WREZ Technical Committee - PowerPoint PPT Presentation

1 / 62
About This Presentation
Title:

WREZ Technical Committee

Description:

Applicable current incentives (e.g., federal production tax credit) Capital cost ... integrated with other study requests during the TEPPC review process (Feb.- Apr. ... – PowerPoint PPT presentation

Number of Views:31
Avg rating:3.0/5.0
Slides: 63
Provided by: PLE3
Category:

less

Transcript and Presenter's Notes

Title: WREZ Technical Committee


1
WREZ Technical Committee
  • Briefing Webcast Part 1
  • December 15, 2008

2
  • Agenda Review
  • Purpose
  • Brief Technical Committee on information about
    WREZ model and WECC study request to be presented
    at January meeting
  • Answer questions and secure feedback on materials
    to achieve approval in January
  • Approve WREZ model documents for public comment
  • Approve submission of study request to WECC

3
WREZ Technical Committee Meeting
  • WREZ Modeling Tools
  • Black Veatch
  • December 15, 2008

4
WREZ Information Flows
  • WREZ will employ linked tools to deliver data and
    information to users
  • ZITA database of renewable projects
  • Generation Transmission Model will allow users to
    access renewable project information, develop
    portfolios and allow users to identify potential
    transmission development collaborations

E L Data
  • ZITA Data

Generation Transmission Model
5
ZITA Zone Identification Process
All RenewableResources
Preliminary ScreeningCriteria
CandidateStudyAreas
Proposed REZ Identification
Environ- mental and Other Land Exclusions
6
REZ-based Technologies
  • Biomass
  • Geothermal
  • Hydro
  • Solar Thermal
  • Solar PV
  • Wind

7
What are Technology Characteristics?
  • Major distinguishing assumptions that determine
    project economics
  • Cost and performance information derived from
    recent Black Veatch projects and public sources
  • Numbers vetted through recent RETI process and
    feedback from WREZ stakeholders
  • Typical, representative information provided
  • Characteristics can vary widely
  • Project size
  • Project location
  • Labor type
  • Air quality requirements
  • Fuel variations

8
Assumptions Renewable technologies
  • Efficiency (if applicable)
  • Capacity factor
  • Typical size(s)
  • Applicable current incentives (e.g., federal
    production tax credit)
  • Capital cost
  • inclusive of all direct and indirect costs,
    except transmission
  • Operating and maintenance costs
  • Typical fuel costs (if applicable)
  • Calculated levelized cost of energy

9
Proxy Technology Assumptions
  • The WREZ cost model will allow the user to input
    any technology cost / performance assumptions
    they want
  • ZITA needs to provide default assumptions for a
    single proxy technology for each resource
  • Proxy technology generally based on the prevalent
    commercial scale technology employed today
  • Alternate technology futures can still be modeled

10
Biomass Assumptions
  • Combustion-based technology (stoker / fluidized
    bed)

Costs are on a dry ton basis and do not include
transportation costs. Transportation costs will
be assumed to be 0.15/dry ton/mile.
11
Biomass fuel cost assumptions
Costs are on a dry ton basis and do not include
transportation costs. Transportation costs will
be assumed to be 0.15/dry ton/mile.
12
Geothermal Assumptions
  • Conventional binary or flash technology,
    depending on resource

13
Hydroelectric Assumptions
  • Various technologies, site-dependent

14
Hydroelectric Assumptions Notes
  • Canadian hydropower will include incremental
    additions to powered dams, new power stations at
    non-powered dams and any feasible new,
    undeveloped hydropower.
  • Applicable for sites before certain in-service
    dates, and which meet certain environmental
    criteria only.

