Title: Managing Project Success
1Managing Project Success
- Vladimir Liberzon
- Spider Management Technologies
- spider_at_mail.cnt.ru
2Part 1
3Project Success Criteria
- Setting project targets is a key task that
defines the process of project decision making
and project performance analysis. - The usual approach of triple constraints is very
complicated, yet it does not include all the
necessary considerations for determining if a
project is successful.
4Project Success Criteria
- Is Sydney Opera construction an example of
successful project? - No, because actual expenses exceeded the planned
budget by several times. - Yes, because it became one of the most famous
Sydney attractions, bringing many tourists and a
lot of money.
5Project Success Criteria
- The Motorola Iridium Project was finished on time
and within budget. Can it be considered a
successful project? - No!
- Iridium, backed by Motorola Inc. (MOT), sought
bankruptcy-court protection in 1999 after its 5
billion low-Earth orbit satellite (LEOS) fleet
failed to attract customers or provide the
quality service its backers had hoped for.
6Project Success Criteria
- If project success criteria are set as finishing
project on time and under budget then proper
decision making will be complicated. - It does not allow us to interpret the
significance if the project exceeds the planned
budget but is finished earlier than expected or
if it is finished late but saves some money. - It fails to evaluate the consequences if the
project was on time and within planned budget but
expected revenues were not achieved.
7Project Success Criteria
- We suggest to set one single project success
criterion that integrates project schedule, cost
and business goals. - Establishing this single criterion is complex
since it must include project scheduling, project
budgeting, estimating of the future business
benefits from the project product delivery, and
risk analysis and simulation.
8Project Success Criteria
- If a project is business oriented then this
project must have business targets and criteria
of its success or failure. - The natural choice setting target Internal Rate
of Return (IRR). - Con
- The Product Life Cycle may be too long for
reliable IRR estimation, - Uncertainties may be too great for proper IRR
management.
9Project Success Criteria
- One of the potential alternative options to set
a target profit that should be achieved at some
point in time based on the forecast of the
revenues to be realized after the project results
are delivered. - If the project profit meets or exceeds the target
profit then performance is successful. - Such success criterion will permit weighting and
balancing of time and money to make reasonable
managerial decisions.
10Project Success Criteria
- On the next slide we will see the project
schedule that is calculated without allowing for
project financing and supply restrictions. - There are periods when the project has no money
to proceed.
11Project Success Criteria
- But, if project manager can find enough money and
materials then the project total profit on the
imposed date will be close to 219,000.
12Project Success Criteria
- If we calculate the project schedule that
accounts for financing, supply, and resource
constraints then the total profit will be more
than 25,000 lower.
13Project Success Criteria
- Maybe it is reasonable to borrow money or to find
some other solution? - To be able to weight options and to choose the
best it is necessary to look beyond the project
results delivery date. It is necessary to
simulate not only expenses but also revenues and
resource constraints. This approach is especially
important for portfolio management.
14Project Success Criteria
- For setting project success criterion it is
necessary to incorporate the following data - Target finish that may be achieved with
reasonable probability, - Target budget that may be achieved with
reasonable probability, - Forecast of the probable future benefits (for an
example future profit or revenue curve). - The target finish and target budget shall be
calculated, taking into account all project
constraints (including resource, financing and
supply constraints) and using risk simulation.
15Project Success Target
- The next step is to define a specific point in
time for measuring project success. - Lets suppose that probable project NPV at this
moment is a defined number of dollars. This date
and amount can then be used as the project target
defining the single project success criterion for
the project management team. - It will, therefore, influence the project
managers decision making processes.
16Project Success Target
- Now management decisions will be made by
estimating their full business consequences.
Project managers may decide to spend additional
money to accelerate project performance if the
NPV at the targeted date will rise as a result of
this action. - At any time project performance may be measured
by the forecasted NPV if it exceeds the target
then total project performance is successful. The
current value of the forecasted NPV defines
project status.
17Project Success Target
- NPV forecast depends not only on project
performance results but also on the market
conditions and other project environmental
parameters. So project managers will analyze not
only project performance but also revenue/profit
forecasts. Their objective will be trying to
improve everything.
18Project Success Targets
- But this target value is not a single value.
- We recommend setting the following success
targets - optimistic project target that is set for the
project team, - project management team target that includes
contingency reserve, - management target that includes contingency and
management reserves, - failure target that defines conditions under
which project execution will be terminated.
19Project Success Targets
- Project Team Target
- Project Management Team Target
- Management Target
- Failure
Contingency Reserve
Management Reserve
Still Profitable
Project Failure
Target Date
20Part 2
- Setting Project Targets
- (deterministic approach)
21Necessary Steps
- 1) Develop corporate databases
- 2) Develop typical fragnet library,
- 3) Create project model,
- 4) Define constraints,
- 5) Create project schedule,
- 6) Forecast future benefits,
- 7) Define project targets.
