Title: WREZ Technical Committee
1WREZ Technical Committee
- Briefing Webcast Part 1
- December 15, 2008
2- Agenda Review
- Purpose
- Brief Technical Committee on information about
WREZ model and WECC study request to be presented
at January meeting - Answer questions and secure feedback on materials
to achieve approval in January - Approve WREZ model documents for public comment
- Approve submission of study request to WECC
3WREZ Technical Committee Meeting
- WREZ Modeling Tools
- Black Veatch
- December 15, 2008
4WREZ Information Flows
- WREZ will employ linked tools to deliver data and
information to users - ZITA database of renewable projects
- Generation Transmission Model will allow users to
access renewable project information, develop
portfolios and allow users to identify potential
transmission development collaborations
E L Data
Generation Transmission Model
5ZITA Zone Identification Process
All RenewableResources
Preliminary ScreeningCriteria
CandidateStudyAreas
Proposed REZ Identification
Environ- mental and Other Land Exclusions
6REZ-based Technologies
- Biomass
- Geothermal
- Hydro
- Solar Thermal
- Solar PV
- Wind
7What are Technology Characteristics?
- Major distinguishing assumptions that determine
project economics - Cost and performance information derived from
recent Black Veatch projects and public sources - Numbers vetted through recent RETI process and
feedback from WREZ stakeholders - Typical, representative information provided
- Characteristics can vary widely
- Project size
- Project location
- Labor type
- Air quality requirements
- Fuel variations
8Assumptions Renewable technologies
- Efficiency (if applicable)
- Capacity factor
- Typical size(s)
- Applicable current incentives (e.g., federal
production tax credit) - Capital cost
- inclusive of all direct and indirect costs,
except transmission - Operating and maintenance costs
- Typical fuel costs (if applicable)
- Calculated levelized cost of energy
9Proxy Technology Assumptions
- The WREZ cost model will allow the user to input
any technology cost / performance assumptions
they want - ZITA needs to provide default assumptions for a
single proxy technology for each resource - Proxy technology generally based on the prevalent
commercial scale technology employed today - Alternate technology futures can still be modeled
10Biomass Assumptions
- Combustion-based technology (stoker / fluidized
bed)
Costs are on a dry ton basis and do not include
transportation costs. Transportation costs will
be assumed to be 0.15/dry ton/mile.
11Biomass fuel cost assumptions
Costs are on a dry ton basis and do not include
transportation costs. Transportation costs will
be assumed to be 0.15/dry ton/mile.
12Geothermal Assumptions
- Conventional binary or flash technology,
depending on resource
13Hydroelectric Assumptions
- Various technologies, site-dependent
14Hydroelectric Assumptions Notes
- Canadian hydropower will include incremental
additions to powered dams, new power stations at
non-powered dams and any feasible new,
undeveloped hydropower. - Applicable for sites before certain in-service
dates, and which meet certain environmental
criteria only.
15Solar Thermal Assumptions
- Dry-cooled Parabolic Trough, with no storage
- Trough with 6 hours of storage also included
16Solar Photovoltaic Assumptions
- Single-Axis Tracking Crystalline
Note all values are on a net ac basis
17Wind Assumptions
- Conventional, horizontal-axis, 3-blade machine,
80m hub-height
18Zone Identification Process
All RenewableResources
Preliminary ScreeningCriteria
CandidateStudyAreas
Proposed REZ Identification
Environ- mental and Other Land Exclusions
Technology Assumptions
Resource Characteri-zation
Cost Assessment
REZ Cost Supply Curves
Generation Transmission Model
Zone Characterization Process
19Information Provided by ZITA to GTMG
- REZ Information
- REZ definition and a list of all resources
included in the REZ - Precise location of transmission interconnection
point for the REZ - Central collector point for all resources within
the REZ - Centroid or other point
20Information Provided by ZITA to GTMG
- Resource Information for Each Resource in Each
Zone - Resource type and technology
- Location
- Performance Information
- Capacity Factor (annual)
- Temporal Profile (12x24)
- Cost of generation (/MWh)
21Generation Transmission Model
- Allow users to identify REZ projects throughout
Western North America and provide cost and value
of energy of these resources to their load area - Provide transmission options to deliver the REZ
energy to load centers - Excel based tool providing flexibility on
operation - Allow users to modify assumptions to meet
individual requirements -
22GenerationTransmission Model Data Flow
Selected Resource Portfolio -Supply
Curve -Resource Summary -Transmission Summary
User Defined Resources
Resource characteristics -Type -Energy
Profile -Capacity -Cost
Select Load Center
Select REZ Resources (User to click on map)
Transmission Mode (P2P or Multi-REZ)
Transmission -Utilization -Capacity -Cost
Supply Curve of Resources User can view details
production profile of area/resource
Delivered LCOE (/MWh)
Value of selected resource(s) to other areas
of interest
Line Attributes
Line Size
23Generation Transmission Model Attributes
- Allow users to see broad range of resource
options - Identify transmission alternatives
- Point-to-point
- Multi-REZ
- Flexibility
- Modify starting point values
- Add additional resources
- Add environmental considerations as they become
available
24(No Transcript)
25(No Transcript)
26(No Transcript)
27(No Transcript)
28(No Transcript)
29(No Transcript)
30(No Transcript)
31(No Transcript)
32Thank You!
