ENERGIA SUSTENTVEL DO BRASIL S'A ESBR - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

ENERGIA SUSTENTVEL DO BRASIL S'A ESBR

Description:

Maintenance of conditions of flow rates and physical / biotic flows during construction phase; ... of physical / biotic flows of sediments, drift of eggs and ... – PowerPoint PPT presentation

Number of Views:71
Avg rating:3.0/5.0
Slides: 16
Provided by: energiasus
Category:

less

Transcript and Presenter's Notes

Title: ENERGIA SUSTENTVEL DO BRASIL S'A ESBR


1
ENERGIA SUSTENTÁVEL DO BRASIL S.AESBR
REDUCTION OF ENVIRONMENTAL IMPACTS OF THE AHE
JIRAU NEW PROJECT
May 20, 2008
1
2
ADVANTAGES OF THE AHE JIRAU NEW PROJECT
  • The revised Project with the new location of the
    dam developed by ESBR presents lower
    environmental impacts in relation to the original
    Basic Project for the following reasons
  • Lower excavation volume
  • Maintenance of conditions of flow rates and
    physical / biotic flows during construction
    phase
  • Arrangement of engineering structures in friendly
    conditions as to river biology
  • Better conformity to the conditions provided for
    in the Previous License as to ichthyofauna,
    movement of sediments and revolving of
    mercury-contaminated bottom
  • Favourable conditions of topography of
    alternative axis in relation to the original
    axis
  • Possible anticipation of energy generation in
    view of appropriate distribution in the
    arrangement of the two power houses
  • Hydraulic engineering arrangement with spillway
    in more favourable conditions for maintenance of
    physical / biotic flows of sediments, drift of
    eggs and passage of young fishes.

2
3
ORIGINAL LOCATION OF JIRAU DAM
3
4
NEW PROJECT NEW DAM LOCATION
Reduction of Environmental Impacts
ALTERNATIVE AXIS
Reduction of Excavation Volumes
Costs Reduction
Power Generation Anticipation
The revised Project will have to be approved by
ANEEL and IBAMA
4
5
NEW PROJECT ENGINEERING ARRANGEMENT
5
6
NEW PROJECT REDUCTION OF ENVIRONMENTAL IMPACTS
  • Reduction of excavation volumes
  • Earth 6.266.169 m³
  • Rock 43.636.876 m³
  • Cofferdams 1.353.830 m³
  • Removal of Cofferdams 530.313 m³
  • Such reductions are possible due to the natural
    widening of the river in the new chosen location
  • 19.5 times the volume of the Maracanã Stadium
    outer envelope
  • 537 times the volume of concrete used in the
    construction of Maracanã Stadium
  • 3.5 times the volume of concrete used in the
    construction of ITAIPU

6
7
NEW PROJECT REDUCTION OF ENVIRONMENTAL IMPACTS
  • Reduction of send-off volumes and cofferdams with
    lower movement of earth and rock as well as lower
    need of removal
  • The reduction of excavation and cofferdams
    present environmental advantages in the new axis
    as they consequently reduce the send-off volumes
    and borrow pit areas and aiming to increase the
    area of original forest surrounding the worksite

7
8
NEW PROJECT REDUCTION OF ENVIRONMENTAL IMPACTS
  • Maintenance of the river on its natural bed
    during two dry periods ? Lower impact on the
    ichthyofauna
  • To maintain the Madeira River diverted by the
    two natural river channels near the existing
    river island represents a more favourable
    environmental condition to the physical / biotic
    environment than the need of construction of an
    excavated channel in the original axis according
    to the Basic Project

8
9
ENVIRONMENTAL BASIC PROJECT(PBA)
Programs with shared performance area according
to LP no. 251/2007
  • Flora Conservation Program
  • Fauna Conservation Program
  • Ichthyofauna Conservation Program
  • Public Health/Malaria Program
  • Hydrosedimentologic Monitoring Program