15
Solar Thermal Assumptions
  • Dry-cooled Parabolic Trough, with no storage
  • Trough with 6 hours of storage also included

16
Solar Photovoltaic Assumptions
  • Single-Axis Tracking Crystalline

Note all values are on a net ac basis
17
Wind Assumptions
  • Conventional, horizontal-axis, 3-blade machine,
    80m hub-height

18
Zone Identification Process
All RenewableResources
Preliminary ScreeningCriteria
CandidateStudyAreas
Proposed REZ Identification
Environ- mental and Other Land Exclusions
Technology Assumptions
Resource Characteri-zation
Cost Assessment
REZ Cost Supply Curves
Generation Transmission Model
Zone Characterization Process
19
Information Provided by ZITA to GTMG
  • REZ Information
  • REZ definition and a list of all resources
    included in the REZ
  • Precise location of transmission interconnection
    point for the REZ
  • Central collector point for all resources within
    the REZ
  • Centroid or other point

20
Information Provided by ZITA to GTMG
  • Resource Information for Each Resource in Each
    Zone
  • Resource type and technology
  • Location
  • Performance Information
  • Capacity Factor (annual)
  • Temporal Profile (12x24)
  • Cost of generation (/MWh)

21
Generation Transmission Model
  • Allow users to identify REZ projects throughout
    Western North America and provide cost and value
    of energy of these resources to their load area
  • Provide transmission options to deliver the REZ
    energy to load centers
  • Excel based tool providing flexibility on
    operation
  • Allow users to modify assumptions to meet
    individual requirements

22
GenerationTransmission Model Data Flow
Selected Resource Portfolio -Supply
Curve -Resource Summary -Transmission Summary
User Defined Resources
Resource characteristics -Type -Energy
Profile -Capacity -Cost
Select Load Center
Select REZ Resources (User to click on map)
Transmission Mode (P2P or Multi-REZ)
Transmission -Utilization -Capacity -Cost
Supply Curve of Resources User can view details
production profile of area/resource
Delivered LCOE (/MWh)
Value of selected resource(s) to other areas
of interest
Line Attributes
Line Size
23
Generation Transmission Model Attributes
  • Allow users to see broad range of resource
    options
  • Identify transmission alternatives
  • Point-to-point
  • Multi-REZ
  • Flexibility
  • Modify starting point values
  • Add additional resources
  • Add environmental considerations as they become
    available

24
(No Transcript)
25
(No Transcript)
26
(No Transcript)
27
(No Transcript)
28
(No Transcript)
29
(No Transcript)
30
(No Transcript)
31
(No Transcript)
32
Thank You!

Ryan Pletka PletkaRJ_at_bv.com Tel 925-949-5929
Kevin Joyce JoyceKP_at_bv.com Tel 913-458-8768
Tim Mason MasonT_at_bv.com Tel 925-949-5943
33
Generation and Transmission Modeling Work Group
Update
  • Co-Chairs
  • Jerry Vaninetti, Trans-Elect
  • Paul Smith, APS
  • Technical Committee Webinar
  • December 15, 2008

34
GTMWG Sub Groups
  • Transmission Characteristics Sub-Group
  • Transmission Segments Sub-Group
  • Model Development Sub-Group

35
Transmission Characteristics Sub-Group
  • Chair Bill Pascoe
  • Charge
  • provide information regarding the cost and
    operating characteristics of transmission lines
    to be included in the WREZ model. 
  • Input assumptions to WREZ model
  • Transmission capacities
  • Transmission capital costs
  • Right of way costs
  • Substations
  • Transmission loss assumptions

36
(No Transcript)
37
(No Transcript)
38
Transmission Segments Sub-Group
  • Chair Andy Leoni, Tri-State
  • Charge
  • provide information on transmission system
    distance and routing inputs to be used in the
    WREZ model. 
  • Input assumptions
  • Identify existing bulk transmission paths for
    modeling purposes
  • Identify load zones
  • Derive distances between segments

39
(No Transcript)
40
WREZ Study Request to WECC
  • Doug Larson and Thomas Carr, WIEB
  • Technical Committee Webinar
  • December 15, 2008