22Step 1. Develop corporate databases
- Corporate project management has to be based on
corporate standards. These standards must include
not only processes and document templates but
also estimates of the typical activity and
assignment parameters. - Activities, resources and assignments belong to
the same type if they share the same
characteristics like unit costs, material
consumption per work volume (quantity) unit,
resource productivity, etc.
23Step 1. Develop corporate databases
- Corporate databases (Reference-books) should
include at least - Activity cost and material requirements per
activity type volume unit, - Resource assignment cost and material
requirements per assignment type volume unit, - Resource assignment productivity,
- Assignment work load.
24Step 2. Develop typical fragnet library
- Project fragnets usually describe typical
processes and technologies that are used more
than once. - Creating project computer models using the
corporate library of typical fragnets will help
to avoid inconsistencies and assures that the
project model follows corporate standards. - A library of typical fragnets is a very important
tool for the development of corporate culture and
management standards.
25Step 3. Create project model
- Project model will be developed using typical
fragnet library with project parameter
estimations based on the corporate
reference-books. - This approach helps to create reliable project
models that correspond with the corporate
standards for technologies to be used and
parameter (activity duration, costs, resource
productivities, etc.) values.
26Step 4. Define constraints
- Project constraints include
- time constraints,
- resource constraints,
- financing constraints (financing schedule),
- supply constraints (supply schedule),
- calendar constraints.
27Step 5. Create project schedule
- The problem of project schedule development
without allowing for resource constraints has a
correct mathematical solution (Critical Path
Method), which would be the same for all PM
packages, provided that the initial data are
identical. All other problems are solved using
different approaches and yielding different
results.
28Step 5. Create project schedule
- Traditional notion of Critical Path works only in
case of unlimited resources availability. - Let us consider a simple project consisting of
five activities, presented at the next slide.
29Step 5. Create project schedule
- Activities 2 and 5 are performed by the same
resource.
30Step 5. Create project schedule
- Please pay attention to activities that became
critical. Now delaying each of the activities 1,
2 and 5 will delay the project finish date. We
call these activities Resource Critical and their
sequence comprises Resource Critical Path.
31Step 5. Create project schedule
- In many projects it is necessary to simulate
financing and production, and calculate project
schedules taking into account all limitations
(including availability of renewable resources,
material supply and financing schedules). True
critical path should account for all schedule
constraints including resource and financial
limitations.
32Step 5. Create project schedule
- We call it Resource Critical Path (RCP) to
distinguish it from the traditional
interpretation of the critical path definition. - The calculation of RCP is similar to the
calculation of the traditional critical path with
the exception that both early and late dates (and
corresponding activity floats) are calculated
during forward and backward resource (and
material, and cost) leveling.
33Step 5. Create project schedule
- This technique permits us to identify resource
constrained floats. - Activity resource constrained float shows the
period for which activity execution may be
postponed within the current schedule with the
set of resources available in this project. - It appears that by adding financial and supply
constraints to the Critical Chain definition as
well as the method of the Critical Chain
calculation, we will obtain something very
similar to RCP.
34Step 6. Forecast future benefits
- Usually a project is considered to be finished
when the project result is delivered and starts
to bring benefits. - Without forecast of these benefits it is
impossible to evaluate the consequences of
management decisions made during project
execution. - That is why the forecast of the future benefits
must be included in the project model.
35Step 7. Define project target
- Future benefits depend on time.
- By defining the target date we restrict the
horizon of benefit forecasting and will be able
to calculate the cash flow value to that moment. - This value can be set as the project success
criterion if the cash flow forecast meets or
exceeds this value then project performance may
be considered to be successful.
36Step 7. Define project target
- Separate management target cash flow values may
be defined for the same project. This target
includes management reserve set for unknown
unknowns. In deterministic approach to project
planning this management reserve can be estimated
based on past experience and expert judgements. - The probabilistic approach allows us to calculate
necessary contingency and management reserves.
37Part 3
- Setting Project Targets
- (probabilistic approach)
38Necessary Steps
- 8) Analyze risks,
- 9) Define target success probability for project
management team, - 10) Define target success probability for the
organization (management), - 11) Calculate target values for PM team and top
management, - 12) Define failure value.
39Risk Simulation
- Risk simulation may be based on
- Monte Carlo simulation
- Three scenarios approach
40Risk Simulation three scenarios approach
- A project planner obtains three estimates
(optimistic, most probable and pessimistic) for
all initial project data (duration, volumes,
productivity, calendars, costs, etc.). - Risk events are selected and ranked using the
usual approach to risk qualitative analysis.
