Title: Blackpools and Lancashires Joint Waste PFI Contract
1Blackpools and LancashiresJoint Waste PFI
Contract
2Many Dimensions?
- Background to the Procurement
- Scope of the Project
- The Procurement process
- Examples of some of the risk issues in the PFI
Waste Sector -
3 The future of waste management in Blackpool and
Lancashire until 2035
- Culmination of a process that started in
1997with the establishment of the Joint Waste
Strategy Steering Group (Subsequently renamed
Lancashire Waste Partnership) - Forward-looking action recognising the risks to
the Authorities of the Landfill Directive to take
effect in 2010 and the long lead-times to
successfully deliver new waste infrastructure
4Risks identified in 1997
- Implications of Landfill Directive limits on
landfill (against 1995/6 levels) - Max 75 municipal waste to landfill by 2010
- Max 50 municipal waste to landfill by 2013
- Max 35 municipal waste to landfill by 2020
- Lancashire Minerals and Waste Local Plan
under-provision of landfill capacity, against
known demand, by 25 in Lancashire by 2006 - No waste disposal assets following the sale of
the LAWDC by 2003 - Recognition that waste management needed to be
plannedon an integrated basis of both collection
and disposal - Recognition of the long lead-in time to new
infrastructure provision (7years?)
5The Lancashire Waste Strategy
The Lancashire Waste Strategy
- The result of 3 years work by all fifteen
authorities - Two major public consultation exercises
1999
2000
6Strategy Approved 2001
- 20,000 Responses to Draft Strategy
- 75 satisfaction
- Everyone wanted by higher and earlier targets for
recycling - Serving 1.4 million residents and managing 1
million tonnes of waste per year - 400,000 tonne per year waste reduction target by
2020 (growth reduced from 3 to 1 by 2005) - 40 recycling composting by 2005
- 56 by 2015
- 90 of households to receive 3-stream collection
service by 2005 - 50 recovery from recycling centres
- Landfill reduced from 85 to 20
- Network of new waste management infrastructure
7 Energy from Waste Incineration
- Provide capacity for 325,000 tonnes of Energy
from Waste incineration by 2010, if the
Strategys waste minimisation and recycling
targets are not exceeded. - A final review of the decision to build will take
place in 2005. - Environmental Standards will be equivalent to the
highest operational standards anywhere in the
world. - Most controversial - a commitment to do
everything possible to avoid incineration
8Mechanical Biological Treatment (MBT)
- In the two years following the approval of the
Strategy the Partnership continued to explore
alternatives to EfW - In 2003 the Lancashire Waste Partnership endorsed
a revision to the Strategy that replaced the need
for EfW Incineration with Mechanical Biological
Treatment of residual waste - MBT is a generic term applied to a range of
technologies that in-effect compost the waste
and mechanically recover recyclable materials.
Most systems produce Refuse Derived Fuel as part
of the process or alternatively pre-treat the
waste prior to landfill and produce a soil
improver - Factory processing of waste
9Risk context to the PFI Procurement
- Primary Risks relate to service failure
- Secondary Risks are financial and land use
planning risks
10Service failure risks
- After April 2010 the Council has no assets or
contracts to dispose of Lancashires waste
without them Councils cannot collect rubbish - The only significant landfill capacity left in
Lancashire around this time will be the Whinney
Hill landfill in Hyndburn (based upon current
rates of disposal) - Geographical differences long term contractual
arrangements mean some sites will have longer
life eg Jamieson Road at Fleetwood could be
available to 2016 - Theses site are controlled by SITA and there is
no guarantee that the Council will be able to
secure capacity at these sites if it wished to
move to a landfill based strategy there are
regional demands - However, we have procured sufficient capacity in
the context of the low PFI landfill demand until
2025 to mitigate this risk
11Service failure risks
- Significant price exposure to monopoly supplier
- Collection Authorities will not be able to
operate without local disposal points - New permissions for landfills would only be
possible based upon capacity assumptions that
assume the Landfill Directive has been
complied-with and sites would need to be
identified in the in the context of the Local
Development Framework - The PFI infrastructure is designed to mitigate
these risks greatly reducing landfill
dependence and providing transfer facilities to
distant disposal points if needed - Our strategy and procurement is based upon 1
annual waste growth, if this is exceeded our
problems are greatly magnified
12Financial Risks
- Costs of final landfill disposal with monopoly
supplier and/or long distance disposal ( If this
can be achieved at all) - Landfill tax rising to 35 per tonne by 2010 (Now
a minimum of 48) - Waste Emissions Trading Act Penalties of 150 per
tonne for exceeding the the Councils landfill
allowances (LATS) - These financial instruments are designed to
encourage Councils to deliver the Landfill
Directive - The need to secure over 280 million of capital
to fund the required investment programme - Cost forecasts are based upon 1 annual growth in
waste. If this is exceeded these costs will
increase greatly
13Land-use Planning Risks
- We cannot deliver our services without new
