Staffordshire Highways - PowerPoint PPT Presentation

1 / 10
About This Presentation
Title:

Staffordshire Highways

Description:

Staffordshire County Council, Enterprise and Wrekin. Keeping Staffordshire's 3,500 miles of road well maintained efficiently and cost ... – PowerPoint PPT presentation

Number of Views:49
Avg rating:3.0/5.0
Slides: 11
Provided by: cfie9
Category:

less

Transcript and Presenter's Notes

Title: Staffordshire Highways


1
Staffordshire Highways
A partnership working together for
you Staffordshire County Council, Enterprise and
Wrekin. Keeping Staffordshires 3,500 miles of
road well maintained efficiently and cost
effectively.
They deliver a complex, value-for-money, public
highway service. Benefits of our partnership
include increased buying power greater
accountability better long term planning and a
committed, highly skilled local workforce.
2
Delivering in Partnership

Staffordshire Highways Partnership
Ian Turner Head of Highway Network
Management Pete Boulton Operations Manager
3
Workshop Outline
  • Development of Staffordshire Highways
  • Where we were
  • Where we are
  • Where were going
  • Key Themes Relating to LTP Delivery
  • Efficiencies
  • Works Planning ECI
  • Contract mechanisms

4
Where We Were
  • 5 Agency arrangements with Districts
  • Separate design maintenance set up
  • Gap between transport strategy and delivery
  • Term maintenance contract schedule of rates
  • Annual tenders different in each division
  • Spot tenders for improvements

5
Where We Are
  • All work delivered by County
  • Term construction contract
  • Term maintenance contract
  • County Council reorganised on area basis
  • Partnership approach organisations aligned

6
Where Were Going
  • Single contractor for majority of work
  • Midlands Alliance contract for large or one offs
  • Risk transfer for some work types

7
Some Key Themes
  • Efficiencies
  • Works planning ECI
  • Contract Mechanisms

8
Efficiencies
  • SCC Overhead 650k
  • Enterprise Overhead 500k
  • Winter Maintenance 440k
  • Environmental Maintenance 88k
  • Cyclical Maintenance 47k
  • Recycling ??m (GFA)
  • Patching

9
Works Planning ECI
  • Longer term programmes
  • Smooth resource requirements
  • Co-ordination with other works
  • Better designs

10
Contract Mechanisms
  • Selection of contractors
  • Contract forms/periods
  • Cost plus cost not price
  • Innovation
  • Performance management
  • Value for money
Write a Comment