Transmission Loading Relief - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

Transmission Loading Relief

Description:

Energy Levels Across a Flowgate are Approaching or Expected to Approach ... Reconfigure transmission system and/or redispatch generation to allow ... – PowerPoint PPT presentation

Number of Views:37
Avg rating:3.0/5.0
Slides: 22
Provided by: rgo3
Category:

less

Transcript and Presenter's Notes

Title: Transmission Loading Relief


1
Transmission Loading Relief Energy Emergency
Alerts
  • Roger Harszy
  • Director, Reliability Coordination

2
Understanding the Levels of Transmission Loading
Relief TLR
3
Transmission Loading Relief
TLR Levels
TLR Level 1 Energy Levels Across a Flowgate are
Approaching or Expected to Approach acceptable
operating limits
  • TLR Level 2
  • Hold Interchange Transactions at Current Levels
    to Prevent Operating Security Limit Violations
  • Additional Information
  • Only allowed to last for 20 minutes
  • Seldom used if ever

4
Transmission Loading Relief
TLR Levels
  • TLR Levels 3A 3B
  • Curtail Non-firm Point-to-Point Transactions
    (pro-rata)
  • Additional Information
  • Curtailments are implemented
  • TLR Level 3A - At the top of the upcoming hour.
  • TLR Level 3B Immediately or as soon as
    possible
  • Higher priority transactions are enabled to start
    by the reallocation process.
  • Available NERC MRD Transactions are initiated.

5 or greater impact on the flowgate
5
Transmission Loading Relief
TLR Levels
  • TLR Level 4
  • Reconfigure transmission system and/or redispatch
    generation to allow Transactions using Firm
    Point-to-Point Transmission Service to continue.
  • Additional Information
  • All Transactions using Non-firm Point-to-Point
    Transmission Service are curtailed under a TLR
    Level 4
  • Available MISO Flowgate Redispatch (FRD) cases
    are initiated.

5 or greater impact on the flowgate
6
Transmission Loading Relief
TLR Levels
  • TLR Levels 5A 5B
  • Curtail Firm Point-to-Point Transactions
    (pro-rata) to allow new Firm Point-to-Point
    Transactions to begin (pro-rata)
  • Additional Information
  • Curtailments are implemented
  • TLR Level 5A - At the top of the upcoming hour.
  • TLR Level 5B Immediately or as soon as
    possible
  • Pro forma tariff requires curtailment on pro rata
    basis with Network Integration Transmission
    Service and Native Load.

5 or greater impact on the flowgate
7
Transmission Loading Relief
TLR Levels
TLR Level 6 Emergency Action. Voltage collapse,
cascading, or other emergency is imminent MISO
Actions Could include demand-side management,
emergency redispatch, voltage reductions,
interruptible and firm load shedding.
8
Transmission Loading Relief
TLR Levels
TLR Level 0 TLR Concluded. Restore all
transactions.
9
A Comparison of TLR Events ATCo
Companies vs. MISO vs. Eastern Interconnection
10
(No Transcript)
11
(No Transcript)
12
(No Transcript)
13
(No Transcript)
14
(No Transcript)
15
EEA Alert Levels
16
EEA Alert Levels
  • EEA Alert Level 1 All available resources in
    use
  • Circumstances
  • All available resources are committed or
    expected to be committed - to meet firm load,
    firm transactions, and reserve commitments
  • Non-firm wholesale energy sales (other than those
    that are recallable to meet reserve requirements)
    have been curtailed

17
EEA Alert Levels
  • EEA Alert Level 2 Load Management Procedures
    in Effect
  • Circumstances
  • Control Area no longer able to provide customers
    expected energy requirements, and is designated
    an ENERGY DEFICIENT ENTITY
  • ENERGY DEFICIENT ENTITY foresees or has
    implemented procedures up to, but excluding,
    interruption of firm load commitments. When time
    permits, these procedures may include, but are
    not limited to
  • Public appeals to reduce demand
  • Voltage reduction
  • Interruption of non-firm end use loads in
    accordance with applicable contracts
  • Demand-side management
  • Utility load conservation measures

18
EEA Alert Levels
EEA Alert Level 2 Load Management Procedures
in Effect During Alert 2, RELIABILITY
COORDINATORS, CONTROL AREAS, and ENERGY DEFICIENT
ENTITIES have the following responsibilities
  • Notify other Control Areas and Market
    Participants
  • ENERGY DEFICIENT ENTITY updates its RELIABILITY
    COORDINATOR of the situation every hour until the
    Alert 2 is terminated.
  • CONTROL AREAS and market participants with
    available resources shall immediately contact the
    ENERGY DEFICIENT ENTITY.

For emergency, not economic, reasons
19
EEA Alert Levels
EEA Alert Level 2 Load Management Procedures
in Effect During Alert 2, RELIABILITY
COORDINATORS, CONTROL AREAS, and ENERGY DEFICIENT
ENTITIES have the following responsibilities
  • Where appropriate, the RELIABILITY COORDINATORS
    shall inform the Transmission Providers of the
    pending ENERGY EMERGENCY and request that they
    increase their Available Transfer Capability
    (ATC)
  • RELIABILITY COORDINATOR shall communicate and
    coordinate implementation of emergency operating
    responses
  • Before declaring an Alert 3, the ENERGY DEFICIENT
    ENTITY must make use of all available resources
  • Under an EEA Level 2, priority 6 transactions may
    be raised to priority 7

20
EEA Alert Levels
  • Alert 3 Firm load interruption imminent or in
    progress
  • Circumstances
  • ENERGY DEFICIENT ENTITY foresees or has
    implemented interruption of firm load
  • Available energy is only accessible with actions
    taken to increase transmission transfer capacity.
    Actions include
  • Continue actions from Alert 2.
  • Use of Transmission short-time limits where
    possible without endangering the system
  • Report listed in appendix 9B, Section C must be
    submitted to the RC within two business days of
    downgrading or termination of the Alert

21
Transmission Loading Relief Energy Emergency
Alerts
  • Roger Harszy
  • Director, Reliability Coordination
Write a Comment
User Comments (0)
About PowerShow.com