infrastructure whether it be landfill,
incineration, MBT, compost plants, MRFs or simple
transfer stations - The single biggest obstacle to building such
infrastucture is site acquisition and planning
consents - Currently we are in a strong position because we
have a fully integrated strategy underpinning our
planning application / decisions and they comply
with the development plan, national and European
policy - Any application based upon a landfill future,
without meeting the Landfill Directive, is likely
to fail and will also be be open to challenge
through judicial review
14PFI Procurement
- Is therefore essentially an exercise in risk
mitigation - Cannot eliminate all the Councils risks
- Seeks to minimise those risks as far as possible
152004-5 Procurement process
- Four companies short-listed
- Two withdrew leaving two
- SITA and Global Renewables Ltd (GRL)
- 3 bids received 28th February 2005
- A) Biological drying with RDF output (Council to
find market) - B) Biological drying with RDF output plus EfW
plant to burn the RDF - C) Combined anaerobic digestion(biogas) and
bio-stabilisation (composting) process
plus soil improver - All bids exceeded Outline Business Case
affordability levels previously approved by
Cabinet - Output specification re-scoped and Revise and
Confirm bids returned 11th July 2005
16Affordability proportionately the same impacts
for Blackpool Council
- GRL appointed preferred bidder for the PFI
contract September 2005 - Basis of that appointment was to negotiate a
reduced budget impact - Full service costs reduced from 104 million per
annum to 91 million per annum (LCC budget
position) - 13th July 2006 Cabinet authorised move to
financial close of the contract based upon this
affordability position - Increased by 3 million per annum by financial
close - Do minimum costs are higher over project life
- but based upon assumed continuation of the
governments fiscal policies and regime for waste
(taxes and penalties)
17What are we buying through the PFI contract ?
- Two strategic processing facilities at Thornton
and Leyland - 340 tonnes per annum residual waste processing
(MBT) - 110,000 tonnes per annum enclosed vessel
composting - 55,000 tonnes per annum MRF
- 56 diversion of residual waste from landfill
- 95 diversion of kitchen and garden waste from
landfill - 93 diversion of separately collected co-mingled
plastics, metals and glass from landfill - 100 diversion of separately collected paper,
cardboard, textiles, plastics, metals and glass
from landfill - An environmental education service
- A waste minimisation and community engagement
programme - A local market development programme
- 2500 acres of woodland planted 2.5 million trees
18What we are buying In place of landfill
Bio-gas production
Residual waste composting
OGM storage
Bio-filters
Kitchen garden waste composting
Percolation
Residual waste reception
Mechanical separation
Materials recycling facility (MRF)
Environmental Education Centre
19PFI in the Waste Sector
- Waste projects exhibit a significantly different
risk profile to accommodation projects schools,
hospitals, etc - Process performance risk
- Biggest risks in the operational phase not the
construction phase unlike accommodation projects - Major financial penalties for under-performance
20Bidding Consortium
- Global Renewables Ltd (50) and Bovis Lend Lease
(50) - Joint owners of the
- SPV
- The Construction Joint Venture
- The Operating Company
- 5 Banks
21Risk transferSite abnormals and contamination
- Planning policy meant that our sites are former
brown-field sites - Procurement bidding based on assumption of normal
site conditions (including estimated provisional
sums) - Major part of the procurement post preferred
bidder was transferring construction cost and
programming risk for site abnormals to the
contractor - At a cost of over 40 million
- Chemical contamination and 8000 piles per site
- Gain share
22Risk transferProcess performance
- Banks at risk (over 200 million) until plant has
passed its acceptance tests - Ability to achieve landfill diversion targets,
environmental emissions and performance levels,
bio-stabilisation guarantees - Massive technical due-diligence on new technology
both funders and council
23Risk transferBio-stabilisation
- At the heart of the process is the diversion of
BMW from landfill through bio-stabilisation - Key to mitigating LATS penalties
- Evolving UK regulatory framework for MBT (no UK
plants) - Established German methodologies
- Italian sub-contactors providing process
guarantees
24Risk transferWaste volume and composition
- Shared volume risk minimum guaranteed tonnages
- 3-stream volumes a contractor risk
- Waste composition in terms of metal, plastic,
kitchen waste etc, critical to processing
performance shared risk - Complex waste-auditingand diversion performance
model
25Planning and licensing risks retained
- Could add a further 20 million to the capital
costs - Current Judicial Review application in relation
to grant of planning permission for the Leyland
site - Delay also means potential for LATS penalties
26Where we are today
- Our service failure risks significantly mitigated
for a key front line service - Big increases in expenditure but largely fixed
and known - One of the most environment friendly waste
management solutions in the world - A deal that has not only closed but construction
starts immediately - We are not there yet but we are a lot closer
27- Thanks for listening
- Any questions?