Title: Next European Dipole (NED) Status Report
1Next European Dipole (NED) Status Report
Arnaud Devred CEA/DSM/DAPNIA/SACM
CERN/AT/MAS on behalf of the NED
Collaboration CARE Steering Committee
Meeting 5 September 2005
2Some very good news
for our American colleagues!
- The DOE has agreed to fund the US-LHC
Accelerator Research Program (LARP) with a budget
of 11 M for FY06 (approved by Congress but not
yet signed by the President. - This budget level should be kept constant for a
few years (until 2009?) - For FY06, it will be divided up into 5 M for
magnets, 4 M for accelerator-related RD and 2
M for management (shared between FNAL, BNL, LBNL
and SLAC). - The goal of the magnet part of LARP is to build
by 2009 one or two 4-m-long, 90-mm-aperture, 200
T/m quadrupole magnet prototypes.
3Some pretty sad news
for the NED collaboration!
- The EUROMAG NEST Adventure proposal has been
turned down by the EU on the ground that it was
not adventurous enough - Hence, we are back to square one regarding the
funding of the model magnet manufacturing and
test
4NED Programme
- The NED Programme is articulated around four
Work Packages and one Working Group - 1 Management Communication (MC),
- 2 Thermal Studies and Quench Protection
(TSQP), - 3 Conductor Development (CD),
- 4 Insulation Development and Implementation
(IDI), - 5 Magnet Design and Optimization (MDO) Working
Group. - It is carried out by a collaboration made up of
8 institutes CCLRC/RAL, CEA, CIEMAT, CERN,
INFN/Genova and INFN/Milano, Twente University
(TEU) and Wroclaw University of Technology (WUT).
5MC Work Package
- We have held three Steering Committee (SC)
meetings since the beginning of the year - 20 January at CERN
- 14 April at CERN
- 7 July at WUT
- Next SC meeting will be held at CERN during the
CARE general meeting next ESAC meeting will be
held at CERN before or after the planned
HHH/WAMDO (April 2005). - Second quarterly report will be completed by the
end of the week. - All relevant documents are stored into EDMS and
posted on the NED website - http//lt.tnw.utwente.nl/project.php?projectid9
6TSQP Work Package
- The TSQ Work Package includes two main Tasks
- development and operation of a test facility to
measure heat transfer to helium through conductor
insulation - (CEA and WUT Task Leader B. Baudouy, CEA),
- quench protection computation
- (INFN-Mi Task Leader G. Volpini).
7Heat Transfer Measurement (1/3)
- The first part of the Task was to design and
build a new double bath cryostat. - CEA wrote detailed specifications that were
handed out to WUT in June 2004. - WUT performed a call for tender in the Summer of
2004 and selected Kryosystem in Poland to
manufacture the cryostat.
Schematic of NED cryostat (courtesy F. Michel, B.
Baudouy and B. Hervieu, CEA)
8Heat Transfer Measurement (2/3)
- A first reception test of the cryostat was
carried out on Kryostems premises the 3rd week
of April 2005, which revealed a few problems. - WUT reacted very promptly and worked in close
collaboration with CEA to correct these problems. - A second reception test was carried out the 2nd
week of July 2005 (including thermal and leak
tests in liquid helium at 4.2 K), which was
deemed successful. - The cryostat will be delivered to CEA/Saclay on
19 September, for final implementation and
commissioning. - The 6-month delay with respect to the initial
schedule is not expected to any deleterious
impacts on the overall NED Programme.
9Heat Transfer Measurement (3/3)
Cryostat with thermal shields
Lambda plate
Inner view of cryostat with Instrumentation
(Courtesy M. Chorowski, WUT)
He II heat exchanger
10Quench Computation (1/3)
- INFN-Mi has undertaken a detailed analysis of
the thermal and electrical behaviors of NED-type
accelerator magnets during a quench. - The computation was started considering the
conservative, 88-mm-aperture, cos?, layer
design developed by D. Leroy. - It studied the influence of
- magnet length (1, 5 and 10 m),
- operating current (15, 22 and 29 kA),
- external dump resistance (15, 25 and 35 m?),
- quench detection delay (30, 40 and 50 ms),
- quench protection heater length.
