Title: ION ACCUMULATION IN LEIR
1ION ACCUMULATION IN LEIR
Presented by M. CHANEL
THIS CONCERNS ONLY LEIR
27 August 2001-PS-MB Technical Seminar
2CONTENTS
- LEAD on LEAD
- General view
- Linac3
- Injection
- Cooling
- Lattice and machine elements
- Vacuum
- PS and further
- Other ions
- Different systems
- Cost
- Planning
- Summary
3LEAD Performance needed
- 7 107 Lead ions/bunch in LHC at 2.7 TeV/n in a
normalised emittance of 1.5 mm(bg s2/bh,v). (
quench limit and central detector limit) - Overall transfer efficiency of 30,
- elt1.2 mm at the exit of SPS,
- elt1 mm at the entrance of SPS after final
stripping, - elt0.7 mm at the entrance of PS.
- This means 4 bunches in Leir with 2.3 108
ions/bunch. Or a total of 0.9 109 ions in 1,2,4
bunches?
4GENERAL SCHEME
LHC.LEAD.PUB
5(No Transcript)
6Stacking tests of lead ions
requested
Sourceefficiency
Lossescharge state
7LINAC3
- Improved afterglow pulsed ECR source (450ms pulse
length but increased current from 100mA to 300mA
Lead 27 Leir uses 200 ms). - Accelerate to 4.2 MeV/n, b0.0945
- Add a cavity to ramp momentum up to 1
- Stripping afterwards and use of Lead 54
(Slightly less intensity than for Lead53, but
acceptable lifetime with electrons of the
electron cooler ) - Pulsing from 1 Hz up to 10 Hz ( 5 Hz probably
sufficient).
Collaboration Catania, Grenobles, Cern, GSI
8LEIR
- Combined H/V/P multiturn injection inclined
septum momentum variation of incoming beam such
the injection orbit (D dp/pbump) remains the
same during injection. 50 injection efficiency
reachable(75 on paper). - Cool and stack the freshly injected beam by
electron cooling in 400 ms max. - 4 injection-cooling-stacking cycles should be
enough (timelt1.6s). - Acceleration and ejection (h2) at T71MeV/n
energy choice is a compromise between the limit
of incoherent tune shift in PS, the time between
bunches for the ejection kicker, the min RF
frequency in PS and the stacking time in SPS/LHC.
9LEIR Injection
- Combined injection gives lower et (better cooling
time) compared to normal multiturn but increases
mom. spread (good long. cool.). - Combined injection implies large D and D/??
5m1/2 (D10, b3).
10X-Y plane105 turns tracked
Cooled beam
E-SEPTUM
New beam from linac D0
11- X-Y plane after 100 turns
- 75 injected
- x and y and momentum projected distributions
12LEIR INJECTION LINE
13Cooling and Stacking
- Electron cooling theory gives
- where q is the relative difference in angle
between the ions and electrons qi?(?/?) - the parameter hecool Lcooler/Lmachine
- and Ie is the electron current.
- A and Q atom mass and charge state
- Large b desirable but ion beam size should remain
smaller then e-beam size and mind the effect of
the e-beam space charge. optimum around b5m
14Lattice
- Good for injection and coolingstill 2 periods
- tune(1.8,2.7)
- longitudinal acceptance reduced to dp/p 1
- 5 quad families, more flexible.
15Electron cooling
16(No Transcript)
17GUN
Dipole
Toroïd
DRIFT
18(No Transcript)
19(No Transcript)
20LEIR cycle for LEAD ions
21RF
22OTHERS
- With an electron beam of 200mA, the cooling rate
is sufficient to counteract the IBS growth rate
and get the emittances wanted. - The beam will be maintained stable mainly during
cooling (coasting beam) by a 100MHz bandwidth
transverse active feedback.
23LEIR EJECTION TO PS
24A word on vacuum
- During the tests in 1997, the Lear vacuum was
good (5E-12T without beam) but the lost lead
ions (e-ion recombination..lead 54 or res. gas
charge exchange or..) degas the chamber walls.
