Transcript and Presenter's Notes

Title: The 7 days at


1
The 7 days at x
Revised May 12 2002
2
The 7 Days at XA Real POC
  • This is a real story with the name(s) changed to
    protect the innocent
  • Each step required only one or two technical
    people
  • The plan changed during the work - this is real
    life and you must allow for it
  • Planning for Problems Prevents Problems

3
Mission at X
  • Business Objectives
  • Reduce MTTR and Operations Staff
  • Focal Point Console with Ability to Zoom to
    Specific Systems
  • Cross platform Scheduling
  • Improve Competitive Position Thru New Services
  • Online Services Availability Impacting
    Competitive Position
  • Detect Network Faults Early and in the context of
    the Business/Enterprise
  • SAP Rollout Quality Impacting Business
  • Manage SAP as a Whole
  • Failed Audit
  • Need single Security Image Across MVS, Unix, NT

4
Mission at X
  • Business Objectives
  • Focal Point Console with Ability to Zoom to
    Specific Systems eliminate consolitis, improve
    MTTR
  • Detect Network Faults Early and in the context of
    the Enterprise improve MTTR
  • Manage SAP as a Whole focus on mission critical
    application as a process
  • Single Security Image Across MVS, Unix, NT
    reduced admin, enhanced security
  • Cross platform Scheduling reduced admin/errors

5
Technical Deliverables
  • Unicenter TNG 2d and 3d Workstations
  • Enterprise Management Event Focal point console
  • SSO Server on Unix
  • Unicenter 1.1 and 1.5 on Unix
  • Unicenter 2.x on NT
  • Unicenter v1 on Novell
  • Polycenter on VMS

6
5
4
1
Automation Point
MVS
Polycenter
DEC UNIX
2
NT 2D
HP UNIX
AIX
NT SQL
SUN Solaris
3
NT Agent
OS/2
6
NT SAP
UNIX SAP/R3
Novell
Novell
Novell
7
Hardware to manage
  • 4 Unix servers
  • 4 NT servers
  • 3 Novell LANs
  • VMS systems
  • MVS SAP R2
  • SAP R3 on Unix

8
Before We Start
  • Verify kits received
  • Verify correct media
  • Scan (again) for key customer issues
  • Check STARTRAK for fixes and test fixes
  • Verify licenses are available
  • Wrong Unix release, no OS on main server, wrong
    media shipped, needed patches

9
Milestones and Process
  • Stepwise Implementation with Deliverables
  • Daily CA Internal Show and Tell
  • Nightly Meetings to Adjust Staffing/Plan

10
The 7 Step POC at X
  • Unix Focal Point Event Console
  • NT Control Event
  • Novell LAN Integrator Event
  • Polycenter VMS Integration
  • Cross Platform Scheduling with Mainframe
  • SAP/R3
  • Demo

11
Discover Customer Network
  • Connect to TCP/IP Network
  • Needed Community Name for Router
  • DNS Address
  • Determine Subnets to Discover
  • DNS synch issues, bad WINS, no one knew community
    name, lab could not see network originally, IP
    address changed during project

12
1 UNIX Focal Point Event Console
Focal Point Console
  • Unix sysadmin would not give root acess

13
2 Add NT Use NT As Console
NT
2D
AIX
SQL
NT
NT
  • Wins and /etc/hosts did not match

14
3 Add Novell
NT
Novell
Novell
  • Novell downlevel, needed to apply maintenance

15
4 Add Polycenter
DEC VAX
NT
  • Trouble finding client contact with VAX access

16
5 Add MVS OPS/MVS Cross Platform Scheduling
NT
Automation Point
MVS
  • MVS change control process added delay

17
6 SAP/R3
NT
SAP/R3
UNIX
  • SAP guru needed resold on solution

18
7 Demo
  • 1 Unix Focal Point Event Console
  • 2 NT Control Event
  • 3 Novell LAN Integrator Event
  • 4 Polycenter Integrator
  • 5 Cross Platform Scheduling with Mainframe
  • 6 SAP/R3
  • 7 Demo

19
5
4
1
2
3
6
20
The 7 Days at XA Real POC
  • Did steps as islands to extent possible
  • Each step required only one or two technical
    people
  • The plan changed during the project - this is
    real life and you must allow for it
  • Build on success
  • System integration testing do not forget and do
    not underestimate problem potential
  • Client had changed the environment as we went so
    day 1 and 2 stuff stopped working - twice