- It also compared the results obtained by two
different codes QLASA at INFN-Mi and QUABER at
CERN.
11Quench Computation (2/3)
- The results show that, for the entire parameter
space, the magnet is quite safe to operate,
thereby justifying the choice of wire and cable
parameters made early on.
Quench simulation results on 10-m-long,
88-mm-aperture, cos?, layer design (Courtesy M.
Sorbi INFN-Mi)
12Quench Computation (3/3)
- Similar computations have now been started on
the more innovative, 160-mm-aperture, slot
design also proposed by D. Leroy. -
- The quench computation task is near completion.
88-mm-aperture, layer design (Courtesy D. Leroy,
CERN)
160-mm-aperture, slot design (Courtesy D. Leroy,
CERN)
13CD Work Package
- The CD Work Package includes two main Tasks
- conductor development
- (under CERN supervision L. Oberli has now taken
over D. Leroy as the official Task Leader), - conductor characterization
- (CEA, INFN-Ge, INFN-Mi, and TEU Task Leader A.
den Ouden, TEU). - It is the core of the programme and absorbs
about 70 of the EU allocated funding.
14Conductor Development (1/2)
- As a conclusion of preliminary design studies
carried out in 2003 and 2004 under the
supervision of D. Leroy, the following
specifications were derived for NED Nb3Sn strands
- diameter 1.250 mm,
- eff. filament diameter lt 50 mm,
- Cu-to-non-Cu ratio 1.25 0.10,
- filament twist pitch 30 mm,
- non-Cu JC 1500 A/mm2 _at_4.2 K 15 T,
- minimum critical current 1636 A at 12 T,
- 818 A at 15 T,
- N-value gt 30 at 4.2 K and 15 T,
- RRR (after heat treatment) gt 200.
- (It is also requested that the billet weight be
higher than 50 kg.)
15Conductor Development (2/2)
- Based on these specifications, a call for tender
was issued by CERN in June 2004 and two contracts
were awarded in November to 2004 to Alstom/MSA in
France (Enhanced Internal Tin process) and SMI
in the Netherlands (Powder in Tube Process). - After discussion with CERN, the two companies
agreed to work out their development program into
two successive RD Steps (referred to as STEP 1
and STEP 2) followed by final cable production. - A tentative schedule was established as follows
- STEP 1 Summer 2005,
- STEP 2 Summer 2006,
- Final production December 2006.
16Conductor Characterization (1/2)
- The NED-type conductor characterization
represents a real challenge, given the
unprecedented performances that are expected
(e.g., a critical current of 1600 A at 4.2 K and
12 T on a 1.25-mm wire, to be compared to the
timid 200 A presently achieved on 0.8 mm ITER
wires). - To validate sample preparation and measurement
processes, the laboratories involved (CEA, TEU
and INFN) have launched a cross-calibration
program reminiscent of the ITER/EDA
cross-calibration program carried out in the
mid-1990s. - Since the Summer of 2004, three rounds of
calibration wires have been prepared and
circulated among the various partners.
17Conductor Characterization (2/2)
- TEU and INFN have now achieved a good
convergence. - The problems at CEA have been identified and are
being solved. - All 3 partners should be ready when the first
wires become available.
SMI/Toshiba Test Wire (results are within 2)
(Courtesy T. Boutboul, CERN)
18FE Wire Model
- In Parallel, INFN-Mi has started to develop an
ANSYS model of an un-reacted, Alstom/MSA-type
wire so as to simulate cabling effects. - Running such a computation requires a detailed
knowledge of the mechanical properties of the
materials making up the wire (in the cold work
state where they end up prior to the cabling
operation). - To determine these properties, CERN has carried
out a series of nano-indentation and
micro-hardness measurements on various wire
samples, and compared the results with available
literature data. - The next step is to apply this model and the
appropriate mechanical properties to the wire
layouts presently considered by Alstom/MSA.
