Title: KwaZulu-Natal Regional Bulk Water Supply
1KwaZulu-Natal Regional Bulk Water Supply
Presented by Umgeni Water to the Portfolio
Committee on Provincial and Local Government
Date 7 June 2005
Version 4 6 June 2005
2Introduction Background
- Global targets challenges
- Millennium Development Goal (MDG) is to halve
proportion of people without access to a
sustainable water and sanitation supply by 2015 - Estimated 1.5 billion people without adequate
water - Estimated 2.5 billion people without adequate
sanitation - Africa challenges
- Estimated one third of 800 million population
without adequate water - Estimated two thirds of population without
adequate sanitation - SADC is unlikely to meet the MDGs unless
something drastic takes place
3Introduction Background (contd.)
- RSA targets challenges
- Provision of clean running water to all
households by 2008 - Provision of decent safe sanitation by 2010
- 4.4 million people do not have access to formal
water infrastructure - 10.4 million people have access to below basic
water RDP standards - Natural disasters-drought conditions in Western
Cape and Free State - Range of water institutions-some limited in
capacity to deliver on targets
4Introduction Background (contd.)
- KZN challenges
- KZN has a population of 9.4 million (2001 census)
- Of which more than 700 000 households do not have
access to basic water supply standards (RDP
standard) - Water Service Authorities can partner with the
existing Bulk Water Suppliers to provide more
sustainable long term solutions ie a REGIONAL
SOLUTION, which also supports the countrys macro
policies -
5Context
- Water Service Authorities (WSAs) have a
responsibility to provide adequate water services
within their area of jurisdiction - WSAs generally undertake insular planning and
development - Backlogs can be addressed through stand-alone
schemes. These stand-alone schemes have proven
to be unsustainable without continual and direct
technical, administrative and financial support - Slow pace of delivery largely due to
co-ordination, capacity and financial constraints - Water Utilities can provide support as Regional
Water Service Providers (WSPs) partnering with
local, provincial and national government, and
other stakeholders
6Regional Bulk Supply Schemes
- Propose that regional bulk supply schemes could
be the most appropriate solution to improve water
service delivery, although not the only solution - Address backlogs
- Improve level of service
- Advantage of regional schemes over stand-alone
schemes - Sustainability of supply
- Rationalisation
- Economies of scale
- Cross subsidisation
- Water quality
- Improved level of service
- Linking water resources to water supply
7Regional Bulk Supply Schemes
The following assumptions were used in developing
the delivery plan
- REGIONAL SYSTEMS Regional bulk water service
provider concept - APPROACH Bulk water provision only
(abstraction, treatment distribution) - DEMANDS Demand centres based predominately on
population distribution (formal growth/economic
development growth points) - INFRASTRUCTURE Utilise existing and proposed
water service infrastructure wherever possible - RATIONALISATION Consolidate WTW and
distribution systems - RAW WATER SOURCE To be located at highest
elevation (gravity vs pumping improved WQ
reduced sedimentation) - WTW LOCATION Close to abstraction point
(minimise non-revenue water losses,maximise
opportunity to supply both rural urban demand
centres) - DISTRIBUTION interlink supply system (minimise
supply risks ), route to maintain elevations,
through demand centres, along road
infrastructure
8Population Densities
Census 2001 data
9Water Service Backlogs in KZN
- Estimated 40 backlog of all households
- Increase of 425 000 households since 1996 Census
(backlog was 33) - 70 of backlogs located in 7 Water Service
Authorities - 50 of backlogs located in 4 District
