Health Based Compliance Alternatives HBCA under MACT Maximum Achieveable Control Technology: Permitt PowerPoint PPT Presentation

presentation player overlay
1 / 29
About This Presentation
Transcript and Presenter's Notes

Title: Health Based Compliance Alternatives HBCA under MACT Maximum Achieveable Control Technology: Permitt


1
Health Based Compliance Alternatives (HBCA) under
MACT (Maximum Achieveable Control
Technology)Permitting Challenges
  • Cindy Phillips, P.E.
  • FDEP Bureau of Air Regulation
  • 2007 Southeastern Permitting Workshop
  • Tampa, Florida
  • May 11, 2007

2
8 Florida Facilities Requested Site-Specific
HBCA for I/C/I Boiler MACT
  • 3 Pulp Paper
  • 2 Plywood
  • 3 Sugar

3
HBCA Review
  • Modeling reviewed by Bureau of Air Regulation
    (BAR)
  • 7 Permit applications/HBCA reviewed by 3
    different FDEP District Offices with parallel
    review by BAR
  • 1 Permit application/HBCA reviewed by BAR
  • 3 of the HBCA demonstrations to be audited by EPA

4
Challenges
  • Florida permitting timeclock does not coincide
    with EPA review time for the 3 facilities being
    audited.
  • Most permitting staff have not had risk
    assessment training.
  • Though I/C/I boiler MACT training was offered by
    Region 4 in May 2006,
  • it was not detailed risk assessment training
    (none of the district permitting staff were able
    to go to it anyway) and
  • example permit conditions were not provided.

5
Tools Developed
  • Summary of Subpart DDDDD
  • Checklist for HBCA Demonstration

6
On-the-job Training
  • OAQPS has been very helpful in answering
    questions about the HBCA as they arise.
  • If you have questions, try contacting
  • Morris.Mark_at_epamail.epa.gov
  • Hirtz.James_at_epamail.epa.gov
  • Eddinger.Jim_at_epamail.epa.gov

7
On-the-job Training (contd)
  • Sample of Permitting Questions and
  • OAQPS Answers

8
Q A
  • Q1. If the maximum modeled manganese
    concentration is shown to be within a plant's
    property boundary, are they still required to
    show a plot plan of nearby residences, or show a
    comparison of the HQ HI to the limit of 1.0 at
    locations where people live or congregate?
  • Does the inhalation exposure for the most
    exposed individual need to be determined?

9
Q A
  • A1. No. Many of the submittals OAQPS has
    received do not specify locations of residence
    (or congregation) but instead locate receptors
    along the fenceline and use a Cartesian grid for
    all offsite locations, then take the highest
    value of all receptors. OAQPS thinks this more
    than adequately covers locations of residence and
    cong.

10
Q A
  • Q2. Though manganese testing was not performed at
    worst-case scenario, the applicant wants to
    demonstrate future compliance with an annual
    manganese limit by complying with their current
    PM limit and BTU design rate, and assuming the
    manganese/PM ratio is the same as during the
    non-worst-case stack testing. Is this
    acceptable?

11
Q A
  • A2. This question has come from several States.
  • OAQPS is currently discussing this with the
    Office of Enforcement and Compliance Assurance
    and Office of General Counsel.
  • OAQPS will get back to us on this.

12
Q A
  • Q3. Fuel oil analyses from 2005 were used. Is
    this acceptable?
  • No analysis of the on-plant recycled fuel oil
    is given at all because it is considered
    insignificant and was not quantified during stack
    testing. Is this acceptable?

13
Q A
  • A3. If the fuel testing is acceptable for MACT
    compliance, OAQPS thinks it is acceptable to use
    in the HBCA.
  • Is the recycled oil used in small quantities
    relative to virgin oil?
  • Is the AP-42 emission factor significantly
    different from the fuel test results?
  • Seems like if is truly used in small quantities
    that a permit condition limiting it could be
    possible.