40
41
Outline
  • Purpose Advance the development of conceptual
    transmission plans from REZs
  • Schedule
  • Background WECCs TEPPC Study Requests and
    Transmission Planning
  • Proposal WREZ study request to WECC/TEPPC
  • Staff proposal
  • Comments and issues received
  • Discussion

41
42
Purpose WREZ Conceptual Transmission Plans
  • WREZ Phase 2
  • Through existing Western Electricity
    Coordinating Council and subregional transmission
    planning groups, develop conceptual transmission
    plans to deliver energy from the highest ranking
    REZs to identified load centers.
  • WREZ Work Plan, p. 5

42
43
Purpose cont.
  • What transmission is needed to deliver power from
    REZs to load centers?
  • WREZ project seeks to tap the expertise of
    existing transmission planning processes in the
    West to develop conceptual transmission plans
  • WECCs Transmission Expansion Planning Policy
    Committee (TEPPC) does WECC-wide planning
  • Subregional Planning Groups perform planning in
    subregions within WECC.
  • e.g. NTTG, ColumbiaGrid, SWAT, CCPG

43
44
Schedule
  • Pre Dec 15 - Staff ideas and feedback
  • Dec 15 Tech Committee webinar
  • Jan 1-9 Revised proposed request
  • Jan 13-14 Tech Committee recommendation
  • Jan 23 Steering Committee action
  • Jan 31 Submission to WECC

44
45
Background WECCs TEPPC Study Requests and
Transmission Planning
  • WECCs TEPPC solicits stakeholder requests for
    modeling regional transmission scenarios/projects.
  • TEPPC study requests need to be submitted by Jan.
    31 to be part of the study cycle for 2009.
  • Details of the WREZ study request can be refined
    and integrated with other study requests during
    the TEPPC review process (Feb.- Apr.)

45
46
46
47
WECC Criteria
  • (a) What portion of the interconnected system
    will be considered by the study?
  • (b) Does the request raise fundamental design
    issues of interest to multiple parties?
  • (c) Does the request raise policy issues of
    national, regional or state interest for
    example, access to renewable power, and location
    of both conventional and renewable resources?
  • (d) Can the objectives of the study be met by
    other studies by clustering or combination?
  • (e) Will the study provide information of broad
    value to customers, regulators, transmission
    providers, etc.?

47
48
WECC Criteria cont.
  • (f) Can similar requests for studies or
    scenarios be represented generically if the
    projects are generally electrically equivalent?
  • (g) Can requests be aggregated into energy or
    load aggregation zones with generic transmission
    expansion between?
  • (f) Does the study request require the use of
    production cost simulation or can it be better
    addressed through technical studies such as power
    flow and stability analysis?
  • BOTTOM LINE WREZ request fits well with WECC
    criteria

48
49
Example 2008 WIRAB Low-Carbon Study Request
  • Three part request
  • High level of renewables by 2017
  • 15 renewables penetration per NERC LTRA
  • Energy efficiency gains consistent with WGA goal
    of 20 improvement by 2020
  • Details worked out in June-July
  • Carbon adder to attain WCI goal of reducing CO2
    15 by 2020 relative to 2005 levels.
  • CO2 adders of 60, 40 and 20 per ton

49
50
WREZ contribution to WECC
  • Future transmission needs critically dependent
    upon future generation
  • Transmission planning by WECC (and SSG-WI before)
    makes assumptions about future generation
  • Weak link of past analyses
  • WREZ project provides WECC unique opportunity to
    identify future generation areas based on best
    REZ zones
  • WREZ model helps LSEs and regulators tool to
    identify the delivered cost of energy from REZ
    zones

50
51
Other Studies Underway
  • Western Wind and Solar Integration Study by
    NREL/WestConnect
  • Focus on operational impacts
  • Renewable penetration 30 wind and 5 solar for
    WestConnect footprint
  • Western Climate Initiative
  • Regional cap and trade modeled to attain 15 GHG
    reductions among members
  • Economic analysis shows power sector GHG
    reductions 25 to 40 depending upon structure
    and complementary policies