Municipalities - 50 of backlogs located in 11 Local
Municipalities
10 70 of backlogs are within 7 WSAs
11Backlog Target Areas
- 70 of backlogs within 7 Water Service
Authorities
Priority Water Service Authority Priority Area, no households below RDP std Target Area, No. potential household below RDP std
A B C D E F G eThekwini Municipality Ugu District Municipality Umzumbe, Hibiscus Coast Msunduzi Local Municipality Umkhanyakude District Municipality Hlabisa,Jozini, Umhlabuyalingana Zululand District Municipality Nongoma, Ulundi Umzinyathi District Municipality Msinga Uthungulu District Municipality Umlalazi 137 803 56 425 25 785 69 797 53 581 30 290 29 111 137 803 101 436 25 785 76 828 92 422 62 219 94 951
TOTAL 405 792 591 444
12Pongola
White Mfolozi
Black Mfolozi
Buffels
Upper Mhlathuze
Upper Thukela
Lower Thukela
Lower Mhlathuze
Mooi
Mvoti
North Coast
Mgeni
15 Regional Bulk Supply Schemes
Mzimkulu
Mzintlava
South Coast
13Regional Bulk Supply Schemes
- Benefits of Schemes on Job Creation Poverty
alleviation - The schemes to be a chapter in the Provincial
Growth Development Strategy - Link into the Provincial Government Integrated
Financial Strategy (IFS) which aims to eradicate
poverty and inequality, create jobs and
facilitate economic growth - Link into the Poverty Alleviation Strategy of the
second economy - Drive service infrastructure delivery in a
sustainable way
14Indicative Costs of Regional Bulk Supply Schemes
Regional bulk scheme Capital Cost Capital Cost Capital Cost Annual Operating Maintenance Cost Annual Operating Maintenance Cost Annual Operating Maintenance Cost
BULK RETICULATION TOTAL BULK RETICULATION TOTAL
(R million) (R million) (R million) (R million/a) (R million/a) (R million/a)
Phongola 200 80 280 0.5 7.0 7.5
White Mfolozi 520 140 660 2.5 13.0 15.5
Black Mfolozi 520 215 735 5.0 20.0 25.0
Buffels 840 205 1 045 3.5 19.0 22.5
Upper Mhlathuze 250 110 360 2.0 10.0 12.0
Lower Mhlatuze 200 60 260 0.5 5.5 6.0
Upper Thukela 710 210 920 4.5 19.5 24.0
Lower Thukela 410 160 570 3.0 15.0 18.0
Mvoti 480 145 625 2.0 13.5 15.5
North Coast 530 190 720 1.5 18.0 19.5
Mooi 150 45 195 0.5 4.5 5.0
Mgeni 700 845 1 545 2.0 79.0 81.0
South Coast 500 325 825 2.0 30.0 32.0
Mzimkulu 1 350 315 1 665 4.5 29.0 33.5
Mzintlava 430 130 560 1.0 12.0 13.0
TOTAL 7 790 3 175 10 965 35.0 295.0 330.0
NOTE Reticulation capital cost and the annual
operational and maintenance costs are based on
yard connections for those households below RDP
standard. Since most of these schemes
currently do not exist, no refurbishment costs
have been included.
15Regional Bulk Supply Schemes
Estimated Rate of backlog eradication
NOTE Reticulation capital cost and the annual
operational and maintenance costs are based on
yard connections for those households below RDP
standard. Since most of these schemes
currently do not exist, no refurbishment costs
have been included.
16Indicative Costs of Water Resource Infrastructure
Water Resource Existing / Total Regional bulk schemes supplied
Infrastructure Proposed Capital Cost
(R million)
Pongolapoort Dam Existing 0 Pongola
Klipfontein Dam Existing 0 White Mfolozi
Black Mfolozi Dam Proposed 350 Black Mfolozi
Ntsingwayo Dam Existing 0 Buffels, Lower Thukela
Mfule Dam Proposed 100 Upper Mhlathuze
Goedertrouw Dam Existing 0 Lower Mhlathuze
Spioenkop Dam Existing 0 Upper Thukela, Lower Thukela
Middledrift Weir Existing 0 Lower Thukela, Lower Mhlathuze
Mvoti-Poort/Isithundu Dam Proposed 230 Mvoti, North Coast
Hazelmere Dam (raised) Proposed 30 North Coast
Spring Grove Dam Proposed 260 Mooi, Mgeni, South Coast
Ngwadini/Lower Mzimkulu Dam Proposed 230 South Coast
Mzimkulu Dam Proposed 350 Mzimkulu, South Coast
Mzintlava Dam Proposed 100 Mzintlava
TOTAL 1 650
NOTE Mkomazi-Mgeni Transfer Scheme (approx. R4
billion) not included in this table, but is a
long-term requirement for the Mgeni scheme.
