Title: Electrical
1Section 16 Electrical
. . . Bruce Zink EO-1 Electrical Lead, Swales
Aerospace, Inc.
2Contents
- System Block Diagram
- Verification Matrix
- Failure Free Time
- Changes since last review
- Remaining Work to be Performed
- Critical RFAs
- Status of Open Actions
- Residual Risk
- Launch Readiness
3System Block Diagram
4Power System Block Diagram
5As Run Verification Matrix
6Projected Power On Time
7Changes Since Red Team Review
- WARP re-integration
- Following WARP repair and test
- Calorimeter integration and verification
- ACDS removal, rework, and re-integration
- Interpoint converter stiffener installation
- GPS Power Converter Unit removal, rework, and
re-integration - Interpoint converter stiffener installation
- AST removal, rework, and re-integration
- Interpoint converter stiffener installation
8Changes Since Red Team Review (continued)
- IRU re-integration
- Following removal to prevent Helium exposure
- 1773 Bus Characterization
- Verify bus performance following breaking
connections to ACDS, WARP, Hyperion, and AST - Minimum system margin gt9dB over temperature range
- Trickle Charge Diode Installation
- Replaced fuse with diode and tested successfully
- S-Band Transponder Removal
- Returned to manufacturer due to AGC oscillations
- Integrated command uplink bypass to continue
powered testing
9Remaining Work To Be Completed
- Harness Closeouts
- Remaining work related to re-installation of
S-Band transponder and bay closeouts for flight. - S-Band Transponder Repair
- S-Band Transponder Re-Integration
- Repeat of previous successful integration
following repair - Hyperion Re-Integration
- Repeat of previous successful integration
following removal to allow integration of S-Band
Transponder
10Remaining Work To Be Completed (continued)
- S/A Integration
- Repeat of previous successful integration for
Vibration Acoustic Test - 1773 Bus Characterization (following Hyperion
final integration) - Required due to Hyperion de-mate
- Repeat of previous successful integrations
- Performed 7 times to date
11Status of Open Actions
- 1773 Bus Fault During MOC Sim (WOA 876 PR20-1,
20-3) - Modification of PSE default power on
configuration mitigated problem - PSE SW Build 8.1 performs load shed of all
non-essential loads following special command
reset - Solar Array Deployment Test
- All testing to date successful
- Planned for launch site
- Primary side with flight fuse plug
12Residual RiskOne Time Events (Redbook Items)
- Chassis current Transient (WOA 770-20-3,
PR20-3) - One event of 300mA, also seen on stripchart
recorder - EMC testing was taking place with probes
connected to spacecraft power bus - No recurrence since event on 11/22/99
- 1390 Hours of powered testing
- Chassis current event (WOA 572-30-10)
- Prolonged chassis current event reaching a peak
of 925 mA - Ad Hoc testing immediately following event caused
brief recurrence of anomaly - Solar Array Simulator cable (EGSE) found to have
split insulation on multiple wires within
backshell - Following inspection a new Solar Array Simulator
cable was fabricated - No recurrence since 8/20/99 ( with exception of
770-20-3 which was a brief event ) - 2370 Hours of powered testing
16 - 12
13Residual Risk(continued)
- 1773 Bus Fault during MOC Sim (WOA 876-20-1 and
876-20-3, PR20-1, 20-3) - 1773 bus susceptible to babbling transmitter
- Low risk of fault (TRMM and XTE heritage)
- Change in PSE default services mitigated risk
associated with this problem (Version 8.1) - Special command reset sheds all non-essential
loads - Operational ability to re-set or power down all
non-essential RTs - Ability to remove babbling RT, or re-set and stop
babbling - Low likelihood of occurrence combined with
operational workarounds results in low risk
associated with this issue - S-Band Transponder Anomaly
- AGC oscillations must be diagnosed and repaired
- See Special Topic
14Launch Readiness
- Complete troubleshooting of S-Band Transponder
- Locate problem
- Fix problem
- Integrate and Test S-Band Transponder
- Repaired unit
- Complete system level testing (CPT, S/A
deployment) - Previous success suggests low risk
- Complete remaining activities
- See previous section on Remaining Work to be
Completed - Low risk S/C closeouts and repeats of previous
integrations - Ready for launch following previously mentioned
activities
15Special Topic Follow-Up Nadir Deck Heater Short
. . . Bruce Zink EO-1 Electrical Lead, Swales
Aerospace, Inc.
