Rand Water Parliamentary Portfolio Committee Water Affairs - PowerPoint PPT Presentation

About This Presentation
Title:

Rand Water Parliamentary Portfolio Committee Water Affairs

Description:

All Rand Water financial reports are unqualified. Staff Employed - 2900 ... KZN Donga Rehabilitation. GDACE. R 1 485 000. Mogale City. DACEL-Alien Plant Removal. GDACE ... – PowerPoint PPT presentation

Number of Views:83
Avg rating:3.0/5.0
Slides: 21
Provided by: knai
Category:

less

Transcript and Presenter's Notes

Title: Rand Water Parliamentary Portfolio Committee Water Affairs


1
Rand WaterParliamentary Portfolio
CommitteeWater Affairs Forestry
  • Presentation of Annual Report

2
Snapshot
  • Revenue - R4,119 bn (R3,672 bn2006)
  • Total Assets - R 6,257 bn (R5,387 bn2006)
  • All Rand Water financial reports are unqualified
  • Staff Employed - 2900
  • Corporate ISO 90012000 accredited
  • All plants ISO 14001 accredited

3
Rand Water Geographical Footprint
Consumers - 12 millionSupply Area - 18
000 km2Total Pipeline Length - 3 400 kmTotal
Number of Reservoirs - 54
4
Performance Highlights
25.3
  • Profit
  • Revenue
  • Cash generated from operations
  • Sales volume

12.2
17.8
2.7
5
Performance Highlights
  • 2007 2006
  • Customer Satisfaction Index 76 76
  • Training spend (as of Total Payroll) 7 7
  • Employment equity at management level 75 64
  • BEE spend 64 60

6
Corporate Social Involvement
  • Water related and non-water related
  • The focus area and allocation of funds ( Approx
    R2.5 m)

Focus Area Type of Support Spent
HIV/AIDS Home based care R780 000
Special needs institutions Training equipment R493 000
People with Disabilities Resource provision R335 000
Women Empowerment Shelter provision R304 000
Care of the Elderly Support to institutions R284 000
Partnerships Partnering with organisations R420 000
Health Grants to organizations R 80 000

7
Corporate Social Involvement
  • This is water related activities in partnership
    with different stakeholders

Summary of Job Creation and Local Supplier Support
Gender Jobs Created
Male 224 48
Female 267 52
Total 513 100
Project funds spent on local labour and suppliers
Items Funds Spent
Traditional Suppliers 468 000.00 4
PDI Suppliers 10 000 000.00 52
Total 10 468 000.00 100
8
Corporate Social Involvement
  • This is water related activities in partnership
    with different stakeholders

Project Description Area Project Value Funder
Water pipeline Reinforcement Winterveldt R 7 000 000 CT
Winterveldt Sanitation Winterveldt R 7 500 000 CT
Emfuleni Leaks Repairs Bekkersdal R 1 900 000 Emfuleni, RWF
Tshwane- Leaks Repairs Mamelodi R 1 500 000 CT, RWF
DACEL-Alien Plant Removal Elandsfontein R 1 665 000 GDACE
DACEL-Alien Plant Removal Mogale City R 1 485 000 GDACE
KZN Donga Rehabilitation Bergville R 4 825 000 DEAT
HIV/Aids Mainstreaming National R 1 754 000 DWAF
Water Sector Monitoring National R 7 200 000 DWAF
Bushbuckridge Water Supply Kumani Village R 1 900 000 BBR
Rand Water Golden Gate Freestate R 2 000 000 RW
Siluma Wetland Gauteng R 5 550 000 RWF
Blesbokspruit Nigel R 1 265 000 RWF
Sri Lanka Water Service Support Sri Lanka R 3 850 000 DWAF
TOTAL R46 383 000
9
Energy Crisis Impact
  • Request by Eskom to cut usage by 10
  • Active engagement with Eskom
  • Cooperation but on our terms
  • Water quality and reliability problems
  • Active/Dynamic pumping and reservoir management
    to encourage savings
  • Essential services exemption
  • Still finding ways of saving on electricity usage
    energy efficiency programme

10
CONSULTATION
  • SALGA
  • Use of surplus to reduce tariff
  • Supported Capital Programme
  • Value chain sustainability
  • National Treasury
  • Inflation target
  • Explore feasibility of further reduction

11
(No Transcript)
12
Allocation of surplus Project Overview
Forecast Cashflow Forecast Cashflow Forecast Cashflow Forecast Cashflow Forecast Cashflow Forecast Cashflow Forecast Cashflow Forecast Cashflow
Significant Capital Projects Significant Capital Projects (R m) Jun-08 Jun-09 Jun-10 Jun-11 Jun-12
A Augment infrastructure 5720 420 439 395 470 529
B Renovation replacement 1370 148.6 271 344 323 310
C Total 7090 569 710 739 793 839
13
Allocation of surplus
  • Central to our operations - pipelines
  • Generally very old mostly in excess of 80 years
  • Significant amounts being spent on augmentation
    and refurbishment to ensure operational
    sustainability
  • Increased expenditure due to escalation
  • Reserves will be used to smooth the tariff and
    cater for new schemes

14
Projects plan - Process Steps
  • Additional water supply scheme due to
    development.
  • Planned programme of renovation to existing
    infrastructure
  • Analyses of latest estimates of future water
    demand growth patterns depending on development
    statistics.

15
Projects plan - Process Steps
  • Condition assessment of current infrastructure.
  • Annual infrastructure recommendations combine
  • - extra capacity for 15 year demand growth
  • - renovation to maintain existing capacity

16
How are costs determined
  • Estimates for these projects are done by
    escalating similar work already completed.
  • By enquiring from the market what the current
    costs for the work are.

17
Water Quality
  • Full adherence to SANS 0241 (based on a WHO
    standards)

18
Water Quality - Cont
19
Fit with overall DWAF Strategy
  • Emfuleni Sanitation
  • Delmas involvement
  • Western Highveld Involvement

20
Challenges Sanitation Environmental Pressures
  • 85 per cent of local municipalities within Rand
    Waters catchment area have challenges with
    meeting DWAFs effluent management standards
  • This increases Rand Waters purification cost
  • This ultimately places greater pressure on Rand
    Waters tariff increments

One solution is to roll out the Emfuleni Regional
Sanitation Scheme
Write a Comment
User Comments (0)
About PowerShow.com