Title: City of Winnipeg SOUTHWESTERN RAPID TRANSIT CORRIDOR
1City of WinnipegSOUTHWESTERN RAPID TRANSIT
CORRIDOR
- Bidder Meeting
- October 16th, 2009
2Site Location
3Field Investigations
- - Klohn Krippen (2003) - Geotechnical
- 4 deep test holes, 1 shallow
- Groundwater monitoring
- Laboratory testing
- AECOM (2009) - Geotechnical
- 2 deep test holes ( rock coring)
- Groundwater monitoring
- Laboratory testing
- AECOM (2009) Hydrogeological
- Two test wells drilling
- Field pump tests
4Location of Test Holes
TW 1
TW 2
5Soil Stratigraphy
6Field and Lab Results
7Groundwater Conditions
- Clay 2 m below ground, Elv. 231 m
- Bedrock/Till Elv. 224 to 226 m
- Impact on
- Excavation stability
- Global stability
- Seepage
8Geotechnical Concerns
- Foundation type
- Rebound, heave and settlement
- Retaining walls
- Base heave
- Temporary shoring and excavation plan
9Bearing capacity and foundation type
- Raft foundation
- Design based on the concept of floating
foundation - Bearing capacity and settlement pressure are
defined
10Rebound, Heave and Settlement
11 Retaining walls
- Reinforced Concrete U-shaped section
- Reinforced Concrete Cantilever wall
- Coulomb Theory
- Design for surcharge from compaction during
construction - Design for live load surcharge from Cooper E90
loading -
12Base heave
Clay
h
Wclay
Till/Bedrock
FS Wclay /
?w h
13TYPICAL
EXTREME HISTORICAL
14Temporary shoring and Excavation plan
- Cut and cover construction
- Staged construction, Stage I and II
- Site constrains
- Limited space
- Utilities
- Private property
- Proximity to CN tracks
- Excavations plan include
- Open excavation
- Cantilever / Braced Shoring
- Combination of shoring and open excavation
15Temporary shoring and Excavation plan
- Excavation configurations
- Open Excavation, up to 6 m cut
- Other geometry lt 6m cut
1
4
3
3
1
3
3
16Temporary shoring and Excavation plan
- Excavation configurations
- Braced Shoring up to 9.5 m
4.6 Min
9.5
5
17Temporary shoring and Excavation plan
- Excavation configurations
- Combination of Braced Shoring and Open excavation
varies 5 m Min.
4.6
7m bench 5 m Crane pad
3
1
2-3
varies 7 Max.
3 - 5
18Temporary shoring and Excavation plan Lateral
Loads from Surcharge
19Temporary shoring and Excavation plan
- Base Instability analogous to bearing capacity
20(No Transcript)
21Global Stability
- - Stress stability coupled finite element
analysis - Locally acceptable soil parameters
- Account for excavation unloading
- Model train loading
- Design objective FS 1.30
22Stability output
23Stability output
24Stability output
25Stress-Deformation Analysis
26Stress-Deformation Analysis
27Performance Monitoring Program
- Instrumentation will be installed to monitor
- Displacement of railway tracks
- Displacement of shoring system
- Horizontal subsoil displacement
- Excavation heave
- Groundwater levels
28