Title: Air Pollution Control
1Air Pollution Control Air Pollution Control
Ordinance ( Chapter 311 )
2 Air Pollution Control Regulations Relevant
to the Construction Industry
- (Construction Dust) Regulation
- (Specified Processes) Regulation
- (Smoke) Regulation
- (Fuel Restriction) Regulation
- (Open Burning) Regulation
-
3 Air Pollution Control Regulations Relevant
to the Construction Industry
(Specified Processes) Regulation
4 Air Pollution Control Regulations Relevant
to the Construction Industry
5Air Pollution Control (Open Burning) Regulation
- Purpose
- Prohibit / Control Open Burning Activities
- Effective date
- 26 Feb 1996
6Prohibited Open Burning
7Application for Open Burning Permit
- 1. Allow at least 28 days for application
- 2. The applicant shall prove?
- a. an absolute need for the burning
- b. there is no other practical alternative
means of waste disposal and - c. there will not be adverse environmental
impact. - 3. The Authority may impose terms and conditions
in the permit.
8Penalties
9Purpose
Air Pollution Control (Construction Dust)
Regulation
- Employ effective dust abatement measures to
- Reduce dust emission,
- Reduce air nuisance, and
- Improve general air quality.
- Set out appropriate dust control measures and
make them as standard practice in the
construction industry.
10Classification of Construction Works
- Three main types of construction works
- Notifiable work building demolition,
construction of superstructure, site formation,
reclamation, etc. - Regulatory work (Notification not required)
road opening /resurfacing, external renovation,
slope stabilization. - Excluded work (Notification not required)
internal renovation, specified process, etc.
11 Notifiable Work
- Site formation
- Reclamation
- Work carried out in any part of a tunnel that is
within 100 m of any exit to the open air
- Road construction work
- Demolition of a building
- Construction of building foundation
- Construction of building superstructure
12Notification Form
13Dust Control Requirement
14Part III of Schedule
- General Control Requirements
15General Requirements
- Stop operating the relevant plant or dusty
process if there is breakdown of air pollution
control equipment. - Avoid using compressed air jet to clean off dust.
16 Site Boundary and Exit
- Provide vehicle washing facilities.
- Pave the area between site exit the vehicle
washing facilities.
- Provide 2.4 m hoarding along site boundary.
17Main Haul Road(4 or more vehicles passing in
any 30 minutes)
- Pave with concrete, bituminous materials, hard
cores, etc. and keep clear of dusty materials or - Maintain entire road surface wet.
18Road Leading Only to A Construction Site
- Clear dusty materials from the portion of any
such road within 30 m of vehicle entrance / exit.
19Cement
Bagged cement exceeding 20 nos should be covered
or enclosed in area sheltered on the top and the
3 sides.
20Cement
Bulk Cement or PFA stored in closed silo with
high level alarm.
21Exposed Earth
Treat by compaction, hydroseeding, vegetation
planting, etc. within 6 months after the last
construction activity.
22Dusty Materials Collected by Fabric Filters or
Other Equipment
- Dispose of in enclosed containers.
- Do not store in open area.
23Part IV of Schedule
- Control Requirements for Individual Activities
24Stockpiling of Dusty Materials
- Cover entirely by impervious sheeting
- Place in an area sheltered on the top and the 3
sides or - Maintain entire surface wet.
25Loading, Unloading or Transfer of Dusty Materials
- Wet dusty materials with water spraying prior to
operation.
26Transfer of Dusty Materials with a Belt Conveyor
System
- Enclose the belt conveyor from the top and the 2
sides. - Enclose the transfer point between conveyors.
- Install belt scraper and bottom plates.
- Maintain vertical distance between belt conveyor
outlet and material landing point at lt1 m. - Enclose the unloading area.
27Use of Vehicles
- Wash every vehicle before leaving the site to
remove dusty materials from body and wheels. - Cover any load of dusty materials.
Wash vehicle before leaving site
Load on truck covered
Load on truck inadequately covered
28Drilling, Cutting Polishing, etc
- Spray surface continuously with water.
- Equip with effective dust extraction and
filtering device.
Wet the breaking area to control emission
Dust collection system to control dust emission
Drilling without watering
29Debris Handling
- Cover or store debris in area sheltered on the
top and the 3 sides. - Enclose the debris chute.
- Wet debris before dumping into chute.
30Excavation or Earth Moving
- Spray the working area with water or chemicals
before, during and immediately after the
operation to maintain entire surface wet.
31Concrete Production
- Carry out de-bagging, batching and mixing of
cement and PFA in area sheltered on the top and
the 3 sides.
Concrete production in open area is NOT allowed
32Site Clearance
- Wet the working area before, during and
immediately after the operation. - Cover all demolished items or place in area
sheltered on the top and the 3 sides within a day
of demolition.
33Blasting
- Wet area within 30 m before blasting.
- No blasting during the strong wind signal or
tropical cyclone warning No.3 or above is hoisted
unless permitted by Commissioner of Mines.
34Part I of Schedule
- Control Requirements for Notifiable Works
35Reclamation
- Treat or seal any stockpile of dusty materials
(gt1.2 m high lt50 m from site boundary) with
bitumen or other suitable surface stabilizer.
36Demolition of a Building
- Wet the working area prior to, during and
immediately after demolition. - Enclose the building with impervious dust screens
to a height of at least 1 m higher. - Wet remaining dusty materials after removal and
clear the road surface.
37Construction of the Superstructure of Building
- Provide effective dust screen where a scaffolding
is erected. - Enclose the skip hoist.
38Part II of Schedule
- Control Requirements for Regulatory Works
39Renovation on Outer Surface of External Wall or
Roof
- Provide dust screen where there is scaffolding.
- Enclose the skip hoist.
- Wet remaining dusty materials after removal and
clear the road surface.
Screen effectively reduce dust nuisance
40Road Opening Resurfacing Work
- Cover dusty material.
- Spray, remove / backfill / reinstate dusty
materials within 24 hours. - Dusty materials shall notbe extended
beyondpedestrian barriers, fencing or traffic
cones. - Any remaining dusty materials after removal shall
be wetted and cleared from road surface.
41Exemption
- Road construction work
- exempt from hoarding requirement.
- Road opening or resurfacing work
- exempt from vehicle washing facilities and
hoarding requirements. - Slope stabilization
- exempt from vehicle washing facilities
requirement, and - exempt from hoarding requirement if the site
boundary adjoins road for vehicular traffic.
42Exemption for Emergency Work
- Where there is a threat to human life or building
safety. - Immediate repair of utility services, road
collapse or road blockage due to accidents.
43Penalties
44Tips to Reduce Dust Emission
- Include the plan and budget of implementation of
dust control measures in the tender. - Arrange delivery of dust suppression materials
and equipment to site at an early stage. - Ensure good communication between frontline
workers and management staff. - Promote staff awareness on dust control measures.
- Supervise frontline workers.