Title: HP3000 Lift and Shift Project
1HP3000 Lift and Shift Project
2What is changing?
3What is the HP3000 LnS Project Timeline
4Current Project Status
- Status Highlights
- The Schedule for Project Technical Work is at 8
complete. - First Speedware deliverable on schedule for end
of December. - 1st QA Report published by Sterling Associates.
- All Project Hardware and Software now purchased.
- Dev/Test Environment installed and functional.
- Detail Test Planning by SBCTC ITD continues.
- Additional Unit Test Cases being developed by
SBCTC ITD staff. - Weekly Status Meetings held with Speedware
Project Management. - Production system being installed at DIS Data
center in Olympia. - Project Technical Timeline is 18 months from
September 21!
5What we will be doing within the project?
- Speedware, Inc. (Contractor) will be
- providing replacement Software products to
operate on the new HP-UX platform - migrating Student Management System, Financial
Management System, and Payroll/Personnel System
to operate with the new HP-UX platform and
software - migrating DataExpress reporting to use an
upgraded version of the software to minimize
end-user training impact - mentoring SBCTC Information Technology Division
staff in working with and supporting the new
HP-UX hardware/software platform (knowledge
transfer) - SBCTC ITD will be
- - providing overall Project Management
- establishing a new hosted production environment
to consolidate all 34 colleges using the new
HP-UX platform and software - supporting the contractor during technical
migration activities - performing functional and system testing of the
migrated Systems - converting remaining DataExpress reports for the
colleges - learning how to technically support the new
technologies - deploying colleges once migration and testing
work is completed
6What will be different in the systems after
project is completed?
- End-user Impact
- Project is not changing application system
functionality - Project is not changing screens and reports,
databases, forms - Project is not changing integration with
external systems - College IT Impact
- Project uses next generation computer
technologies to replace 30 year old products - Project consolidates 34 HP based systems to
operate in a single hosted environment at the
State of Washington primary data center - Technical and user support for the production
systems will be provided by SBCTC ITD staff
7Will there be a need for user training for the
new systems, DataExpress replacement, etc?
User Training requirements are expected to be
very limited with this project since the Systems
are not changing. There may be some minor
technical changes in how the replacement for DX
operates that requires instructional updates to
users. We will know more once the first migrated
DX reports are available from the
Contractor. The contractor and SBCTC ITD staff
will be converting DX reports however, users
will be asked to run these reports to make sure
the conversion was successful.
8What you should know about the code freeze?
- Why is a Code Freeze necessary?
- - The Project requires control of any/all changes
to the 3,000,000 plus lines of Application code
(a mix of Cobol and other coding approaches) - - The Contractor bid price for the project was
based upon the line of migrated code and
limitations on any changes to the codebase
during the project - Any changes to the codebase will be costly to
the State, will have major impact on the vendor
and SBCTC staff testing the migrated systems - Code changes can cause major delay to the
project completion - During the Code Freeze only Federally and State
mandated changes or critical bug fixes to the
Systems will be considered and these will tightly
controlled