16Nadir Deck Short Circuit
- Summary of Event (WOA 676-20-8)
- Mis-wired heaters caused high current events in
first TVAC - Repair Implementation
- Heater circuits and switched services in question
abandoned - New heaters installed on nadir deck
- Re-wiring performed to re-establish lost services
- Test and Verification
- Circuits tested by jumpering thermostats
- Circuits verified in T/V II cold plateau
- Negligible residual risk
17Special Topic Umbilical Console Operational
Issues
. . . Bruce Zink EO-1 Electrical Lead, Swales
Aerospace, Inc.
18Description of Problem
- GPIB bus internal to Umbilical Console suffers
from periodic crashes - Conflict on bus (cause not fully understood)
results in loss of commanding and status
telemetry from solar array simulators and Direct
Power Converter supply - Existing configuration of supplies remains
following a crash - Commanding of output relays for the solar array
simulators and DPC is not affected by GPIB
crash - Communications with ASIST is not affected by a
crash - Does this situation create risk associated with
Launch??
19Umbilical Console Block Diagram
Ethernet ASIST Link
Switch Control
Windows NT Computer
- ASIST used to command UC and acquire telemetry
- GPIB Bus used to control settings on power
supplies - Sorenson Bus mimics GPIB bus for remaining
supplies - Output relays controlled via dedicated hardware
not on GPIB bus
HP Solar Array Simulator
GPIB Bus
To Spacecraft
Sorenson DPC/Master
Sorenson SAS 3
Sorenson Bus
Sorenson SAS 10
20Umbilical Command Timeline
- Power up
- Configure DPC to 30V
- Close DPC output relay
- Bring S/C Battery On-Line
- Adjust DPC to match battery voltage
- Send battery on pulse
- Open DPC output relay
- Adjust DPC voltage to 22VDC
- Configure Solar Array Simulators
- Adjust HP SAS and all Sorenson supplies to
standard settings
Denotes use of GPIB Bus
21Umbilical Command Timeline
- Standard Spacecraft Operations
- Cycle SAS output relays to control battery
charging - Launch (T-5 minutes)
- Open all SAS output relays to go to internal
power - Scrub/Power Down Spacecraft
- Adjust DPC to match battery voltage (iterative
process) - Close DPC output relay
- Issue battery off pulse
- Open DPC output relay
Denotes use of GPIB Bus
22Umbilical Recovery Procedure
- Wait for spacecraft night
- SAS supplies reconfigured during recovery, no
effect on spacecraft when SAS output relays are
open - Exit Umbilical SW program
- Performed using remote administration from
remotely located computer - Cycle AC power to Sorenson DPC supply
- Performed using remote controlled power switch
- Controlled via fiber link from remote PC
- Re-start Umbilical SW program
- Performed using remote administration from
remotely located computer - Continue testing
23Summary
- Problem has seen extensive effort by a large
group of people - Definitely related to Sorenson internal bus
- Unable to precisely locate and fix problem
- Further attempts to fix problem are
counter-productive - Configuration changes this close to launch carry
risk of other problems - Recovery procedure is in place, and exercised
regularly - Problem cannot threaten launch
- See command timeline, which shows no GPIB
activity required to handle launch (following
initial configuration) - Power up and SAS configuration completed gt8 hours
prior to launch - Recovery time is on the order of 10 minutes
- UC crash occurred during last Launch Sim, S/C
launched successfully and on time!!!
24Special Topic Solar Array Cable Damage PR
1045-40-1
. . . Bruce Zink EO-1 Electrical Lead, Swales
Aerospace, Inc.
25Solar Array Cable Damage
- Background
- During final panel closeout inspections on June 6
a hair line mark (centered around three o'clock)
was noticed on the 86 wire bundle that comes out
of the SADA - The hair line mark was further inspected and
determined to be a cut of the insulation for
seven wires. The geometry of the cut indicated
damage due to a sharp object. It must be noted
that this cut was very difficult to see due to
fine cut. The location of the cut is
approximately 0.75 inches off the face of the
SADA interface which is approximately at the
start of the bend radius for the cable bundle as
it is folded up against the Solar Array Yoke.