Ryan Pletka PletkaRJ_at_bv.com Tel 925-949-5929
Kevin Joyce JoyceKP_at_bv.com Tel 913-458-8768
Tim Mason MasonT_at_bv.com Tel 925-949-5943
33Generation and Transmission Modeling Work Group
Update
- Co-Chairs
- Jerry Vaninetti, Trans-Elect
- Paul Smith, APS
- Technical Committee Webinar
- December 15, 2008
34GTMWG Sub Groups
-
- Transmission Characteristics Sub-Group
- Transmission Segments Sub-Group
- Model Development Sub-Group
-
35Transmission Characteristics Sub-Group
- Chair Bill Pascoe
- Charge
- provide information regarding the cost and
operating characteristics of transmission lines
to be included in the WREZ model. - Input assumptions to WREZ model
- Transmission capacities
- Transmission capital costs
- Right of way costs
- Substations
- Transmission loss assumptions
36(No Transcript)
37(No Transcript)
38Transmission Segments Sub-Group
- Chair Andy Leoni, Tri-State
- Charge
- provide information on transmission system
distance and routing inputs to be used in the
WREZ model. - Input assumptions
- Identify existing bulk transmission paths for
modeling purposes - Identify load zones
- Derive distances between segments
39(No Transcript)
40WREZ Study Request to WECC
- Doug Larson and Thomas Carr, WIEB
- Technical Committee Webinar
- December 15, 2008
40
41Outline
-
- Purpose Advance the development of conceptual
transmission plans from REZs - Schedule
- Background WECCs TEPPC Study Requests and
Transmission Planning - Proposal WREZ study request to WECC/TEPPC
- Staff proposal
- Comments and issues received
- Discussion
-
41
42Purpose WREZ Conceptual Transmission Plans
- WREZ Phase 2
- Through existing Western Electricity
Coordinating Council and subregional transmission
planning groups, develop conceptual transmission
plans to deliver energy from the highest ranking
REZs to identified load centers. - WREZ Work Plan, p. 5
42
43Purpose cont.
- What transmission is needed to deliver power from
REZs to load centers? - WREZ project seeks to tap the expertise of
existing transmission planning processes in the
West to develop conceptual transmission plans - WECCs Transmission Expansion Planning Policy
Committee (TEPPC) does WECC-wide planning - Subregional Planning Groups perform planning in
subregions within WECC. - e.g. NTTG, ColumbiaGrid, SWAT, CCPG
43
44Schedule
- Pre Dec 15 - Staff ideas and feedback
- Dec 15 Tech Committee webinar
- Jan 1-9 Revised proposed request
- Jan 13-14 Tech Committee recommendation
- Jan 23 Steering Committee action
- Jan 31 Submission to WECC
44
45Background WECCs TEPPC Study Requests and
Transmission Planning
- WECCs TEPPC solicits stakeholder requests for
modeling regional transmission scenarios/projects.
- TEPPC study requests need to be submitted by Jan.
31 to be part of the study cycle for 2009. - Details of the WREZ study request can be refined
and integrated with other study requests during
the TEPPC review process (Feb.- Apr.)
45
4646
47WECC Criteria
- (a) What portion of the interconnected system
will be considered by the study? - (b) Does the request raise fundamental design
issues of interest to multiple parties? - (c) Does the request raise policy issues of
national, regional or state interest for
example, access to renewable power, and location
of both conventional and renewable resources? - (d) Can the objectives of the study be met by
other studies by clustering or combination? - (e) Will the study provide information of broad
value to customers, regulators, transmission
providers, etc.?
47
48WECC Criteria cont.