One lead ion releases 105 molecules!!!! - At end of linac3, tests of different vacuum
chamber treatment are under way. - Hope outgassing can be reduced by appropriate
treatment of the vacuum chamber. - Already known when ions are lost perpendicularly
to walls, outgassing is decreased.
25(No Transcript)
26(No Transcript)
27PS(preliminary)
- Inject (change/modif. septum-kicker) and
accelerate on h16 up to T1.5 GeV/n - h16?14?10 , split 2b. to 4 bunches and finally
h20 ?17 - h17 is chosen to have 125ns b. separation at
flatop in LHC and it is compatible at 4.25GeV/n
with 200MHz RF system in SPS. - Acceleration to 4.25GeV/n, cp/Q20. GeV/c/charge.
- Stripping in TT2. Change of TT2 line to have a
low beta at stripper.
28TT2(from PS to SPS, has to be changed)
- At stripper bh,v20m?5m, D-1m
- Blow-up reduced by a factor 4 compared to
old(normal)optic.needs MD for SPS matching.
De0.2mm after re-matching in SPS?. - Need of 4 quad, 6 power supplies building?.
29LIMITS OF THE ACTUAL SCHEME
- Specifs for LHC-LEAD not achievable by SPS ( tune
shift too high, el growing by IBS too large) - SPS tune shift acceptable if cp/QPS risen to 26
GeV/c/Q but IBS still not acceptable (RF 200 MHz
? 80MHz?). No implication on LEIR as it is
proposed. - Specifs for light ions not achievable and strong
implications on LEIR. To harmonise tune shifts
along the chain ( LEIR,PS-0.25, SPS-0.07) - a simple way to increase limit in the SPS is
- increase extraction energy in PS.(RF change in
SPS?) - strip ions completely at the exit of LINAC3 then
RF frequency higher in LEIR (max from 3.5 MHz to
6 MHz). - increase extraction energy in LEIR to increase
limit in PS but then limit at low energy in LEIR. - It is then mandatory to review the overall chain.
30Other ions
- PS-SPS transfer 26GVSPS RF 200MHz (IBS?)
- always 4 bunches from PS to SPS
31Different Systems
- Inj./Ej. Line magnet spec. (not detailed) 8
QTWs, 2 BHN 1.7 and 0.4 Tm2 cores, 2-4 DVN
instrumentation. One inclined SEH , one pulsed
magnetic septum, and pulsed power supplies. All
others recup. But some power supplies
modifications or renewal(kickers, bumpers) - Electron cooling- specifs known.Novosibirsk? 2
DHVs Old quad power supplies for solenoids. - Machine magnets- all recuperated (even 4 reserve
quad added ) but 6 big powers supplies (BHN5
quads families) . renewal of controls. - RF-2 cavities partly specified- Japanese cores
- Machine instrumentation- specifs knownadjust.
32Different Systems (suite)
- MechanicsAll elements position known
- Vacuum not completely known. This is the weakest
point of the study but an important point for
the machine. - Controls ok but not detailed.
- Subsystems like safety, water cooling..
33LEIR COST (and only LEIR)
/specifications/cost-recapitule/cost..xls
34Why a difference with the original price (1994)
35Staffing (from PS-conclave in FV)
36Planning
37Summary
- Accumulation schemes for different kind of ions
are well advanced but to finalise SPS must be
studied. - Electron cooling of heavy ions is defined.
- Space charge limits both in LEAR and PS are
harmonised. Space charge cooling/filling time
are the main limitations especially for light
ions. - Vacuum degradation due to losses is a challenge.
- IBS and conservation of high beam density is
another challenge. - Rough planning established, cost known within
10. - All technical systems are specified.
38OUTLOOK
- REVIEW OF COMPLETE CHAIN
- September DESIGN report (readable draft end of
sept.). - Start detailed planning,
- Final specifications end of this year.
39TUNE SHIFT