects
- South Quad Complex Structure
- LAC Central Plant Structure
- LAC Learning Resources Center Structure
- LAC Building R, Mens Gymnasium Renovation
- PCC Central Plant
- PCC Learning Resources Center
- PCC Industrial Tech Phase 1
- Q A
3Completed Construction Projects
Various Projects Completed in 2006 2007
- PCC Industrial Technology Center Phase 2 7/07
- PCC Central Plant Utilities, LAC Central Plant
SQC Utilities 6/07 - LAC/LRC Interim 5/07
- East Campus Demo 12/06 LAC Mens Gym Façade
Replacement (FEMA Insurance Funded) 8/06 - LAC/LRC Utilities 6/06
- PCC CDC 4/06
- Mens Gym Boiler Replacement 4/06
- LAC Athletic Field 3/06
- District Facilities Warehouse Complex 1/06
4LAC Facility Site Plan
l i b e r a l a r t s
5Current and UpcomingConstruction Projects
LAC Central Plant Structure
- Part of Infrastructure Master Plan Improvements
- Awarded to Siemens on DBOM Contract
- Construction 55 Complete
- Completion Anticipated Summer 2008
6Current and UpcomingConstruction Projects
LAC/Learning Resources Center Structure
- Construction 38 Complete
- Utility Installation Complete Under Previous
Phase (Bid Pkg. 1) - Completion Anticipated First Quarter 2009
7Current and UpcomingConstruction Projects
LAC Building R, Mens Gymnasium Renovation
- Original floor and bleachers removed
- New sprung wood flooring system
- Lettering, graphics and game lines applied to the
new floor system - New telescopic bleachers installed on both the
main floor and the mezzanine level - Interior of the gym painted
- Lamps replaced for new fixtures and electrical
capabilities added
8Current and UpcomingConstruction Projects
South Quad Complex Structure (Bid Pkg. 3)
- Construction Approx. 48 Complete
- Additional Modern Classrooms, Multi-purpose Rm.,
Offices, etc. - Shifts Campus Center South of Carson off Lew
Davis - Completion Anticipated Summer 2008
9PCC Facility Site Plan
p a c i f i c c o a s t
10Current and UpcomingConstruction Projects
PCC Central Plant
- Part of Infrastructure Master Plan Improvements
- Early Utility Package Construction Complete
- DBOM Contract Awarded to Siemens Finalizing
Value Engineering Negotiations - Construction Approximately 20 Complete
- Completion Anticipated Summer 2008
11Current and UpcomingConstruction Projects
PCC Learning Resources Center
- Construction 55 Complete
- Modern Facility with Computer Lab and Multimedia
- Expanded Facility
- Bridge to Bldg. EE
- Completion Anticipated Winter 2008
12Current and UpcomingConstruction Projects
PCC Industrial Technology Center Phase 1
- Replaces Existing Antiquated Structures
- Construction is 8 Complete
- Modern Facility Houses Machine Tool and Welding
Departments - New Campus Bookend
- Completion Anticipated Winter 2009
13Escalation Trends per Leland Saylor Associates
14QUESTIONS ANSWERS
Cordoba Corporation
- Prepared by
- Bond Management Team
- January 28, 2008
BUILDING ? TOMORROW ? TODAY