Title: Status and Schedule
1Status and Schedule
M. Della Negra US CMS Collaboration Meeting
Florida State University, 11 May 2002 Civil
Engineering and Magnet Updates on sub-detectors
status Finances Schedule and Milestones
2UXC
Experimental Cavern UXC55 More than 50
complete UXC55 ready July 04
3USC
Service Cavern USC55 More than 50 complete USC55
ready March 04
4Swiveling Platform
Swiveling Platform (Korea) Assembly finished at
Pt. 5
5Swiveling test in 2002
A counterweight will be installed to simulate
the equivalent weight and momentum due to the
cantilevered 250 t of the Cold Mass
6Status of Conductor
Each length is 2650m long
7Winding Prototype
4 layers winding using spare length of 2.65km
progressing well
Full diameter 6m 1/4 length 0.6m
8CB-2 mandrel ready
Coil is made of 5 submodules CB-2, CB-1, CB0,
CB1, CB2 Mandrel for CB-2 is finished 6
months late problem with supply of special
elements in high strength alloy for mandrels,
plates and flanges. CB-2 completed end 02 CB2
completed end 03
9Compressors for Cryogenics at point 5
10Tracker Outer Barrel Module
Hybrid
with ST sensors
APV
- 50 of Si Strip Tracker budget committed
- Si modules from the Milestone 200 produced in
different production centers - Start of Si module production shifted from June
2002 to Nov. 2002 due to hybrid optimization
(safer design and cost).
11Production Hybrids
First 4 received, flex cable ok !!! 20 20
ordered, delivery ½ May All mechanical test up to
now are ok Specifications ready by 25/5 Going to
tender asap
12Outer barrel rod fully equipped for system test
First small sub-system (outer barrel rod)
equipped with modules
13Beam Pipe EDR and Pixel installation
EDR went well and pixel installation was proven
to be compatible with our expectations.
14Crystals and Photodetectors
All 138 ovens at BTCP modified to grow large
boules Offers in hand for endcap xtals
APDs
Expected rate of 5000 APDs/month reached. 25k
out of 130k APDs delivered
VPTs
First 500 production VPTs delivered
15ECAL Mechanics
Module assembly
Endcap Supercrystal
Assembly of modules for first supermodule (SM1)
started in CERN and Rome.
EE EDR mid-2002
16Supermodule Assembly
Assemble a few bare SMs in 2002
17ECAL Electronics
CMS and LHCC Reviews in 2001 revealed major cost
overruns in electronics Last RRB Double speed of
optical links half cost of links BUT
insufficient Action - Mar 02 Alter electronics
architecture to contain costs generate L1
trigger primitive (S25 xtals) on-detector rather
than off-detector reduce links and off detector
electronics by factor 10. FPPA Final
submission May02 Electronics team reorganised,
synergy between ECAL, Tracker Preshower
electronics
TDR
TP
91000 Data and Control Links 800 Off-detector
Trig/DAQ Boards
12000 Data and Control Links 120 Off-detector
Trig/DAQ Boards
18ECAL Planning
Goal Apr 07 - ECAL complete and
commissioned Advance the detailed test (also
system test) of 1st SM to mid-2003 (final analog
electronics emulated FPGA digital part) EB
electronics mounted in 2004/2005 calibrate at
least 9 SMs in 2004 EE and SE mounted in
2005/2006, calibrate 1 Dee in 2006
Electronics Schedule
19Evolution of CMS Data Acquisition
New modular design of Event Builder - Break into
a number of functionally identical, parallel,
smaller DAQ systems A 64x64 system is feasible
today Submit DAQ TDR end-02
20High Level Trigger
- Lvl-1 trigger in construction phase now
- HLT running in processor farm immense amount of
data generated exercising remote sites - Detailed analysis leads to lt 400gt ms/event (on a
PIII _at_ 700 MHz box) - Maximum flexibility full event data available
- using offline software (very important to
understand HLT performance) - In terms of 2007 CPU units, this is 31.5 years
away. - CPU needs should be within reach
- A 50kHz system at startup will need 2500 CPUs
- N(CPU) (0.4 sec x 50000 sec-1)/(222) 20000/8
2500
CPU time/evt
L1-rate
Moores law
At (staged) startup 50kHz _at_ Lvl-1 and 80Hz to
storage Discovery physics safe. SM physics
resource-driven High luminosity in DAQ TDR at
end-2002
21Construction Commitment Profile
Apr 02 RRB
By end of 2002 70 of the available funds will
have been committed. 62.7 MCHF of additional
funds need to be committed soon in order to have
a complete initial low luminosity detector in
2007.