Programs under joint responsibility according to
LP no. 251/2007
  • Support Program to Indigenous Communities
  • Programs related to the Archaeological,
    Prehistorical and Historical Heritage

10
ENVIRONMENTAL BASIC PROJECT(PBA)
  • Environmental Program for Construction PAC
  • Water Table Monitoring Program
  • Seismologic Monitoring Program
  • Climatologic Monitoring Program
  • Hydro-biogeochemical Monitoring Program
  • Mining Rights and Prospecting Activity
    Monitoring Program
  • Paleontological Heritage Preservation Program
  • Limnological Monitoring Program
  • Macrophytes Monitoring Program
  • Flooded Area Deforestation Program
  • Environmental Compensation Program
  • Deforestation and Wildlife Rescue Activities
    Follow-up Program
  • Social Communication and Environmental Education
    Program
  • Affected Population Relocation Program
  • Affected Infrastructure Recovery Program
  • Social Compensation Program
  • Reservoir Master Plan
  • Leisure and Tourism Activities Support Program
  • Clay pits and Campinarana Use Monitoring
    Program (LP)
  • Environmental Compensation Program
  • Considering the degree of impact on the
    Campinarana region (LP)

Programs with exclusive application to the
development of AHE Jirau.
11
IMPLEMENTATION STRATEGY OF JIRAU PBA
Programs regarded as shared ones due to their
nature and scientific condition of implementation
shall be compulsorily unified as required in the
LP. Once identified the overlap of effects in the
areas of the two reservoirs of the Madeira
Complex will be treated as inserted in a common
universe
The relocation of the dam at 9.2 km downstream
the original axis does not change the natural
conditions of the physical / biotic environment
taking into account the scientific need of
sharing the various environmental studies within
the same universe determined by IBAMA in the
licensing process of the Madeira Complex
Due to common studies and integrated dimension of
environmental actions to be developed in both
projects the breakdown of the previous issue of
the worksite installation license and subsequent
installation environmental license covering the
reservoir is circumstantially justified
11
12
ADDITIONAL INVESTMENTS IN THE SOCIAL AREA
Aiming at reducing social impacts on the city of
Porto Velho, ESBR has decided to increase its
investments in the social area and build a new
district in order to relocate the population of
Mutum Paraná.
  • During the construction of Nova Mutum Paraná, we
    will implement
  • Main and sewage treatment system
  • Water distribution system
  • Solid residues gathering and treatment
  • Urban drainage and paved streets
  • Green areas
  • Primary and Secondary schools
  • Health station
  • Leisure and business area

12
13
ADDITIONAL INVESTMENTS IN THE SOCIAL AREA NOVA
MUTUM PARANÁ
  • During the construction of Nova Mutum Paraná, we
    will implement
  • 300 houses for the relocated population
  • 300 houses for technicians and engineers of the
    works ? after the end of works, the houses shall
    be passed on to the public authorities
  • Infrastructure services (water sewage
    garbage) shall be passed on without cost to the
    Municipality of Porto Velho

We will carry out the city's master plan
including a long-term sustainability planning by
means of attracting economic activities and job
creation.
13
14
ECONOMIC ADVANTAGES OF THE NEW PROJECT
  • Advantages
  • A power house with 28 units and the second one
    with 16 units
  • Reduction in the number of cofferdams and
    environmental impacts
  • Anticipation in the concreting of the second
    power house
  • Increase of erection areas
  • Simultaneous erection and commissioning of both
    power houses
  • Power generation anticipation
  • Reduction in the tariff offered to consumer

14
15
NEW PROJECT IMPLEMENTATION SCHEDULE
  • Beginning of civil works April 2009
  • First phase cofferdams beginning May 2009 end
    July 2009
  • Beginning of concreting for the power house and
    spillway January 2010
  • River diverted by lower openings November 2010
  • End of dam construction January 2012
  • Beginning of generation in base-case March 2012
  • Beginning of generation in optimistic case
    December 2011

15
Write a Comment
User Comments (0)
About PowerShow.com