14
Q A
  • Q4. Section 63.7521 requires that a fuel analysis
    plan be submitted no later than 60 days before
    the date that you intend to demonstrate
    compliance.
  • Applicants state that since the compliance date
    is September 13, 2007, they do not have to submit
    these plans yet.
  • Would OAQPS agree that this is true even for
    facilities that have submitted health-based
    eligibility demonstrations?

15
Q A
  • A4. No. Appendix A to subpart DDDDD
    section8.(a)(3) requires that the demonstration
    must include the fuel analysis.

16
Q A
  • Q5. If a facility uses the HBCA to get out of
    including manganese in the TSM limit, do they
    still have to determine compliance with the TSM
    limit?

17
Q A
  • A5. Yes. Annually if by stack test,
  • or every 5 years if by fuel analysis.

18
Examples of Permit Conditions
  • Methods of Operation
  • Permitted Capacity
  • Stack Information
  • Emissions Limits

19
Examples of Permit Conditions (contd)
  • A.9.a. Hydrogen Chloride. Except as provided in
    Conditions A.9.b. and c., hydrogen chloride
    emissions shall not exceed 0.09 lb per MMBtu of
    heat input.
  • 40 CFR 63.7500(a)(1) Table 1 to Subpart DDDDD
    of Part 63 - Emissions Limits and Work Practice
    Standards 9.b
  • A.9.b. Hydrogen Chloride - Health Based
    Compliance Alternative (HBCA). For this
    emissions unit, the permittee has self-certified
    that they are eligible to use the Health Based
    Compliance Alternative (HBCA) for hydrogen
    chloride emissions utilizing the procedures
    prescribed in Appendix A of 40 CFR 63 Subpart
    DDDDD and as authorized in 40 CFR 63.7507(a).
  • 40 CFR 63.7507(a)

20
Examples of Permit Conditions (contd)
  • A.9.c. Hydrogen Chloride - Health Based
    Compliance Alternative (HBCA). The chlorine
    emissions from this emissions unit shall not
    exceed 0.05 lb per MMBtu of boiler heat input1.
    This emissions limit is based on an annual
    average. The emissions unit is assumed to be in
    compliance with this chlorine emissions limit
    when the following conditions are met
  • 1 From January 2005 January 2007
    Fuel Analyses, potential HCl emission rate from
    fuels bark0.014 lb/MMBtu, bark/wastewater wood
    residuals0.025 lb/MMBtu, No. 6 Fuel Oil3.6x10-3
    lb/MMBtu. Applicant utilized a safety factor of
    2 to bark/wastewater wood residuals results
    (highest) due to potential variability in
    chlorine content of bark and wastewater wood
    residuals.

21
Examples of Permit Conditions (contd)
  • (1) Exhaust gases shall be released through a
    vertical stack with a release height of 257 feet
    (78.3 meters), 11.0 feet (3.35 meters) in
    diameter, 450F (505K), 235,000 acfm gas flow
    rate, and 41.2 fps (12.6 mps) velocity. The
    stack location is UTM Zone 17, E.456,274.5,
    N.3,394,248.9.

22
Examples of Permit Conditions (contd)
  • (2) Operate a multicyclone (without flyash
    reinjection) followed by an ESP.
  • (3) Fire carbonaceous fuel (including wastewater
    wood fiber residuals, No. 6 Fuel Oil, No. 2 Fuel
    Oil, On-Specification Fuel Oil as stated in
    Condition A.2. above

23
Examples of Permit Conditions (contd)
  • (4) For the purposes of the HCl HBCA, the
    worse-case fuel mix has been identified as the
    combination of carbonaceous fuel (bark and
    wastewater wood fiber residuals) and No. 6 Fuel
    Oil. This mix consists of a maximum of 25 tons
    per hour2,3 from bark and wastewater wood
    residuals and 348 MMBtu/hr3,4 from No. 6 Fuel
    Oil, and
  • 2 Based on 9,137 Btu/lb for bark and
    wastewater wood fiber residuals sludge from
    sludge press from January 2005 submitted fuel
    analysis from HBCA eligibility.
  • 3 Maximum firing rate of any
    combination of fuels, as identified in Condition
    A.2. above, 457.0 MMBtu/hr of carbonaceous fuel
    and 348 MMBtu/hr of No. 6 Fuel Oil.
  • 4 Based on 150,257 Btu/gallon for No. 6 Fuel
    Oil from January 2005 submitted fuel analysis
    from HBCA eligibility.