2220 MCHF Staging/Savings ?
After RRB13 the Director of Research requested
CMS to prepare plans for the case where 20 MCHF
of the shortfall is not covered (with respect to
the RRB13 shortfall of 67.9 MCHF) BUT with the
hope of getting it later. Staging/Saving already
applied for 1st Physics Run 5
MCHF HCAL Reduce no. of longitudinal
samplings 2.0 MCHF ME1/1a Reduce no. of
electronics channels 1.5 MCHF ME4/1 re-stage
electronics 1.5 MCHF Additional Staging
Considered for 1st Physics Run 8.5 MCHF
TRIDAS Start with 50 of DAQ Capacity 8.0 MCHF
Infrastructure SCX Cooling and Ventilation
Plant 0.5 MCHF Additional Saving Under
Technical Evaluation 5 MCHF LV Supplies Use
400Hz, 400V system 5.0 MCHF Decision in June
2002. TOTAL Staging/Savings 18.5 MCHF
23Additional Collaborators
Serbia Corner Pieces Magnet approved in Mar CMS
Week 400 kCHF protocol agreement Milan,
INFN ECAL approved in Mar CMS Week Naples,
INFN RPCs approved in Mar CMS Week Brazil YE4
farm YE4 funded (500 kCHF), application in
2002 Ireland ECAL electr.?, farm Visited CERN
18-19 Feb Expect application in
mid-02 Mexico Silicon Tracker Expect application
soon NZ farmPixels Applic. received, Pres. in
June Visit at CERN S. Thompson Thailand ME
electronics boards in progress US-NP
(HI) TriDAS, farm Successful workshop in MIT
8.02 Proposal submitted to DoE March 15 0.9
MCHF already in Financial Plan.
24High Luminosity Upgrades
10. Items (upgrades) for high luminosity 19
MCHF 10.1 ME4/2 mechanics and electronics
9.2 10.2 ME4/1 electronics 1.5 10.3 ME4/1
assembly in PNPI 0.5 10.4 Restore ME1/1a
electronics 1.5 10.5 Neutron Shielding
(extra) 1.0 10.6 3rd Forward Pixel
Layer 2.5 10.7 5th endcap RPC layer 2.0
10.8 Extra Installation Costs 1.0
The decision to build many of these items will
only be taken after inspection of the first
physics data. This upgrade cost comes on top of
the 62.7 MCHF shortfall. A plan for the funding
of the upgrade will have to be worked out in due
time. Basic ingredients are new collaborators or
upgrade plans by funding agencies willing to
upgrade items in which they have been working on.
25April RRB (RRB14) Outcome
MO MoU accepted, proceed with signatures MO cat
A 2002 Budget accepted (1 MCHF with sharing
according to nb of PhDs). No request for in kind
contributions in 2002. MO Cat B Must work out a
way to share costs (by Oct RRB) CI costs
accepted (positive report by scrutiny group). CI
profile peaks in 2003. Cash flow? 50 of CI is
manpower. CMS Financial Plan well received.
Expect 54 MCHF additional funds for a shortfall
of 62.7 MCHF. Next step - Reach an agreement
with Agencies by end June 02 on likely
availability of funds (firm, less firm
promisies), amounts and time profiles. Then
prepare Financial Plan for Oct RRB (also discuss
during LHCC CMS CR in Oct02)
26Expectations for additional funding at RRB14
Guideline Expect
Guideline Expect
Austria 600. 600. Belgium
870. 300. Brazil 500. 500. Bulgaria
106. CERN 13500. 13500. China
700. 700. Croatia 49. 49.
Cyprus 106. Estonia
16. Finland 870. 870.
France CEA 1000. 660. France
IN2P3 4000. 2000. Germany 2703. 2703.
Greece 880. Hungary
58.
India 774. 300. Iran 500. 500. It
aly 12900. 12900 req. Korea
458. Pakistan 428.
Poland 528. Portugal
352. 352. RDMS 2250. 2250. Serbia
400. 400. Spain 1350. 1350.
Switzerland Taipei 410.
Turkey 58. UK
1530. 1530. USA 15000. 12800. TOTAL
62896. 54264.
27V33 Draft Schedule Extended Surface Phase
Additional costs part of C I
Objectives channel test of HV/LV burn-in of
electronics flushing gas readout test of ?10
of subdet (MB,ME, RB etc) vertical slice
tests with test-beam DAQ prototype final
DAQ
28v33 Draft Schedule
- A new planning v33 is in preparation for the next
LHCC comprehensive review. - Objective Complete CMS (except pixels and ME4)
for 1 April 2007 - UX and US area ready (12 months shift, now firm
date) Jul 04. - Install floor plates and shielding in UX
area Nov 04- Apr 05 - Magnet test on surface (9 months shift) Jan
05- Apr 05 - Start lowering CMS May 05
- ECAL Barrel (EB) ready for installation ( 4
months) Jul 05 - Start EB installation cabling (3 months float)
Nov 05 - Tracker ready for installation Oct 05
- Start Tracker installation cabling (3 months
float) Feb 06 - EE (ECAL endcap positive z-side) calibration in
SPS beam Apr 06- Sep 06 - Start EE installation Nov 06
- Start EE- installation Jan 07
- CMS closed ready Apr 07
29Conclusion
Magnet Yoke finished. Conductor and winding well
advanced. 1st coil delivered end 02 with 6 months
delay. Not critical HCAL, Endcap Muons
construction on schedule and well advanced.
Problems are being encountered but are also
being overcome. To watch Production rate of DTs
and RPCs need to watch production rate Start of
mass assembly of Si modules (Q4 2002) ECAL
Redesign of electronics chain. Very tight
schedule. Draft v33 CMS Schedule Magnet test on
surface Jan 05- Apr 05. Start lowering detector
in May 05. CMS closed ready for 1st beam 1st
April 07. CMS construction is proceeding at
speed. A low luminosity detector can be ready
for physics in 2007. The low luminosity detector
is the complete CMS detector, except the 4th
forward muon station (ME4) and the 3rd forward
pixel layer.