This obviously is a high stress area. - Under higher magnification (10 - 20x) it was
determined that at least three wires had exposed
copper. In addition oxidation has occurred
indicating the damage was done some time ago.
26Solar Array Cable Damage
- Background (continued)
- All seven wires were verified as follows
- Connector Pin Description - Function
- Cable Wrap J2 7 Inboard S/A panel structural
ground - Cable Wrap J2 37 Circuit 11 (outboard panel
fixed string) - Cable Wrap J2 19 Circuit 4- (Outboard panel,
shuntable) - Cable Wrap J2 38 Guard (ground wire shield for
CSS) - Cable Wrap J2 14 Guard
- Cable Wrap J2 42 Guard
- Cable Wrap J2 27 Coarse Sun Sensor 2
27Solar Array Cable Damage
Detail View A
28Solar Array Cable DamageClose-up
Detail View A
29Solar Array Cable Damage
- Probable Cause
- It is believed that this damage occurred while in
the 238 TV chamber in the preparation of the
Spacecraft for TV (October 99) or while clearing
out the GSE blankets in and around the SADA .
This can not be verified and it is more than
likely an accident which went unnoticed. The
SADA and cable wrap were thoroughly inspected via
bore scope shortly before TV and was found to be
nominal. - Prior to TV 1, a through inspection was
performed in this area without issue - No work has been done in this area since leaving
TV, until recently - Cutting instruments are generally used in chamber
operations (TC number cutting, GSE MLI
clearing,etc.) - One TV GSE cabling was found damaged in similar
manner following TV - Configuration in chamber was not conducive to
ideal working conditions for technicians due
to extremely tight configuration and poor
lighting - QA oversight was from distance during T/V buildup
and T/V teardown in chamber due to continuous
monitoring of Oxygen level at chamber door due to
concern of nitrogen Purge in closed chamber.
Safety of personnel was first priority! Also
there was insufficient room to have two people in
the same physical area. - Other post TV activity require use of razor
blades (Radiator tape cutting, excess adhesive
removal/trimming, etc.) however this has been
limited and is under constant monitoring by QA
30Solar Array Cable Damage
- Corrective Action
- Based on the type of damage critical location
it was determined by both Swales Aerospace GSFC
Quality (M. Kelly) that this damage could not be
repaired by splicing or any other means. The
wires associated with pin J2-7, J2-37, J2-19,
J2-27 would need to be replaced by swapping with
existing spares within assembly. - Implementation of swap was made using a patch
cable due to access restrictions. - Make use of current internal Bay 5 SADA cabling
interface connection - Fabricated Connector Bracket Assembly which
essentially swaps wires (J2-7, J2-37, J2-19
J2-27) with the spares
31Bay 4 View of SADA
Detail View B
32Bay 4 View of SADA
Detail View B
33Solar Array Cable Damage
- Corrective Action (continued)
- In addition to the fabrication of Connector
Bracket Assembly the following other actions
were taken - Millohm insulation resistance (cross pin)
testing of entire cable to verify all wires prior
to initiating of change rework of damaged
cables - Although J 2-7, J2-37, J2-19, J2-27 wires were
abandoned, exposed copper insulation wiring was
covered. Guard wires were also reworked. - Millohm HiPot entire cable following rework.
(Connector Bracket Assembly testing which also
includes HiPot testing performed prior to
delivery to Spacecraft) - Integrated Connector Bracket Assembly with Cable
Wrap Assembly - Verified all SADA signals with Connector Bracket
Assembly installed - Followed by full SADA functional
- Following completion of S/C bay closure a S/C
Aliveness Test was performed
34Solar Array Cable Damage
- Corrective Action (continued)
- Other Global actions taken
- Inspected all external cabling prior to blanket
installation. - Fabricated Red Tag Item to cover critical area of
Solar Array cable. It will be removed prior to
Solar Array installation. - Rework of cable harness will have no effect to
overall deployment of Solar Array - Deployment Hinge has gt4x Torque margin for worst
case environmental effects
35Connector Bracket Assembly Fitcheck on
SpacecraftMonday 6/12/00 - 1400
36Summary
- All repairs and preventative measures implemented
successfully - All changes documented in appropriate drawings
- Extensive spacecraft testing has taken place
since repair, including a full TVAC test with no
anomalies related to the cable wrap assembly - Negligible residual risk
- Ready to fly