24
Examples of Permit Conditions (contd)
  • (5) Maximum boiler heat inputs as stated in
    Condition A.2. above.
  • Should the emission unit not meet any one of
    the stated above criteria, the owner or operator
    shall update the HBCA eligibility demonstration
    as stated in Condition A.9.d.
  • 40 CFR 63.7507(a) 11(a) of Appendix A of 40
    CFR 63 Subpart DDDDD

25
Examples of Permit Conditions (contd)
  • A.9.d. Updated HBCA Eligibility Demonstration and
    Resubmittal. The HBCA eligibility demonstration
    must be updated and resubmitted each time that
    any of the parameters that defined the boiler as
    eligible for the HBCA changes in a way that could
    result in increased HAP emissions or increased
    risk from exposure to emissions. These
    parameters include, but are not limited to, fuel
    type, fuel mix (annual average), type of control
    devices, HAP emission rate, stack height, process
    parameters (e.g., heat input capacity), relevant
    reference values, and locations where people
    live).
  • If the HBCA eligibility demonstration is being
    updated to account for an action described above
    that is under the control of the facility (e.g.
    change in heat input capacity of the boiler), the
    revised eligibility demonstration must be
    submitted to the Department prior to making the
    change. The Permittee shall apply for and obtain
    a Title V Permit Revision in order to incorporate
    the change into the Title V Operation Permit.

26
Examples of Permit Conditions (contd)
  • A.9.d.(contd) Should it be determined that the
    emissions unit is no longer eligible for the
    HBCA, then the Permittee shall comply with the
    applicable emission limits, operating limits, and
    compliance requirements in 40 CFR 63 Subpart
    DDDDD prior to making the process change and
    revising the permit.
  • If the HBCA eligibility demonstration is being
    updated to account for an action described above
    that is outside of the control of the facility
    (e.g. change in a reference value), and that
    change causes the boiler to no longer be able to
    meet the criteria for the HBCA, the Permittee
    shall comply with the applicable emission limits,
    operating limits, and compliance requirements in
    40 CFR 63 Subpart DDDDD within 3 years.
  • 11(a) and 11(b) of Appendix A of 40 CFR
    63 Subpart DDDDD

27
Examples of Permit Conditions (contd)
  • A.9.e. Updated HBCA Eligibility Demonstration
    Review. The revised eligibility demonstration
    may be reviewed by the Department or EPA to
    verify that the demonstration meets the
    requirements of Appendix A of 40 CFR 63, Subpart
    DDDDD and is technically sound (i.e. use of the
    look-up tables is appropriate or the
    site-specific assessment is technically valid).
    If the Permittee is notified by the Department or
    EPA of any deficiencies in the submission, the
    emissions unit will not remain eligible for the
    HBCA until the Department or EPA verifies that
    the deficiencies are corrected.
  • 11(c) of Appendix A of 40 CFR 63 Subpart
    DDDDD

28
Examples of Permit Conditions (contd)
  • A.9.f. HBCA - Recordkeeping. Records of the
    information used in developing the HCl HBCA
    Eligibility Demonstration for this boiler must be
    kept, including all of the information specified
    in Section 8 of Appendix A of 40 CFR 63 Subpart
    DDDDD.
  • 12 of Appendix A of 40 CFR 63 Subpart DDDDD

29
Questions?
  • Contact
  • Cindy Phillips, P.E.
  • FDEP Bureau of Air Regulation
  • (850)921-9534
  • Cindy.Phillips_at_dep.state.fl.us
Write a Comment
User Comments (0)
About PowerShow.com