Title: Health Based Compliance Alternatives HBCA under MACT Maximum Achieveable Control Technology: Permitt
1Health Based Compliance Alternatives (HBCA) under
MACT (Maximum Achieveable Control
Technology)Permitting Challenges
- Cindy Phillips, P.E.
- FDEP Bureau of Air Regulation
- 2007 Southeastern Permitting Workshop
- Tampa, Florida
- May 11, 2007
28 Florida Facilities Requested Site-Specific
HBCA for I/C/I Boiler MACT
- 3 Pulp Paper
- 2 Plywood
- 3 Sugar
3HBCA Review
- Modeling reviewed by Bureau of Air Regulation
(BAR) - 7 Permit applications/HBCA reviewed by 3
different FDEP District Offices with parallel
review by BAR - 1 Permit application/HBCA reviewed by BAR
- 3 of the HBCA demonstrations to be audited by EPA
4Challenges
- Florida permitting timeclock does not coincide
with EPA review time for the 3 facilities being
audited. - Most permitting staff have not had risk
assessment training. - Though I/C/I boiler MACT training was offered by
Region 4 in May 2006, - it was not detailed risk assessment training
(none of the district permitting staff were able
to go to it anyway) and - example permit conditions were not provided.
5Tools Developed
- Summary of Subpart DDDDD
- Checklist for HBCA Demonstration
6On-the-job Training
- OAQPS has been very helpful in answering
questions about the HBCA as they arise. - If you have questions, try contacting
- Morris.Mark_at_epamail.epa.gov
- Hirtz.James_at_epamail.epa.gov
- Eddinger.Jim_at_epamail.epa.gov
7On-the-job Training (contd)
- Sample of Permitting Questions and
- OAQPS Answers
8Q A
- Q1. If the maximum modeled manganese
concentration is shown to be within a plant's
property boundary, are they still required to
show a plot plan of nearby residences, or show a
comparison of the HQ HI to the limit of 1.0 at
locations where people live or congregate? - Does the inhalation exposure for the most
exposed individual need to be determined?
9Q A
- A1. No. Many of the submittals OAQPS has
received do not specify locations of residence
(or congregation) but instead locate receptors
along the fenceline and use a Cartesian grid for
all offsite locations, then take the highest
value of all receptors. OAQPS thinks this more
than adequately covers locations of residence and
cong.
10Q A
- Q2. Though manganese testing was not performed at
worst-case scenario, the applicant wants to
demonstrate future compliance with an annual
manganese limit by complying with their current
PM limit and BTU design rate, and assuming the
manganese/PM ratio is the same as during the
non-worst-case stack testing. Is this
acceptable?
11Q A
- A2. This question has come from several States.
- OAQPS is currently discussing this with the
Office of Enforcement and Compliance Assurance
and Office of General Counsel. - OAQPS will get back to us on this.
12Q A
- Q3. Fuel oil analyses from 2005 were used. Is
this acceptable? - No analysis of the on-plant recycled fuel oil
is given at all because it is considered
insignificant and was not quantified during stack
testing. Is this acceptable?
13Q A
- A3. If the fuel testing is acceptable for MACT
compliance, OAQPS thinks it is acceptable to use
in the HBCA. - Is the recycled oil used in small quantities
relative to virgin oil? - Is the AP-42 emission factor significantly
different from the fuel test results? - Seems like if is truly used in small quantities
that a permit condition limiting it could be
possible.
14Q A
- Q4. Section 63.7521 requires that a fuel analysis
plan be submitted no later than 60 days before
the date that you intend to demonstrate
compliance. - Applicants state that since the compliance date
is September 13, 2007, they do not have to submit
these plans yet. - Would OAQPS agree that this is true even for
facilities that have submitted health-based
eligibility demonstrations?
15Q A
- A4. No. Appendix A to subpart DDDDD
section8.(a)(3) requires that the demonstration
must include the fuel analysis.
16Q A
- Q5. If a facility uses the HBCA to get out of
including manganese in the TSM limit, do they
still have to determine compliance with the TSM
limit?
17Q A
- A5. Yes. Annually if by stack test,
- or every 5 years if by fuel analysis.
18Examples of Permit Conditions
- Methods of Operation
- Permitted Capacity
- Stack Information
- Emissions Limits
19Examples of Permit Conditions (contd)
- A.9.a. Hydrogen Chloride. Except as provided in
Conditions A.9.b. and c., hydrogen chloride
emissions shall not exceed 0.09 lb per MMBtu of
heat input. - 40 CFR 63.7500(a)(1) Table 1 to Subpart DDDDD
of Part 63 - Emissions Limits and Work Practice
Standards 9.b - A.9.b. Hydrogen Chloride - Health Based
Compliance Alternative (HBCA). For this
emissions unit, the permittee has self-certified
that they are eligible to use the Health Based
Compliance Alternative (HBCA) for hydrogen
chloride emissions utilizing the procedures
prescribed in Appendix A of 40 CFR 63 Subpart
DDDDD and as authorized in 40 CFR 63.7507(a). - 40 CFR 63.7507(a)
20Examples of Permit Conditions (contd)
- A.9.c. Hydrogen Chloride - Health Based
Compliance Alternative (HBCA). The chlorine
emissions from this emissions unit shall not
exceed 0.05 lb per MMBtu of boiler heat input1.
