NITROGEN OPERATIONS UNITS - PowerPoint PPT Presentation

1 / 6
About This Presentation
Title:

NITROGEN OPERATIONS UNITS

Description:

NITROGEN OPERATIONS UNITS. 2004 Phosphate Process Unit ... Control Center Monitoring the TDC Screens & Observing the Gypsum Filtration by Remote Camera ... – PowerPoint PPT presentation

Number of Views:70
Avg rating:3.0/5.0
Slides: 7
Provided by: tshe5
Category:

less

Transcript and Presenter's Notes

Title: NITROGEN OPERATIONS UNITS


1
NITROGEN OPERATIONS UNITS
PHOSPHATE OPERATIONS CAPACITY STORAGE
2004 Phosphate Process Unit Capacities and
Storage Values
2
PHOSPHATE OPERATIONS CONTROL ROOM
An Agrium Redwater Granulation Panel Operator at
the Phosphate Control Center Monitoring the TDC
Screens Observing the Gypsum Filtration by
Remote Camera
3
PHOSPHATE OPERATIONS UNITS
An Aerial View of Both Sulphuric Acid Units, the
Phosphoric Acid Unit, Granulation Units
4
PHOSPHOGYPSUM STACK EXTENSION - AERIAL VIEW
TOTAL EXTENSION (DOTTED YELLOW)
INTERCEPT SYSTEM (BLUE)
PUMPHOUSE (LIGHT BLUE)
UNDER DRAIN SYSTEM (BLUE)
EXISTING GROUNDWATER RECOVERY SYSTEM - TO BE
REMOVED (DOTTED BLUE PURPLE)
GYPSUM STARTER DYKE - WORKING LEVEL (RED)
PERIMETER DYKE (DOTTED ORANGE PURPLE)
SLURRY WALL (GREEN)
Aerial View of the Phosphogypsum Stack Extension
Including all Required Components
5
PHOSPHOGYPSUM STACK EXTENSION - SCHEDULE
Construction Schedule for Phase I of the
Phosphogypsum Stack Extension Project View of
Scraping Equipment Removing Top Soil from the
Extension Area
6
PHOSPHOGYPSUM STACK EXTENSION - SECTION VIEW
SLURRY WALL CONSTRUCTION
HDPE LINER SHIPMENT
Existing Gypsum Stack
PROPOSED EXTENSION
PROPOSED EXTENSION
Silty Sand
Clay Till
Sandstone
Clay Shale
UNDERDRAINS
EXISTING INTERCEPT SYSTEM
SOIL-BENTONITE CUT-OFF WALL
HDPE LINER
GAS VENTING SYSTEM
Cutaway View of the Proposed Phosphogypsum Stack
Extension Views of A Slurry Wall Excavator
Equipment and a Shipment of HDPE Liner
Write a Comment