- (f) Can similar requests for studies or
scenarios be represented generically if the
projects are generally electrically equivalent? - (g) Can requests be aggregated into energy or
load aggregation zones with generic transmission
expansion between? - (f) Does the study request require the use of
production cost simulation or can it be better
addressed through technical studies such as power
flow and stability analysis? - BOTTOM LINE WREZ request fits well with WECC
criteria
48
49Example 2008 WIRAB Low-Carbon Study Request
- Three part request
- High level of renewables by 2017
- 15 renewables penetration per NERC LTRA
- Energy efficiency gains consistent with WGA goal
of 20 improvement by 2020 - Details worked out in June-July
- Carbon adder to attain WCI goal of reducing CO2
15 by 2020 relative to 2005 levels. - CO2 adders of 60, 40 and 20 per ton
49
50WREZ contribution to WECC
- Future transmission needs critically dependent
upon future generation - Transmission planning by WECC (and SSG-WI before)
makes assumptions about future generation - Weak link of past analyses
- WREZ project provides WECC unique opportunity to
identify future generation areas based on best
REZ zones - WREZ model helps LSEs and regulators tool to
identify the delivered cost of energy from REZ
zones -
50
51Other Studies Underway
- Western Wind and Solar Integration Study by
NREL/WestConnect - Focus on operational impacts
- Renewable penetration 30 wind and 5 solar for
WestConnect footprint - Western Climate Initiative
- Regional cap and trade modeled to attain 15 GHG
reductions among members - Economic analysis shows power sector GHG
reductions 25 to 40 depending upon structure
and complementary policies
51
52Proposal WREZ study requests to WECC
- Outline Staff draft proposal
- Request 1 LSE-specified resource preferences
- A Reference Case
- B Near-term sensitivity cases (2018)
- C Long-term sensitivity cases (2028)
- Request 2 Western transmission superhighway
network
52
53Draft study request
- Request 1 LSE preferences
- A. Reference Case
- LSE resource planners use WREZ model (or other
tools) to identify their preferred REZs and
identify their MWs needed for 2018. - LSE resource planners also identify amount of
local renewable generation. - If some LSEs do not provide this information,
WREZ project must provide the missing data.
53
54Draft study request
- Request 1 LSE-specified preferences
- . . .
- B. Near-term sensitivity cases (2018)
- 1. Maximum local generation preference
- LSEs develop renewable resources within own
state/province - 2. Maximum REZ generation preference
- All generation based on the preferred REZs
identified by the WREZ model - gt Compare the cost differential between local
renewables (small transmission) and regional
renewables (big transmission)
54
55Draft study request
- Request 1 LSE-specified preferences
- . . .
- C. Long-term sensitivity cases (2028). Assumes
renewable penetration level of 33. - 1. Current technology case
- Assume default generation costs values
- 1/3 local renewables and 2/3 REZ renewables
- 2. Alternative renewable technology cost case
- Assume technology changes that lower the cost of
different renewables (PV, CSP, wind, geothermal)
by certain percentage - Evaluate the transmission implications of
different significant technological changes, - e.g. PV innovations make most generation local
and diminish need for transmission
55
56Draft study request
- Request 2 Western transmission superhighway
network. - Assume a transmission superhighway overlay that
reflect the general location of proposed mega
transmission projects. - A. Reference Case
- Assumes current generation costs. 1/3 local
renewables and 2/3 REZ renewables. - B. Sensitivity case
- Assumes cost reductions of renewable
technologies, e.g. PV, CSP, wind, geo.
56
57Comments Issues
- Concern that LSE planners will be reluctant to
provide responses on their renewable energy
preferences. Suggest that WREZ project provide
LSE planners with generation plan and seek
feedback.
57
58Comments Issues
- Should WREZ propose a higher renewable
penetration scenario for near term analysis such
as the 30-35 range in NRELs Western Wind and
Solar Integration Study? - Do we need a low growth (energy
efficiency/conservation) scenario?
58
59Comments Issues
- New laws likely in the future that the WREZ
scenarios may want to explore - Higher RPS levels or national RPS with export
opportunities for the West - Carbon constraints, more likely under new U.S.
administration - Natural gas sensitivity cases.
- Higher renewable penetration could push gas
prices higher or lower in long term.
59
60Schedule
- Pre Dec 15 - Staff ideas and feedback
- Dec 15 Tech Committee webinar
- Comments/suggestions
- Jan 1-9 Revised proposed request
- Jan 13-14 Tech Committee recommendation
- Jan 23 Steering Committee action
- Jan 31 Submission to WECC
60
61Questions, Comments, Suggestions?
61
62Technical Committee Briefing Webcast Part 2
- Thursday, Dec 18, 100 300pm MST
- Agenda
- ZITA proposal to refine CSAs into Qualified
Resource Areas - EL initial exclusion and avoidance areas,
criteria for categorizing land, and wildlife data
request - Public comment package process
- Draft Phase 1 report outline