This emissions limit is based on an annual
average. The emissions unit is assumed to be in
compliance with this chlorine emissions limit
when the following conditions are met - 1 From January 2005 January 2007
Fuel Analyses, potential HCl emission rate from
fuels bark0.014 lb/MMBtu, bark/wastewater wood
residuals0.025 lb/MMBtu, No. 6 Fuel Oil3.6x10-3
lb/MMBtu. Applicant utilized a safety factor of
2 to bark/wastewater wood residuals results
(highest) due to potential variability in
chlorine content of bark and wastewater wood
residuals.
21Examples of Permit Conditions (contd)
- (1) Exhaust gases shall be released through a
vertical stack with a release height of 257 feet
(78.3 meters), 11.0 feet (3.35 meters) in
diameter, 450F (505K), 235,000 acfm gas flow
rate, and 41.2 fps (12.6 mps) velocity. The
stack location is UTM Zone 17, E.456,274.5,
N.3,394,248.9.
22Examples of Permit Conditions (contd)
- (2) Operate a multicyclone (without flyash
reinjection) followed by an ESP. - (3) Fire carbonaceous fuel (including wastewater
wood fiber residuals, No. 6 Fuel Oil, No. 2 Fuel
Oil, On-Specification Fuel Oil as stated in
Condition A.2. above
23Examples of Permit Conditions (contd)
- (4) For the purposes of the HCl HBCA, the
worse-case fuel mix has been identified as the
combination of carbonaceous fuel (bark and
wastewater wood fiber residuals) and No. 6 Fuel
Oil. This mix consists of a maximum of 25 tons
per hour2,3 from bark and wastewater wood
residuals and 348 MMBtu/hr3,4 from No. 6 Fuel
Oil, and - 2 Based on 9,137 Btu/lb for bark and
wastewater wood fiber residuals sludge from
sludge press from January 2005 submitted fuel
analysis from HBCA eligibility. - 3 Maximum firing rate of any
combination of fuels, as identified in Condition
A.2. above, 457.0 MMBtu/hr of carbonaceous fuel
and 348 MMBtu/hr of No. 6 Fuel Oil. - 4 Based on 150,257 Btu/gallon for No. 6 Fuel
Oil from January 2005 submitted fuel analysis
from HBCA eligibility.
24Examples of Permit Conditions (contd)
- (5) Maximum boiler heat inputs as stated in
Condition A.2. above. - Should the emission unit not meet any one of
the stated above criteria, the owner or operator
shall update the HBCA eligibility demonstration
as stated in Condition A.9.d. - 40 CFR 63.7507(a) 11(a) of Appendix A of 40
CFR 63 Subpart DDDDD
25Examples of Permit Conditions (contd)
- A.9.d. Updated HBCA Eligibility Demonstration and
Resubmittal. The HBCA eligibility demonstration
must be updated and resubmitted each time that
any of the parameters that defined the boiler as
eligible for the HBCA changes in a way that could
result in increased HAP emissions or increased
risk from exposure to emissions. These
parameters include, but are not limited to, fuel
type, fuel mix (annual average), type of control
devices, HAP emission rate, stack height, process
parameters (e.g., heat input capacity), relevant
reference values, and locations where people
live). - If the HBCA eligibility demonstration is being
updated to account for an action described above
that is under the control of the facility (e.g.
change in heat input capacity of the boiler), the
revised eligibility demonstration must be
submitted to the Department prior to making the
change. The Permittee shall apply for and obtain
a Title V Permit Revision in order to incorporate
the change into the Title V Operation Permit.
26Examples of Permit Conditions (contd)
- A.9.d.(contd) Should it be determined that the
emissions unit is no longer eligible for the
HBCA, then the Permittee shall comply with the
applicable emission limits, operating limits, and
compliance requirements in 40 CFR 63 Subpart
DDDDD prior to making the process change and
revising the permit. - If the HBCA eligibility demonstration is being
updated to account for an action described above
that is outside of the control of the facility
(e.g. change in a reference value), and that
change causes the boiler to no longer be able to
meet the criteria for the HBCA, the Permittee
shall comply with the applicable emission limits,
operating limits, and compliance requirements in
40 CFR 63 Subpart DDDDD within 3 years. - 11(a) and 11(b) of Appendix A of 40 CFR
63 Subpart DDDDD
27Examples of Permit Conditions (contd)
- A.9.e. Updated HBCA Eligibility Demonstration
Review. The revised eligibility demonstration
may be reviewed by the Department or EPA to
verify that the demonstration meets the
requirements of Appendix A of 40 CFR 63, Subpart
DDDDD and is technically sound (i.e. use of the
look-up tables is appropriate or the
site-specific assessment is technically valid).
If the Permittee is notified by the Department or
EPA of any deficiencies in the submission, the
emissions unit will not remain eligible for the
HBCA until the Department or EPA verifies that
the deficiencies are corrected. - 11(c) of Appendix A of 40 CFR 63 Subpart
DDDDD
28Examples of Permit Conditions (contd)
- A.9.f. HBCA - Recordkeeping. Records of the
information used in developing the HCl HBCA
Eligibility Demonstration for this boiler must be
kept, including all of the information specified
in Section 8 of Appendix A of 40 CFR 63 Subpart
DDDDD. - 12 of Appendix A of 40 CFR 63 Subpart DDDDD
29Questions?
- Contact
- Cindy Phillips, P.E.
- FDEP Bureau of Air Regulation
- (850)921-9534
- Cindy.Phillips_at_dep.state.fl.us