19IDI Work Package
- The IDI Work Package includes two main Tasks
- studies on conventional insulation systems
relying on ceramic or glass fiber tape and
vacuum-impregnation by epoxy resin - (CCLRC Task Leader E. Baynham),
- studies on innovative insulation systems
relying on pre-impregnated fiber tapes and
eliminating the need for a vacuum impregnation - (CEA Task Leader F. Rondeaux).
20Conventional Insulation (1/2)
- CCLRC and CEA have developed in collaboration an
engineering specification (issued in July 2004)
and a coordinated test programme (issued in
October 2004). - Since then, CCLRC has carried out a number of
screening tests of candidate materials. - The tests are applied to standardized laminates
representative of inter-turn insulation and
include - electrical breakdown test,
- short beam shear test,
- inter-laminar fracture test.
Example of Double Cantilever Beam (DCB) fracture
test (courtesy S. Canfer, CCLRC)
21Conventional Insulation (2/2)
- CCLRC has also investigated the issue of
sizing (a lubricant, usually organic, coated
onto the fibers of tapes, that need to be removed
prior to conductor wrapping and winding, thereby
rendering the fiber tape fragile and easy to tear
off). - Very promising results have been obtained with
an improved polyimide sizing, produced by
Hydrosize, NC, and applied by JPS, SC, which
seems to be able to sustain the required Nb3Sn
heat treatment without carbonization (thereby
eliminating the need for de-sizing). - More complete evaluation tests are underway.
22Innovative Insulation
- The work on innovative insulation has not
started yet, pending the hiring of a technician
at the CEA chemistry laboratory, which has been
delayed until early next year. - To compensate for this lack, it was decided last
spring to reallocate the EU funding of this task
to hire a postdoc at CEA. - A candidate has been identified, who is expected
to start working this fall. - The timing of this task is now becoming critical
with respect to the overall NED program.
23MDO Working Group (1/3)
- The MDO Working Group is made up of
representatives from CCLRC, CEA, CERN and CIEMAT,
under the Leadership of F. Toral, CIEMAT. - Its main charge is to compare different magnet
configurations so as to assess their efficiency
in terms of manufacturability, performance and
cost.
Cos???layer design (courtesy D. Leroy, CERN)
Intersecting-Ellipses design (courtesy H.
Felice, CEA)
Motor-type design (courtesy F. Toral, CIEMAT)
24MDO Working Group (2/3)
- In parallel, work is pursued at CERN so as to
optimize the baseline, 88-mm-aperture, cos? layer
design with respect to - conductor geometry,
- iron shape (to reduce saturation effects),
- ferromagnetic shims (to compensate magnetization
effects).
(courtesy N. Schwerg, CERN)
25MDO Working Group (3/3)
- CCLRC/RAL is also developing a 2D ANSYS model of
the 88-mm-aperture, cos? layer design so as to
optimize mechanical support. - This model includes sub-models of individual
coil turns to compute peak stresses in cable
strands and cable insulation.
(courtesy P. Loveridge, CCLRC)
26Conclusion
- A great deal of progress has been made since my
last presentation (at the CARE general meeting in
Hamburg last year), leading to a number papers
presented at various conferences (1 at CEC/ICMC,
1 at EUCAS and 4 at MT). - The cryostat for heat transfer measurements is
completed and will be delivered to CEA next week.
- The next few months will be critical for the
Conductor Development program with the results of
the STEP 1 wires. - The only Task that has not started is the
Innovative Insulation Task at CEA, but the hiring
of a Postdoc should help. - The funding of the model magnet manufacturing
remains an open question.