Usually we recommend including negative risk
events with probability - exceeding 90 in the optimistic scenario,
- exceeding 50 in the most probable scenario,
- all selected risks in the pessimistic scenario.
- Selection of positive risk events is opposite.
41Risk Simulation three scenarios approach
- The most probable and pessimistic project
scenarios may contain additional activities and
costs due to corresponding risk events and may
employ additional resources and different
calendars than the optimistic project scenario. - As a result the project planner obtains three
expected finish dates, costs and material
consumptions for all major milestones.
42Recommended Parameters
- They are used to rebuild probability curves for
the dates, costs and material requirements. - Defining desired probabilities of meeting project
targets a project planner obtains recommended
finish dates, costs and material requirements for
any project deliverable.
43Success Probabilities
- If different targets were approved then it is
necessary to calculate the probabilities of
meeting these targets. If they are reasonable
then they may be accepted. - Probabilities to meet approved project targets we
call Success Probabilities. - These targets may be set for all project
parameters that will be controlled (profit,
expenses, duration, material consumption).
44Baseline
- Target dates do not belong to any schedule.
Usually they are between most probable and
pessimistic dates. A set of target dates and
costs (analogue of milestone schedule) is the
real project baseline. - But, the baseline schedule does not exist!
45Buffers
- We recommend using the optimistic scenario for
setting task objectives for project implementers
and managing project reserves at the management
level. - The difference between scheduled and target
finish dates shows current schedule contingency
reserve (buffer), - Cost buffer is the difference between targeted
and calculated cost.
46Buffers
- As we discussed earlier there are several targets
for each parameter and corresponding buffers (PM
team targets, top management targets, contract
targets, failure targets). - Each target has its own initial probability of
successful achievement. - Example
- Project team target profit can be achieved with
65 probability, - Management target profit has 80 probability of
success, - Failure profit will be exceeded with 95 initial
probability.
47Risk Analysis Sample
- There are time, cost and material buffers that
show contingency reserves not only for a project
as a whole (analogue of Critical Chain project
buffer) but also for any activity in the
optimistic project schedule.
48Part 4
49Trend Analysis
- Project Performance Management will be based on
trend analysis. - It is necessary to discover problems as soon as
possible and, by analyzing trends of the major
project parameters, the project manager can
quickly understand if there are problems with
project performance.
50Trend Analysis (Deterministic approach)
- If risks were not analyzed and simulated it is
reasonable to analyze trends of the forecasts for
data that were used in success criteria
definition. - If we defined that the project performance will
be considered as successful if NPV forecast for
the specified date exceeds the target value then
we will analyze if this forecast is growing or
not. - Negative trend shows problems in project
performance and requires consideration of
corrective actions.
51Success Probability Trends
- The best way to measure project performance is to
analyze what is going on with the project success
probabilities. If they are increasing it means
that contingency reserves were spent slower than
expected, if they dropped it means that project
performance is not as good as planned and
corrective actions are needed.
52Success Probability Trends
- Success probabilities may change due to
- Performance results
- Scope changes
- Cost changes
- Risk changes
- Resource changes
- Market conditions changes
53Success Probability Trends
- Thus, success probability trends reflect not only
project performance results but also what is
going on around the project. - We consider success probability trends to be the
really integrated project performance measurement
tool.
54Success Probability Trends
- Success probability trends may be used as the
only information about project performance at the
top management level because this information is
sufficient for project performance estimation and
for appropriate decision making. - We call the described methodology Success Driven
Project Management.
55Part 5
56Success Management Steps
- Project Success Management includes following
steps - 1) Define integrated project success criterion
that is based on the project business goal.
Usually this criterion is the project cash flow
(profit) value at some specific date in the
future. - 2) Set reasonable and achievable target values of
project success criterion for project stuff, for
project management team, for organization
management. - 3) Define what business results mean that project
termination shall be considered.
57Project Success Management Steps
- 4) Basing on performance management results
calculate current value of success criterion, and
current probabilities to meet project targets. - 5) Analyze success probability trends. If this
trends are negative consider corrective actions. - 6) Determine, analyze and implement corrective
actions. Corrective action should raise success
criterion value.
58Project Success Management Benefits
- One single integrated success criterion makes
management and project performance analysis
easier and more reliable. - Risk simulation helps to determine necessary
contingency and management reserves and to set
reasonable targets. - Success Probability Trends integrate project
performance results and show performance problems
immediately.
59Project Success Management Benefits
- Success Probability Trends integrate project
scope, time, cost, risk, and procurement
performance information. They may be used at the
top management level as the only and sufficient
tool for reliable project performance analysis
and decision making.
60THANK YOU!
- I will appreciate your feedback
- and future discussions.
- Vladimir Liberzon
- spider_at_mail.cnt.ru
- www.spiderproject.ru