Title: PACS IHDR
1PACS IHDR
- Model Philosophy, Budgets, Interfaces and IID-B
Reinhard Katterloher
2Configuration and Development of PACS Instrument
Models
- Flight Instrument consists of 1 cryogenic FPU, 4
electronics boxes (units) at ambient temperature,
1 set of WIH - CQMAVM Instrument consists of 1 cryogenic FPU,
4 electronics boxes (units) at ambient
temperature, 1 set of WIH - Flight Spare philosophy demands 1 cryogenic FPU
(which is the refurbished CQM unit), and
electronics spare kits - Development program, performance verification and
environmental qualification of Units is taken
care by the individual manufacturers - For each Unit a dedicated Development and Test
Plan (covering all AIV activities on Unit level)
is issued and enforced - AIV of the different models on instrument level
starts after delivery of the Units to MPE
3Model Philosophy (deliverables to ESA are marked
in blue)
4CQM-FPU and AVM-WE characteristics compared to PFM
- FPU CQM is a nearly FM representative FPU Unit
- Complete optics, all mechanisms, all sensors
- Blue spectrometer array 12 modules instead of
25 - Red spectrometer array 11 modules instead of 25
- Blue photometer array 8 sub-arrays (2 near
perfo.) of 8 - Red photometer array 2 sub-arrays (1 near
perfo.) of 2 - AVM electronics is built with commercial grade
components, no redundancy, DECMEC, BOLC and SPU
are not form fit with FM - CQM wavelength calibration program cannot be
executed to the same accuracy as planned for FM
due to schedule limitations - EMC tests during CQM ILT and on system level
(EQM) planned
5Functional Properties of Units (deliverables to
MPE)
Unit Model status
FPU STM (mass, size, thermal, ext. alignm.) CQM (full repres. of FM, 50 Ge-arrays) PFM (full flight representative) delivered
DPU AVM (functional repres. of FM, FFF) PFM (nom and red part) QM (functional repres. of FM, for ILT FS) delivered
SPU AVM (functional repres. of FM) EM (functional repres. of FM, for ILT FS) PFM (2 identical boxes nom/red) delivered
DECMEC AVM Simulator (supports electrical S/W performance verification)EM (1MEC2DEC)QM (1MEC1DEC, upgrd. requ. for ILT FS)PFM (2MEC2DEC in 1 unit) delivered
BOLC BOLC Simulator (supports electr.S/W ver.)QM1 (supports FPU ILT performance verif.) QM2 (full QM, for initial FM, for ILT FS)PFM (full flight representative) delivered
6Combination of Units during ILT Phases
7FPU Schematic and Interfaces
8Mechanical interfaces of FPU OB and WE SVM
- The PACS FPU is mounted on the OB with 3 CFRP
feet - The mechanical Interface is fully described in
the drawing - PACS-KT-ICD-0000W1 issue 27 draft dated
04-07-2003 - The FPU ICD drawing is annex to IID-B
- The bolting scheme of BOLC QM to SVM is not
identical with FM - The mechanical interfaces of other WE FM boxes to
SVM are given in the relevant PACS Interface
Control Drawings - WE FM ICDs are annex to IID-B
- Change requests are issued for WE AVM boxes
9Thermal Budget and Interface FPU - S/C cryostat
- FPU requires two temperature levels- level 0 at
nominal 1.7K (max. 1.75 K accepted)- level 1
around 4K (max. 5.0 K accepted) - Other temperatures inside the FPU are produced
autonomously (2.2K blue array/ 0.3K bolometers) - Thermal coupling to cooling level 0 via 4 heat
straps - Thermal coupling to cooling level 1 via 3 heat
straps - FPU is thermally decoupled from OB by CFRP feet
- Thermal loads and final heat fluxes are
calculated using the PACS TMM combined with the
cryostat TMM
10Steady State Heat Dissipation (table from PACS
TMM)
11Harness Interface FPUWES/C and Electrical Budget
- Harness is specified in PACS-MA-SP-001-V3.2,
annex to IID-B It consists of- total inside
CVV 1060 wires 255 shields - total outside
CVV 1060 wires 255 shields 15
overshields- Warm Interconnect Harness (specs.
given in PACS-CL-RS-010) - Power consumption of WE see separate table
- Science data rate in PACS prime mode is 130 kbps
max (120 kbps average per day)
12Power Consumption on SVM (present allocation is
120 W, CR-0033_V3 pending, demand for LCL class
III)
Table of maximum average power and short and long
peak power demand is provided in IID-B CR-0033_V3
13Mass and Size of Instrument Units
Project code Instrument unit Dimensions (mm)length x width x height Nominal mass (kg)
FPFPU Cold focal plane unit See configuration drawings annex IID-B 73.6
FPDECMEC Detector control and mechanism control unit EM 560x318x304 FM 560x318x305 TBC 23 (TBC)
FPBOLC Bolometer and cooler control unit QM 328.5x300.2x314.3 FM 382.5x289x333.5 incl. connect. backshell 499.5x289x376.9 TBC 15.35
FPDPU Digital processing unit 274x258x197 including fixation feet 240x258x197 exclud.f.f. 6.62
FPSPU nom.redu. stacked Signal processing unit AVM 280x240.5x350 FM 270x221x186 TBC 7.0
FPWIH Warm interconnect harness Length AVM 2000 Length FM 1300/1500 1.5 TBC
Total mass FM (allocation 130 kg) 127
14Current IID-B Status
- Status of open CRs submitted or still to be
written will be given under topic PA/QA - Status of open RFWs submitted or still to be
written will be given under topic PA/QA - Lot of figures and few tables need to be replaced
according to progress in instrument development
and have to be included in the very next version
of IID-B (many of the figures are ready for
submission) - Missing figures, drawings and all text additions
can be expected from PACS within the next two
weeks
15Urgent Pending Activities w.r.t. Documentation
- Update of IID-B has highest priority
- Next issues of AIV Plan and Test Plan are due
(PCD draft 7 up to date) - Definition of the optimized ILT test sequence and
consolidation of test steps need further
technical discussions - Definition of detailed test procedure for the
CQMAVM ILT in progress already, issueing of the
document Test Plan will be started immediately
after AIV Plan is completed - Selection of building blocks out of the ILT
program for the EQM test program has to be
started soon (test steps adapted to EQM
constraints) - Approval of RFW0003 expected soon, qualification
program of black paint needs to be finished
because manufacture of FM structure has started