51
52
Proposal WREZ study requests to WECC
  • Outline Staff draft proposal
  • Request 1 LSE-specified resource preferences
  • A Reference Case
  • B Near-term sensitivity cases (2018)
  • C Long-term sensitivity cases (2028)
  • Request 2 Western transmission superhighway
    network

52
53
Draft study request
  • Request 1 LSE preferences
  • A. Reference Case
  • LSE resource planners use WREZ model (or other
    tools) to identify their preferred REZs and
    identify their MWs needed for 2018.
  • LSE resource planners also identify amount of
    local renewable generation.
  • If some LSEs do not provide this information,
    WREZ project must provide the missing data.

53
54
Draft study request
  • Request 1 LSE-specified preferences
  • . . .
  • B. Near-term sensitivity cases (2018)
  • 1. Maximum local generation preference
  • LSEs develop renewable resources within own
    state/province
  • 2. Maximum REZ generation preference
  • All generation based on the preferred REZs
    identified by the WREZ model
  • gt Compare the cost differential between local
    renewables (small transmission) and regional
    renewables (big transmission)

54
55
Draft study request
  • Request 1 LSE-specified preferences
  • . . .
  • C. Long-term sensitivity cases (2028). Assumes
    renewable penetration level of 33.
  • 1. Current technology case
  • Assume default generation costs values
  • 1/3 local renewables and 2/3 REZ renewables
  • 2. Alternative renewable technology cost case
  • Assume technology changes that lower the cost of
    different renewables (PV, CSP, wind, geothermal)
    by certain percentage
  • Evaluate the transmission implications of
    different significant technological changes,
  • e.g. PV innovations make most generation local
    and diminish need for transmission

55
56
Draft study request
  • Request 2 Western transmission superhighway
    network.
  • Assume a transmission superhighway overlay that
    reflect the general location of proposed mega
    transmission projects.
  • A. Reference Case
  • Assumes current generation costs. 1/3 local
    renewables and 2/3 REZ renewables.
  • B. Sensitivity case
  • Assumes cost reductions of renewable
    technologies, e.g. PV, CSP, wind, geo.

56
57
Comments Issues
  • Concern that LSE planners will be reluctant to
    provide responses on their renewable energy
    preferences. Suggest that WREZ project provide
    LSE planners with generation plan and seek
    feedback.

57
58
Comments Issues
  • Should WREZ propose a higher renewable
    penetration scenario for near term analysis such
    as the 30-35 range in NRELs Western Wind and
    Solar Integration Study?
  • Do we need a low growth (energy
    efficiency/conservation) scenario?

58
59
Comments Issues
  • New laws likely in the future that the WREZ
    scenarios may want to explore
  • Higher RPS levels or national RPS with export
    opportunities for the West
  • Carbon constraints, more likely under new U.S.
    administration
  • Natural gas sensitivity cases.
  • Higher renewable penetration could push gas
    prices higher or lower in long term.

59
60
Schedule
  • Pre Dec 15 - Staff ideas and feedback
  • Dec 15 Tech Committee webinar
  • Comments/suggestions
  • Jan 1-9 Revised proposed request
  • Jan 13-14 Tech Committee recommendation
  • Jan 23 Steering Committee action
  • Jan 31 Submission to WECC

60
61
Questions, Comments, Suggestions?
61
62
Technical Committee Briefing Webcast Part 2
  • Thursday, Dec 18, 100 300pm MST
  • Agenda
  • ZITA proposal to refine CSAs into Qualified
    Resource Areas
  • EL initial exclusion and avoidance areas,
    criteria for categorizing land, and wildlife data
    request
  • Public comment package process
  • Draft Phase 1 report outline
Write a Comment
User Comments (0)
About PowerShow.com