17Regional Bulk Supply Schemes
- Job Creation Opportunities
- Direct Temporary 73 700 (6.7 jobs per R
million) - Direct Permanent (includes Water Waste Water
Schemes, Reticulation Associated Services)
Estimated Total 5 000 - Assuming a direct to indirect ratio of 13 this
relates to - Indirect Temporary jobs - 221 100
- Indirect Permanent jobs - 15 000
18Regional Bulk Supply Schemes
- Job Creation Opportunities (contd.)
- Multiplier effect arising from water service
delivery - Agriculture (irrigation, aquaculture)
- Residential Development (including housing,
electricity, roads, communication) - Temporary Jobs Direct
- Permanent Jobs
- SMMEs through water electrical servicing
(estimate 1 new small business per every 10
electrical connections) - Industrial Activity Stimulated
19BEE Opportunities
- Expanded Public Works Programme (EPWP) to be
applied to the implementation of both bulk and
reticulation schemes - Infrastructure sector of EPWP emphasizes work
creation through labour-intensive construction
methods - These schemes will be a catalyst to the Water
Sector Charter - Estimated BEE benefits derived from the
construction of the regional bulk schemes
Component Total Component Value (R million) BEE BEE Component (R million)
Professional 2 360 80 1 900
Contractors 4 956 60 3 000
Local Labour 2 124 80 1 700
TOTAL 9 440 6 600
20Funding
- Innovative approach to project financing required
- Water tariffs to remain affordable to end-users
- Integrate plans and funding into Municipal IDPs
- Possible sources of funding available include
- Partially or fully obtained from WSPs
- Financial institutions
21Funding Solutions
- The R11billion to be broken down into the 15
projects and for each project establish
-
- Raw costs for Capex, Opex and Maintenance
- Direct Revenue Streams
- Level of financial support required from the
various stakeholders (Treasury,
Municipalities, Water Utilities, DWAF)
- The above framework would address critical
issues such as - - implementation vehicle
- - specific risk mitigation
- - affordability of water tariff to end
users. -
22Funding Challenge
Reduce the project debt illustrating the
effects of R150m per year from 2009
All KZN Bulk Retic All KZN Bulk Retic with
Umgeni Water R150m subsidy
23Funding
- Funding Options What will it look like?
- PPP Concession Structure
- Leasing Structure - Share Based or Asset Based
- Funding Sources Who will finance it?
- Banks most flexible but not the cheapest
- Securitisation Conduits
- Debt Capital Market CPP, Bonds (Corporate
Project) - Non-banking Intermediaries INCA TCTA
- Development Finance e.g DBSA, DFID (UK)
- Infrastructure Funds AIIF, KZN Growth Fund
MIG - Financial Sector Charter
- Factors to be considered
- Credit enhancement Impact on sources and cost
of funding
24Regional Bulk Supply Schemes
Stakeholder consultations to date
- DWAF Minister
- DWAF DG
- Provincial and local government DG 2 deputy
DGs - KZN Premier subsequently KZN full Provincial
Cabinet - Presidency (Mr Aboobaker and Mr M Morobe)
- Other Water Utilities Uthukela and Mhlathuze
- Municipalities Ugu, Illembe, Sisonke, Ethekwini,
Msunduzi - Financial institutions RMB, Standard Bank,
Investec, ABSA and DBSA - National Treasury DG Deputy DG
- Banking Association (Mr Coovadia)
- Local Government Housing and Traditional Affairs
KZN MEC - KZN Local Government Association by 10 June
- Institutional Investors e.g. Public Investment
Corporation (To schedule)
25Regional Bulk Supply Schemes
Progress to date
- Technical task team established
- Representatives from DWAF(KZN), Mhlathuze Water,
uThukela Water eThekwini and Umgeni Water - Producing a high level business plan
- Presentation to Municipal Managers, CEOs and
EXCOs of water utilities by 30 June 2005
26Regional Bulk Supply Schemes
Way Forward
- Need to drive initiative at
- - National Level targets to met per province
- - Provincial level Alignment to be achieved
across the province - National Treasury to provide a Technical Advisor
to the KZN Regional Bulk Supply task team - Project action plan and financial packaging to be
completed by July 2005
27Thanks for listeningLets get to it!